Construction Planning and Management The direct cost of a project with respect to normal time is Infinite Zero Minimum Maximum Infinite Zero Minimum Maximum ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the scheduled completion time of a project is more than the earliest expected time for completion of the project, then the probability of completion of the project within the scheduled completion time will be 1 More than 50 % Less than 50 % 0.5 1 More than 50 % Less than 50 % 0.5 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Earliest finish of an activity is always Less than or equal to earliest event time of the following node Greater than or equal to earliest event time of the following node Less than earliest event time of the following node Greater than earliest event time of the following node Less than or equal to earliest event time of the following node Greater than or equal to earliest event time of the following node Less than earliest event time of the following node Greater than earliest event time of the following node ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Interfering float is the difference between Free float and independent float None of these Total float and independent float Total float and free float Free float and independent float None of these Total float and independent float Total float and free float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as Constraint Dummy Event Free float Constraint Dummy Event Free float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management What estimate would you give for the variance in above problem ? 9 36 81 54 9 36 81 54 ANSWER DOWNLOAD EXAMIANS APP