Construction Planning and Management Crash project duration is obtained by summing the Crash durations for all activities Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities Normal durations for all the activities Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities Crash durations for all activities Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities Normal durations for all the activities Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The direct cost of a project with respect to normal time is Infinite Maximum Zero Minimum Infinite Maximum Zero Minimum ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following activities in a building construction: 1. Concreting of roof slabs 2. Brick-jelly lime concrete terracing 3. Erection of form work for slab 4. Construction of parapet wall in terrace The correct sequence of these activities is 1, 3, 4, 2 3, 1, 4, 2 1, 3, 2, 4 3, 1, 2, 4 1, 3, 4, 2 3, 1, 4, 2 1, 3, 2, 4 3, 1, 2, 4 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management What estimate would you give for the variance in above problem ? 54 36 9 81 54 36 9 81 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Economic saving of time results by crashing Cheapest critical activity Cheapest noncritical activity Costliest critical activity Costliest noncritical activity Cheapest critical activity Cheapest noncritical activity Costliest critical activity Costliest noncritical activity ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Assertion (A): Activity 57 is critical.Reason (R): Earliest finish time and latest finish time for events 57 are same R is correct but A is not correct Both A and R is incorrect Both A and R is correct A is correct but R is not correct R is correct but A is not correct Both A and R is incorrect Both A and R is correct A is correct but R is not correct ANSWER DOWNLOAD EXAMIANS APP