Construction Planning and Management What estimate would you give for the variance in above problem ? 54 81 36 9 54 81 36 9 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following earth moving machines has the shortest cycle time? Drag line Hoe Clam shell Dipper shovel Drag line Hoe Clam shell Dipper shovel ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following activities in a building construction: 1. Concreting of roof slabs 2. Brick-jelly lime concrete terracing 3. Erection of form work for slab 4. Construction of parapet wall in terrace The correct sequence of these activities is 1, 3, 4, 2 1, 3, 2, 4 3, 1, 4, 2 3, 1, 2, 4 1, 3, 4, 2 1, 3, 2, 4 3, 1, 4, 2 3, 1, 2, 4 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Whenever an activity has zero total float, then Independent float must be zero but free float need not be zero Free float of the activity must be zero but independent float need not be zero Free float and independent float both must be zero Free float and independent float both need not be zero Independent float must be zero but free float need not be zero Free float of the activity must be zero but independent float need not be zero Free float and independent float both must be zero Free float and independent float both need not be zero ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Pick up the correct statement from the following with regards to C.P.M. network analysis of projects Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time All listed here The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time All listed here The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Economic saving of time results by crashing Costliest noncritical activity Cheapest noncritical activity Costliest critical activity Cheapest critical activity Costliest noncritical activity Cheapest noncritical activity Costliest critical activity Cheapest critical activity ANSWER DOWNLOAD EXAMIANS APP