Construction Planning and Management What estimate would you give for the variance in above problem ? 36 54 9 81 36 54 9 81 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A tractor whose weight is 20 tonnes has a drawbar pull of 2500 kg, when operated on a level road having a rolling resistance of 30 kg per tonne. If this tractor is operated on a level road having a rolling resistance of 40 kg per tonne, then the drawbar pull of the tractor will Reduce by 250 kg Increase by 250 kg Reduce by 200 kg Increase by 200 kg Reduce by 250 kg Increase by 250 kg Reduce by 200 kg Increase by 200 kg ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Assertion (A): Activity 57 is critical.Reason (R): Earliest finish time and latest finish time for events 57 are same Both A and R is correct R is correct but A is not correct Both A and R is incorrect A is correct but R is not correct Both A and R is correct R is correct but A is not correct Both A and R is incorrect A is correct but R is not correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Final technical authority of a project lies with Executive Engineer Chief Engineer Superintending Engineer Assistant Engineer Executive Engineer Chief Engineer Superintending Engineer Assistant Engineer ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For the network shown in the given figure, the expected time for the activity 3-4 is 8 All listed here 2-3 is 7 1-2 is 4 3-4 is 8 All listed here 2-3 is 7 1-2 is 4 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then the following relation holds good LF = LS + D EF = ES + D LS = LF - D All listed here LF = LS + D EF = ES + D LS = LF - D All listed here ANSWER DOWNLOAD EXAMIANS APP