Construction Planning and Management The part of a derrick crane include (i) Mast (ii) Boom (iii) Bull wheel (iv) Jack which of these statements are correct? (ii), (iii) and (iv) are correct (i), (ii) and (iv) are correct (i), (iii) and (iv) are correct (i), (ii) and (iii) are correct (ii), (iii) and (iv) are correct (i), (ii) and (iv) are correct (i), (iii) and (iv) are correct (i), (ii) and (iii) are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The constraints in case of resource smoothening operation would be Resources Both resources and project duration time None of these Project duration time Resources Both resources and project duration time None of these Project duration time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management PERT analysis is based on Most likely time All listed here Optimistic time Pessimistic time Most likely time All listed here Optimistic time Pessimistic time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as Free float Total float Duration Interfering float Free float Total float Duration Interfering float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The main principle of an organization, is All listed here Effective control at all levels Delegation of authority Unity of command All listed here Effective control at all levels Delegation of authority Unity of command ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A machine is purchased for Rs. 10,000,00 and has an estimated life of 10 years. The salvage value at the end of 10 years is Rs. 1,50,000. The book value of the machine at the end of 5 years using general straight line method of evaluation of depreciation is Rs. 6,50,000 Rs. 8,50,000 Rs. 5,75,000 Rs. 4,75,000 Rs. 6,50,000 Rs. 8,50,000 Rs. 5,75,000 Rs. 4,75,000 ANSWER DOWNLOAD EXAMIANS APP