Construction Planning and Management What estimate would you give for the variance in above problem ? 54 81 9 36 54 81 9 36 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the gross vehicle weight of a truck is 30 tonne and rolling resistance is 30 kg/tonne, then the tractive effort required to keep the truck moving at a uniform speed is 900 kg 300 kg 30 kg 1000 kg 900 kg 300 kg 30 kg 1000 kg ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The area under the Beta distribution curve is divided into two equal parts by Pessimistic time Optimistic time Expected time Most likely time Pessimistic time Optimistic time Expected time Most likely time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Construction team means An engineer An owner All listed here An architect An engineer An owner All listed here An architect ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which one of the following represents an event? Concrete cured Plastering of walls Selecting sites Fixing of door Concrete cured Plastering of walls Selecting sites Fixing of door ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Total float for any activity is defined as the difference between Its latest start time and earliest start time Its latest finish time and earliest start time for its successor activity Its latest start time and earliest finish time Its earliest finish time and earliest start time for its successor activity Its latest start time and earliest start time Its latest finish time and earliest start time for its successor activity Its latest start time and earliest finish time Its earliest finish time and earliest start time for its successor activity ANSWER DOWNLOAD EXAMIANS APP