Construction Planning and Management The direct cost of a project with respect to normal time is Infinite Zero Maximum Minimum Infinite Zero Maximum Minimum ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following features/factors:1. Projects are of the non-repetitive type2. Time required need not be known3. Time required is known precisely4. Events have been established for planning5. Emphasis is given to activities of projectPERT is preferred for planning because of 1, 2 and 4 1, 2 and 5 1, 3 and 4 3, 4 and 5 1, 2 and 4 1, 2 and 5 1, 3 and 4 3, 4 and 5 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the expected time for completion of a project is 10 days with a standard deviation of 2 days, the expected time of completion of the project with 99.9% probability is 6 days 10 days 4 days 16 days 6 days 10 days 4 days 16 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is 9 days 8 days 10 days 15 days 9 days 8 days 10 days 15 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time which results in the least possible construction cost of an activity, is known as Slow time Standard time Normal time Crash time Slow time Standard time Normal time Crash time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The basic action involved in sheep foot rolling is Kneading Tamping Pressing Vibration Kneading Tamping Pressing Vibration ANSWER DOWNLOAD EXAMIANS APP