Construction Planning and Management Crash project duration is obtained by summing the Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities Crash durations for all activities Normal durations for all the activities Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities Crash durations for all activities Normal durations for all the activities ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For which of the following materials, the output of power shovels for a fixed shovel size will be maximum Well blasted rock Good common earth Moist loam Wet sticky clay Well blasted rock Good common earth Moist loam Wet sticky clay ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The critical activity has Minimum float None of these Maximum float Zero float Minimum float None of these Maximum float Zero float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In the given figure, the network of a project represents None of these Activity of excavation which takes 8 units of time Activity of an excavation which starts at event No. 1 and ends at even No. 2 Activity of an excavation of a footing None of these Activity of excavation which takes 8 units of time Activity of an excavation which starts at event No. 1 and ends at even No. 2 Activity of an excavation of a footing ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The original cost of an equipment is Rs.10,000. Its salvage value at the end of its total useful life of five years is Rs. 1,000. Its book value at the end of two years of its useful life (as per straight line method of evaluation of depreciation) will be Rs. 5,000 Rs. 8,800 Rs. 6,400 Rs. 7,600 Rs. 5,000 Rs. 8,800 Rs. 6,400 Rs. 7,600 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management PERT analysis is based on Most likely time All listed here Pessimistic time Optimistic time Most likely time All listed here Pessimistic time Optimistic time ANSWER DOWNLOAD EXAMIANS APP