Construction Planning and Management Crash project duration is obtained by summing the Crash durations for all activities Normal durations for all the activities Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities Crash durations for all activities Normal durations for all the activities Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Railway projects are treated as Industrial construction Heavy construction None of these Light construction Industrial construction Heavy construction None of these Light construction ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Time and progress chart of a construction, is also known as Gantt chart All listed here Modified Mile stone chart Bar chart Gantt chart All listed here Modified Mile stone chart Bar chart ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time corresponding to minimum total project cost is Normal time Optimistic time Crash time Between normal time and crash time Normal time Optimistic time Crash time Between normal time and crash time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Construction team means An engineer An architect An owner All listed here An engineer An architect An owner All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In time-cost optimization of a project, crashing is done. On all the activities On original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope On all the activities lying on the critical path Only on activities lying on the original critical path and having flatter cost slopes On all the activities On original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope On all the activities lying on the critical path Only on activities lying on the original critical path and having flatter cost slopes ANSWER DOWNLOAD EXAMIANS APP