Construction Planning and Management
Crash project duration is obtained by summing the

Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities
Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities
Crash durations for all activities
Normal durations for all the activities

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Whenever an activity has zero total float, then

Free float and independent float both must be zero
Free float and independent float both need not be zero
Independent float must be zero but free float need not be zero
Free float of the activity must be zero but independent float need not be zero

ANSWER DOWNLOAD EXAMIANS APP