The time by which a particular activity can be delayed without affecting the preceding and succeeding activities is known as

Interfering float
Free float
Independent float
Total float

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
CPM is

Is built of activities oriented programme
Synthesising in concepts
All listed here
Is based on time estimate

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Railway projects are treated as

Light construction
None of these
Industrial construction
Heavy construction

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Works costing less than Rs. 20,000 are treated as

All listed here
Minor projects
Any project
Major projects

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Which one of the following surfaces will give highest coefficient of traction while using crawler track tractors?

Ice
Earth
Loose sand
Concrete

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
PERT analysis is based on

Pessimistic time
Optimistic time
Most likely time
All listed here

ANSWER DOWNLOAD EXAMIANS APP
MORE MCQ ON Construction Planning and Management

DOWNLOAD APP

  • APPLE
    from app store
  • ANDROID
    from play store

SEARCH

LOGIN HERE


  • GOOGLE

FIND US

  • 1.70K
    FOLLOW US
  • EXAMIANSSTUDY FOR YOUR DREAMS.
  • SUPPORT :SUPPORT EMAIL ACCOUNT : examians@yahoo.com

OTHER WEBSITES

  • GUJARATI MCQ
  • ACCOUNTIANS

QUICK LINKS

  • HOME
  • QUIZ
  • PRIVACY POLICY
  • DISCLAIMER
  • TERMS & CONDITIONS
  • CONTACT US
↑