Construction Planning and Management What estimate would you give for the variance in above problem ? 9 36 54 81 9 36 54 81 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In time-cost optimization of a project, crashing is done. On all the activities Only on activities lying on the original critical path and having flatter cost slopes On all the activities lying on the critical path On original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope On all the activities Only on activities lying on the original critical path and having flatter cost slopes On all the activities lying on the critical path On original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Whenever an activity has zero total float, then Independent float must be zero but free float need not be zero Free float of the activity must be zero but independent float need not be zero Free float and independent float both must be zero Free float and independent float both need not be zero Independent float must be zero but free float need not be zero Free float of the activity must be zero but independent float need not be zero Free float and independent float both must be zero Free float and independent float both need not be zero ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements:In the critical path method of construction planning, Free Float can be.1. Greater than Total Float.2. Greater than Independent Float3. Equal to Total Float.4. Less than Independent Float 2 and 3 are correct 1 and 4 are correct 1 and 2 are correct 1 and 4 are correct 2 and 3 are correct 1 and 4 are correct 1 and 2 are correct 1 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having Least cost slope Longest duration Highest cost slope Shortest duration Least cost slope Longest duration Highest cost slope Shortest duration ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management PERT technique of network analysis is mainly useful for Large and complex projects Deterministic activities Research and development projects Small projects Large and complex projects Deterministic activities Research and development projects Small projects ANSWER DOWNLOAD EXAMIANS APP