Construction Planning and Management What estimate would you give for the variance in above problem ? 81 36 54 9 81 36 54 9 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The three time estimates for the activities of the network shown in the given figure are shown above their arrows. The earliest expected time for the event 4, is 14 19 None of these 24 14 19 None of these 24 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Military organization is known as None of these Line organization Line and staff organization Functional organization None of these Line organization Line and staff organization Functional organization ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Critical path method Is an improvement upon bar chart method All listed here Provides a realistic approach to daily problems Avoids delays which are very common in bar charts Is an improvement upon bar chart method All listed here Provides a realistic approach to daily problems Avoids delays which are very common in bar charts ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The critical activity has Zero float Maximum float Minimum float None of these Zero float Maximum float Minimum float None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements: In the critical path method of construction planning, Free Float can be. 1. Greater than Total Float. 2. Greater than Independent Float 3. Equal to Total Float. 4. Less than Independent Float 1 and 4 are correct 1 and 4 are correct 2 and 3 are correct 1 and 2 are correct 1 and 4 are correct 1 and 4 are correct 2 and 3 are correct 1 and 2 are correct ANSWER DOWNLOAD EXAMIANS APP