Construction Planning and Management If the expected time for completion of a project is 10 days with a standard deviation of 2 days, the expected time of completion of the project with 99.9% probability is 4 days 10 days 16 days 6 days 4 days 10 days 16 days 6 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In the given figure, the network of a project represents None of these Activity of an excavation of a footing Activity of an excavation which starts at event No. 1 and ends at even No. 2 Activity of excavation which takes 8 units of time None of these Activity of an excavation of a footing Activity of an excavation which starts at event No. 1 and ends at even No. 2 Activity of excavation which takes 8 units of time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Residential buildings are treated as Heavy construction Private construction Light construction Industrial construction Heavy construction Private construction Light construction Industrial construction ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following activities in a building construction: 1. Concreting of roof slabs 2. Brick-jelly lime concrete terracing 3. Erection of form work for slab 4. Construction of parapet wall in terrace The correct sequence of these activities is 3, 1, 4, 2 1, 3, 2, 4 1, 3, 4, 2 3, 1, 2, 4 3, 1, 4, 2 1, 3, 2, 4 1, 3, 4, 2 3, 1, 2, 4 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The Overall in-charge of an organization at the site responsible for the execution of the works, is Junior Engineer Executive Engineer Assistant Engineer Engineer Junior Engineer Executive Engineer Assistant Engineer Engineer ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Various activities of a project, are shown on bar charts by Horizontal lines Vertical lines Crosses Dots Horizontal lines Vertical lines Crosses Dots ANSWER DOWNLOAD EXAMIANS APP