Construction Planning and Management The part of a derrick crane include (i) Mast (ii) Boom (iii) Bull wheel (iv) Jack which of these statements are correct? (i), (ii) and (iii) are correct (i), (ii) and (iv) are correct (ii), (iii) and (iv) are correct (i), (iii) and (iv) are correct (i), (ii) and (iii) are correct (i), (ii) and (iv) are correct (ii), (iii) and (iv) are correct (i), (iii) and (iv) are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The original cost of an equipment is Rs.10,000. Its salvage value at the end of its total useful life of five years is Rs. 1,000. Its book value at the end of two years of its useful life (as per straight line method of evaluation of depreciation) will be Rs. 8,800 Rs. 5,000 Rs. 7,600 Rs. 6,400 Rs. 8,800 Rs. 5,000 Rs. 7,600 Rs. 6,400 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The first method invented for planning projects, was Critical path method (CPM) Programme Evaluation and Review Technique (PERT) Bar chart method Milestone chart Critical path method (CPM) Programme Evaluation and Review Technique (PERT) Bar chart method Milestone chart ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The Overall in-charge of an organization at the site responsible for the execution of the works, is Junior Engineer Executive Engineer Assistant Engineer Engineer Junior Engineer Executive Engineer Assistant Engineer Engineer ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For the supply of materials for concrete, form work reinforcing and placing of concrete, removal of form work and curing of concrete, number of bar(s) required on bar chart, is 4 2 3 1 4 2 3 1 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The difference between the time avail-to do a job and the time required to do the job, is known as Float Constraint Event Duration Float Constraint Event Duration ANSWER DOWNLOAD EXAMIANS APP