Construction Planning and Management Crash project duration is obtained by summing the Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities Crash durations for all activities Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities Normal durations for all the activities Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities Crash durations for all activities Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities Normal durations for all the activities ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements: In the critical path method of construction planning, Free Float can be. 1. Greater than Total Float. 2. Greater than Independent Float 3. Equal to Total Float. 4. Less than Independent Float 1 and 2 are correct 1 and 4 are correct 1 and 4 are correct 2 and 3 are correct 1 and 2 are correct 1 and 4 are correct 1 and 4 are correct 2 and 3 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively 4 and 5/6 5 and 25/36 3.5 and 5/6 3.5 and 25/36 4 and 5/6 5 and 25/36 3.5 and 5/6 3.5 and 25/36 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In India, are prefabricated components costlier than those of traditional cast-in-situ items that the prefabricated components replace? No, because of repetitive manufacture of a number of elements Yes, because of heavier overheads and handling cost Yes, because of the very high order of quality control for the factory made components No, because of savings in site labour No, because of repetitive manufacture of a number of elements Yes, because of heavier overheads and handling cost Yes, because of the very high order of quality control for the factory made components No, because of savings in site labour ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time by which a particular activity can be delayed without affecting the preceding and succeeding activities is known as Independent float Free float Interfering float Total float Independent float Free float Interfering float Total float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The most suitable type of equipment for compaction of cohesive soils is Sheep foot rollers Vibratory rollers Smooth-wheeled rollers Tampers Sheep foot rollers Vibratory rollers Smooth-wheeled rollers Tampers ANSWER DOWNLOAD EXAMIANS APP