Construction Planning and Management For the network shown in the given figure, the expected time for the activity All listed here 3-4 is 8 2-3 is 7 1-2 is 4 All listed here 3-4 is 8 2-3 is 7 1-2 is 4 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A machine costs Rs. 20000 and its useful life is 8 years. The money is borrowed at 8% interest per annum. The capital recovery factor at 8% interest per annum for 8 years is 0.174. The annual equipment cost of the machine will be Rs. 3480 Rs. 5220 Rs. 6960 Rs. 1740 Rs. 3480 Rs. 5220 Rs. 6960 Rs. 1740 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Frequency distribution curves Having a single lump, are called uninodal curves If not symmetrical, are called skew curves All listed here If symmetrical, are called normal curves Having a single lump, are called uninodal curves If not symmetrical, are called skew curves All listed here If symmetrical, are called normal curves ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The first method invented for planning projects, was Bar chart method Critical path method (CPM) Milestone chart Programme Evaluation and Review Technique (PERT) Bar chart method Critical path method (CPM) Milestone chart Programme Evaluation and Review Technique (PERT) ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Pick up the PERT event from the following: Digging of foundation completed All listed here Laying of concrete started Digging of foundation started Digging of foundation completed All listed here Laying of concrete started Digging of foundation started ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Optimistic time, most likely time and pessimistic times for the activities of a network in the given figure are written above their arrows. If the contractual obligation time for the project is 75, the latest occurrence time for the event 2, is 35 25 20 15 35 25 20 15 ANSWER DOWNLOAD EXAMIANS APP