Construction Planning and Management What estimate would you give for the variance in above problem ? 9 81 36 54 9 81 36 54 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The difference between the time avail-to do a job and the time required to do the job, is known as Duration Constraint Event Float Duration Constraint Event Float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A machine is purchased for Rs. 10,000,00 and has an estimated life of 10 years. The salvage value at the end of 10 years is Rs. 1,50,000. The book value of the machine at the end of 5 years using general straight line method of evaluation of depreciation is Rs. 5,75,000 Rs. 4,75,000 Rs. 6,50,000 Rs. 8,50,000 Rs. 5,75,000 Rs. 4,75,000 Rs. 6,50,000 Rs. 8,50,000 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the excavation of earth is done manually then it costs Rs. 10 per cum. A machine can excavate at a fixed cost of Rs. 4000 plus a variable cost of Rs. 2 per cum. The quantity of earth for which the cost of excavation by machine will be equal to the cost of manual excavation is 1500 cum 1000 cum 500 cum 2000 cum 1500 cum 1000 cum 500 cum 2000 cum ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A wheeled tractor hauling unit is working on firm earth. The total loaded weight distribution of this unit is:Drive wheels: 25000 kgScraper wheels: 10000 kgIf the coefficient of traction for wheeled tractor on firm earth is 0.5, the rimpull which this tractor can exert without slipping is 10000 kg 12500 kg 5000 kg 22500 kg 10000 kg 12500 kg 5000 kg 22500 kg ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In PERT analysis, the time estimates of activities and probability of their occurrence follow None of these Poisson's distribution curve Normal distribution curve Beta distribution curve None of these Poisson's distribution curve Normal distribution curve Beta distribution curve ANSWER DOWNLOAD EXAMIANS APP