Construction Planning and Management The Overall in-charge of an organization at the site responsible for the execution of the works, is Engineer Junior Engineer Assistant Engineer Executive Engineer Engineer Junior Engineer Assistant Engineer Executive Engineer ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The salient feature of functional organization is Each individual maintains functional efficiency All listed here Strict adherence to specifications Separation of planning and design part Each individual maintains functional efficiency All listed here Strict adherence to specifications Separation of planning and design part ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Critical path lies along the activities having total float Same Zero Positive Negative Same Zero Positive Negative ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For completion of a project, the critical path of the network represents Maximum time Minimum cost Maximum cost Minimum time Maximum time Minimum cost Maximum cost Minimum time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management While scheduling a project by C.P.M. A project is divided into various activities Required time for each activity is established All listed here Net work is drawn by connecting the activities and the events A project is divided into various activities Required time for each activity is established All listed here Net work is drawn by connecting the activities and the events ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following features/factors:1. Projects are of the non-repetitive type2. Time required need not be known3. Time required is known precisely4. Events have been established for planning5. Emphasis is given to activities of projectPERT is preferred for planning because of 1, 2 and 5 1, 3 and 4 3, 4 and 5 1, 2 and 4 1, 2 and 5 1, 3 and 4 3, 4 and 5 1, 2 and 4 ANSWER DOWNLOAD EXAMIANS APP