Construction Planning and Management
Assertion A: For a given depth of cut, the output of a power shovel can be increased by decreasing the angle of swing.Reason R: If the angle of swing is decreased, the cycle time will be decreased.

A is false but R is true
Both A and R is true but R is not the correct explanation of A
A is true but R is false
Both A and R is true and R is the correct explanation of A

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
In time-cost optimization of a project, crashing is done.

On all the activities lying on the critical path
On all the activities
Only on activities lying on the original critical path and having flatter cost slopes
On original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope

ANSWER DOWNLOAD EXAMIANS APP