Construction Planning and Management For excavating utility trenches with precise control of depth, the excavation equipment used is Shovel Hoe None of these Dragline Shovel Hoe None of these Dragline ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Site order book is used for recording Construction measurements Names of the casual labour Instructions by the executive engineers Issue of store equipments Construction measurements Names of the casual labour Instructions by the executive engineers Issue of store equipments ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively 3.5 and 5/6 4 and 5/6 3.5 and 25/36 5 and 25/36 3.5 and 5/6 4 and 5/6 3.5 and 25/36 5 and 25/36 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The process of incorporating changes and rescheduling or replanning is called Resource levelling Resource smoothening Updating Critical path scheduling Resource levelling Resource smoothening Updating Critical path scheduling ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management What estimate would you give for the variance in above problem ? 9 81 36 54 9 81 36 54 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements:In the bar chart planning1. Interdependence of the operations cannot be portrayed.2. Progress of work can be measured.3. Spare time of the activities can be determined.4. Schedule cannot be updated. 1, 2 and 3 are correct 2, 3 and 4 are correct 1, 2 and 4 are correct 1 and 4 are correct 1, 2 and 3 are correct 2, 3 and 4 are correct 1, 2 and 4 are correct 1 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP