Construction Planning and Management What estimate would you give for the variance in above problem ? 81 36 9 54 81 36 9 54 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In PERT analysis, the time estimates of activities and probability of their occurrence follow Poisson's distribution curve Beta distribution curve None of these Normal distribution curve Poisson's distribution curve Beta distribution curve None of these Normal distribution curve ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements:In the critical path method of construction planning, Free Float can be.1. Greater than Total Float.2. Greater than Independent Float3. Equal to Total Float.4. Less than Independent Float 1 and 4 are correct 1 and 4 are correct 1 and 2 are correct 2 and 3 are correct 1 and 4 are correct 1 and 4 are correct 1 and 2 are correct 2 and 3 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Free float for any activity is defined as the difference between its latest finish time and earliest start time for its successor activity its latest start time and earliest start time its earliest finish time and earliest start time for its successor activity its earliest finish time and latest start time for its successor activity its latest finish time and earliest start time for its successor activity its latest start time and earliest start time its earliest finish time and earliest start time for its successor activity its earliest finish time and latest start time for its successor activity ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the scheduled completion time of a project is more than the earliest expected time for completion of the project, then the probability of completion of the project within the scheduled completion time will be 0.5 1 More than 50 % Less than 50 % 0.5 1 More than 50 % Less than 50 % ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Updating may result in Decrease of project completion time Increase of project completion time All of these Change of critical path Decrease of project completion time Increase of project completion time All of these Change of critical path ANSWER DOWNLOAD EXAMIANS APP