Construction Planning and Management For the network shown in the given figure, the expected time for the activity 3-4 is 8 1-2 is 4 2-3 is 7 All listed here 3-4 is 8 1-2 is 4 2-3 is 7 All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A CPM family includes All listed here CPP (Critical Path Plotted) MCE (Minimum Cost Expenditure) CPA (Critical Path Analysis) All listed here CPP (Critical Path Plotted) MCE (Minimum Cost Expenditure) CPA (Critical Path Analysis) ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time by which a particular activity can be delayed without affecting the preceding and succeeding activities is known as Interfering float Free float Independent float Total float Interfering float Free float Independent float Total float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is (a + 2m + b)/6 (a + 4m + b)/6 (a + 5m + b)/6 (a + m + b)/6 (a + 2m + b)/6 (a + 4m + b)/6 (a + 5m + b)/6 (a + m + b)/6 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The basic action involved in sheep foot rolling is Vibration Pressing Kneading Tamping Vibration Pressing Kneading Tamping ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time which results in the least possible construction cost of an activity, is known as Crash time Slow time Normal time Standard time Crash time Slow time Normal time Standard time ANSWER DOWNLOAD EXAMIANS APP