Construction Planning and Management Grader is used mainly for Shaping and trimming Finishing, shaping and trimming Trimming and finishing Finishing and shaping Shaping and trimming Finishing, shaping and trimming Trimming and finishing Finishing and shaping ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The constraints in case of resource smoothening operation would be Project duration time None of these Resources Both resources and project duration time Project duration time None of these Resources Both resources and project duration time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The first stage of a construction, is Preparation of estimate Initiation of proposal Preparation of tender Survey of the site Preparation of estimate Initiation of proposal Preparation of tender Survey of the site ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The Overall in-charge of an organization at the site responsible for the execution of the works, is Assistant Engineer Junior Engineer Engineer Executive Engineer Assistant Engineer Junior Engineer Engineer Executive Engineer ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following activities in a building construction:1. Concreting of roof slabs2. Brick-jelly lime concrete terracing3. Erection of form work for slab4. Construction of parapet wall in terraceThe correct sequence of these activities is 1, 3, 2, 4 3, 1, 4, 2 1, 3, 4, 2 3, 1, 2, 4 1, 3, 2, 4 3, 1, 4, 2 1, 3, 4, 2 3, 1, 2, 4 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Assertion (A): Activity 57 is critical.Reason (R): Earliest finish time and latest finish time for events 57 are same Both A and R is incorrect Both A and R is correct R is correct but A is not correct A is correct but R is not correct Both A and R is incorrect Both A and R is correct R is correct but A is not correct A is correct but R is not correct ANSWER DOWNLOAD EXAMIANS APP