Construction Planning and Management Crash project duration is obtained by summing the Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities Normal durations for all the activities Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities Crash durations for all activities Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities Normal durations for all the activities Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities Crash durations for all activities ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is (a + 4m + b)/6 (a + m + b)/6 (a + 2m + b)/6 (a + 5m + b)/6 (a + 4m + b)/6 (a + m + b)/6 (a + 2m + b)/6 (a + 5m + b)/6 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The area under the Beta distribution curve is divided into two equal parts by Pessimistic time Optimistic time Most likely time Expected time Pessimistic time Optimistic time Most likely time Expected time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A tractor shovel has a purchase price of Rs. 4.7 lacs and could save the organization an amount of rupees one lac per year on operating costs. The salvage value after the amortization period is 10% of the purchase price. The capital recovery period will be 3.7 years 5 years 7.87 years 4.23 years 3.7 years 5 years 7.87 years 4.23 years ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management While filling the tender for any work, the contractor considers All listed here Availability of construction materials Site survey Availability of labour All listed here Availability of construction materials Site survey Availability of labour ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Free float is mainly used to Establish priorities Identify the activities, which can be delayed without affecting the total float of succeeding activity Identify the activities which can be delayed without affecting the total float of preceding activity Identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities Establish priorities Identify the activities, which can be delayed without affecting the total float of succeeding activity Identify the activities which can be delayed without affecting the total float of preceding activity Identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities ANSWER DOWNLOAD EXAMIANS APP