Construction Planning and Management What estimate would you give for the variance in above problem ? 36 81 54 9 36 81 54 9 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management PERT analysis is based on Most likely time Pessimistic time Optimistic time All listed here Most likely time Pessimistic time Optimistic time All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Updating may result in Decrease of project completion time Increase of project completion time Change of critical path All of these Decrease of project completion time Increase of project completion time Change of critical path All of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For completion of a project, the critical path of the network represents Maximum cost Minimum cost Minimum time Maximum time Maximum cost Minimum cost Minimum time Maximum time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A four wheel truck or whose operating weight is 12000 kg is pulled along a road having a rising slope of 2% at a uniform speed. Assume grade resistance factor = 10 kg/tonne. The tension in the tow cable is 720 kg. The rolling resistance of the road will be 30 kg/tonne 20 kg/tonne 40 kg/tonne 50 kg/tonne 30 kg/tonne 20 kg/tonne 40 kg/tonne 50 kg/tonne ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which one of the following surfaces will give highest coefficient of traction while using crawler track tractors? Earth Concrete Ice Loose sand Earth Concrete Ice Loose sand ANSWER DOWNLOAD EXAMIANS APP