Construction Planning and Management For excavating utility trenches with precise control of depth, the excavation equipment used is Hoe Shovel None of these Dragline Hoe Shovel None of these Dragline ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The normal time required for the completion of project in the above problem is 19 days 9 days 13 days 14 days 19 days 9 days 13 days 14 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Optimistic time, most likely time and pessimistic times for the activities of a network in the given figure are written above their arrows. If the contractual obligation time for the project is 75, the latest occurrence time for the event 2, is 15 25 20 35 15 25 20 35 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the scheduled completion time of a project is more than the earliest expected time for completion of the project, then the probability of completion of the project within the scheduled completion time will be 0.5 1 Less than 50 % More than 50 % 0.5 1 Less than 50 % More than 50 % ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements: In the bar chart planning 1. Interdependence of the operations cannot be portrayed. 2. Progress of work can be measured. 3. Spare time of the activities can be determined. 4. Schedule cannot be updated. 1, 2 and 3 are correct 1, 2 and 4 are correct 2, 3 and 4 are correct 1 and 4 are correct 1, 2 and 3 are correct 1, 2 and 4 are correct 2, 3 and 4 are correct 1 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following excavators is most suitable for digging under water? Drag line Hoe Clam shell Dipper shovel Drag line Hoe Clam shell Dipper shovel ANSWER DOWNLOAD EXAMIANS APP