Construction Planning and Management What estimate would you give for the variance in above problem ? 81 9 36 54 81 9 36 54 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Grader is used mainly for Trimming and finishing Shaping and trimming Finishing and shaping Finishing, shaping and trimming Trimming and finishing Shaping and trimming Finishing and shaping Finishing, shaping and trimming ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Free float for any activity is defined as the difference between its earliest finish time and latest start time for its successor activity its earliest finish time and earliest start time for its successor activity its latest finish time and earliest start time for its successor activity its latest start time and earliest start time its earliest finish time and latest start time for its successor activity its earliest finish time and earliest start time for its successor activity its latest finish time and earliest start time for its successor activity its latest start time and earliest start time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Pick up the PERT event from the following: Digging of foundation completed All listed here Laying of concrete started Digging of foundation started Digging of foundation completed All listed here Laying of concrete started Digging of foundation started ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is 15 days 9 days 10 days 8 days 15 days 9 days 10 days 8 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Power stations are generally treated as Electrical construction Heavy construction Industrial construction Light construction Electrical construction Heavy construction Industrial construction Light construction ANSWER DOWNLOAD EXAMIANS APP