Construction Planning and Management Crash project duration is obtained by summing the Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities Crash durations for all activities Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities Normal durations for all the activities Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities Crash durations for all activities Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities Normal durations for all the activities ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management During the construction period, price variation clause in contracts caters to Rate of inflation Increase in rates of only important materials Variation in cost in materials element, labour element and petrol-oil-lubricant element Variation in total cost of the project on an ad hoc basis Rate of inflation Increase in rates of only important materials Variation in cost in materials element, labour element and petrol-oil-lubricant element Variation in total cost of the project on an ad hoc basis ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The main principle of an organization, is Delegation of authority All listed here Unity of command Effective control at all levels Delegation of authority All listed here Unity of command Effective control at all levels ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time which results in the least possible construction cost of an activity, is known as Normal time Standard time Crash time Slow time Normal time Standard time Crash time Slow time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following features/factors:1. Projects are of the non-repetitive type2. Time required need not be known3. Time required is known precisely4. Events have been established for planning5. Emphasis is given to activities of projectPERT is preferred for planning because of 1, 2 and 4 3, 4 and 5 1, 2 and 5 1, 3 and 4 1, 2 and 4 3, 4 and 5 1, 2 and 5 1, 3 and 4 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which one of the following is not an excavating and moving type of equipment? Bulldozer Clam shell Dump truck Scraper Bulldozer Clam shell Dump truck Scraper ANSWER DOWNLOAD EXAMIANS APP