Construction Planning and Management What estimate would you give for the variance in above problem ? 54 36 9 81 54 36 9 81 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the expected time for completion of a project is 10 days with a standard deviation of 2 days, the expected time of completion of the project with 99.9% probability is 4 days 10 days 16 days 6 days 4 days 10 days 16 days 6 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following activities in a building construction:1. Concreting of roof slabs2. Brick-jelly lime concrete terracing3. Erection of form work for slab4. Construction of parapet wall in terraceThe correct sequence of these activities is 3, 1, 2, 4 1, 3, 4, 2 1, 3, 2, 4 3, 1, 4, 2 3, 1, 2, 4 1, 3, 4, 2 1, 3, 2, 4 3, 1, 4, 2 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A critical ratio scheduling None of these Is a dynamic system Determines the status of each activity Adjusts automatically changes in activity progress None of these Is a dynamic system Determines the status of each activity Adjusts automatically changes in activity progress ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time corresponding to minimum total project cost is Normal time Between normal time and crash time Optimistic time Crash time Normal time Between normal time and crash time Optimistic time Crash time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A construction schedule is prepared after collecting Output of labour Number of operations Output of machinery All listed here Output of labour Number of operations Output of machinery All listed here ANSWER DOWNLOAD EXAMIANS APP