Construction Planning and Management If the expected time for completion of a project is 10 days with a standard deviation of 2 days, the expected time of completion of the project with 99.9% probability is 6 days 16 days 10 days 4 days 6 days 16 days 10 days 4 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Pick up the PERT event from the following: Digging of foundation started Laying of concrete started Digging of foundation completed All listed here Digging of foundation started Laying of concrete started Digging of foundation completed All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management An excavator costs Rs. 20,00,000 and has an estimated life of 8 years. It has no salvage value at the end of 8 years. The book value of the excavator at the end of 3 years using general double declining balance method is Rs. 11,56,250 Rs. 10,50,000 Rs. 8,43,750 Rs. 8,75,000 Rs. 11,56,250 Rs. 10,50,000 Rs. 8,43,750 Rs. 8,75,000 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The constraints in case of resource smoothening operation would be Both resources and project duration time Resources Project duration time None of these Both resources and project duration time Resources Project duration time None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A wheeled tractor hauling unit is working on firm earth. The total loaded weight distribution of this unit is:Drive wheels: 25000 kgScraper wheels: 10000 kgIf the coefficient of traction for wheeled tractor on firm earth is 0.5, the rimpull which this tractor can exert without slipping is 12500 kg 22500 kg 10000 kg 5000 kg 12500 kg 22500 kg 10000 kg 5000 kg ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Slack time refers to An activity Both event and activity None of these An event An activity Both event and activity None of these An event ANSWER DOWNLOAD EXAMIANS APP