Construction Planning and Management
Crash project duration is obtained by summing the

Normal durations for all the activities
Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities
Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities
Crash durations for all activities

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Output of a bulldozer is (i) Increased if drawbar HP of the tractor is increased for a given hauling distance (ii) Decreased if drawbar HP of the tractor is increased for a given hauling distance (iii) Increased if the hauling distance is increased for a given drawbar HP of the tractor (iv) Decreased if the hauling distance is increased for a given drawbar HP of the tractor

(i) and (iv) are correct
(i) and (iii) are correct
(ii) and (iv) are correct
(ii) and (iii) are correct

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Sinking fund is

A part of the money kept in reserve for providing additional structures and structural modifications
The fund for rebuilding a structure when its economic life is over
Raised to meet maintenance costs
The total sum to be paid to the municipal authorities by the tenants

ANSWER DOWNLOAD EXAMIANS APP