Construction Planning and Management What estimate would you give for the variance in above problem ? 81 54 9 36 81 54 9 36 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the output of a drag-line for 90° angle of swing at optimum depth of cut is X, then the output for 120° angle of swing at 120 % of optimum depth of cut will be More than X Any of the above Less than X Equal to X More than X Any of the above Less than X Equal to X ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the scheduled completion time of a project is more than the earliest expected time for completion of the project, then the probability of completion of the project within the scheduled completion time will be Less than 50 % 1 0.5 More than 50 % Less than 50 % 1 0.5 More than 50 % ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The main principle of an organization, is Effective control at all levels All listed here Unity of command Delegation of authority Effective control at all levels All listed here Unity of command Delegation of authority ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the excavation of earth is done manually then it costs Rs. 10 per cum. A machine can excavate at a fixed cost of Rs. 4000 plus a variable cost of Rs. 2 per cum. The quantity of earth for which the cost of excavation by machine will be equal to the cost of manual excavation is 500 cum 2000 cum 1000 cum 1500 cum 500 cum 2000 cum 1000 cum 1500 cum ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In PERT analysis, the time estimates of activities and probability of their occurrence follow Normal distribution curve Poisson's distribution curve Beta distribution curve None of these Normal distribution curve Poisson's distribution curve Beta distribution curve None of these ANSWER DOWNLOAD EXAMIANS APP