Construction Planning and Management What estimate would you give for the variance in above problem ? 81 9 54 36 81 9 54 36 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A wheeled tractor hauling unit is working on firm earth. The total loaded weight distribution of this unit is: Drive wheels: 25000 kg Scraper wheels: 10000 kgIf the coefficient of traction for wheeled tractor on firm earth is 0.5, the rimpull which this tractor can exert without slipping is 5000 kg 10000 kg 12500 kg 22500 kg 5000 kg 10000 kg 12500 kg 22500 kg ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Military organization is known as None of these Functional organization Line organization Line and staff organization None of these Functional organization Line organization Line and staff organization ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The three time estimates for the activities of the network shown in the given figure are shown above their arrows. The earliest expected time for the event 4, is None of these 24 14 19 None of these 24 14 19 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A golden rule for the procurement of construction stones, suggests 33% at the site and 67% under procurement 50% at the site and 50% under procurement 100% at the site 67% at the site and 33% under procurement 33% at the site and 67% under procurement 50% at the site and 50% under procurement 100% at the site 67% at the site and 33% under procurement ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Assertion (A): Activity 57 is critical.Reason (R): Earliest finish time and latest finish time for events 57 are same R is correct but A is not correct Both A and R is incorrect Both A and R is correct A is correct but R is not correct R is correct but A is not correct Both A and R is incorrect Both A and R is correct A is correct but R is not correct ANSWER DOWNLOAD EXAMIANS APP