Construction Planning and Management The part of a derrick crane include (i) Mast (ii) Boom (iii) Bull wheel (iv) Jack which of these statements are correct? (i), (ii) and (iii) are correct (ii), (iii) and (iv) are correct (i), (iii) and (iv) are correct (i), (ii) and (iv) are correct (i), (ii) and (iii) are correct (ii), (iii) and (iv) are correct (i), (iii) and (iv) are correct (i), (ii) and (iv) are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Preliminary project report for a road project must contain The detailed estimated cost based on detailed design The soil survey, traffic survey, concept design and approximate cost The contract documents for inviting tenders The several alternatives of the project that have been considered The detailed estimated cost based on detailed design The soil survey, traffic survey, concept design and approximate cost The contract documents for inviting tenders The several alternatives of the project that have been considered ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management An excavator costs Rs. 20,00,000 and has an estimated life of 8 years. It has no salvage value at the end of 8 years. The book value of the excavator at the end of 3 years using general double declining balance method is Rs. 8,43,750 Rs. 10,50,000 Rs. 8,75,000 Rs. 11,56,250 Rs. 8,43,750 Rs. 10,50,000 Rs. 8,75,000 Rs. 11,56,250 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements:In the critical path method of construction planning, Free Float can be.1. Greater than Total Float.2. Greater than Independent Float3. Equal to Total Float.4. Less than Independent Float 1 and 4 are correct 1 and 2 are correct 1 and 4 are correct 2 and 3 are correct 1 and 4 are correct 1 and 2 are correct 1 and 4 are correct 2 and 3 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The independent float affects only None of these The particular activity involved Preceding activities Succeeding activities None of these The particular activity involved Preceding activities Succeeding activities ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the excavation of earth is done manually then it costs Rs. 10 per cum. A machine can excavate at a fixed cost of Rs. 4000 plus a variable cost of Rs. 2 per cum. The quantity of earth for which the cost of excavation by machine will be equal to the cost of manual excavation is 500 cum 1000 cum 1500 cum 2000 cum 500 cum 1000 cum 1500 cum 2000 cum ANSWER DOWNLOAD EXAMIANS APP