Construction Planning and Management If the expected time for completion of a project is 10 days with a standard deviation of 2 days, the expected time of completion of the project with 99.9% probability is 16 days 6 days 4 days 10 days 16 days 6 days 4 days 10 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management While scheduling a project by C.P.M. Net work is drawn by connecting the activities and the events A project is divided into various activities All listed here Required time for each activity is established Net work is drawn by connecting the activities and the events A project is divided into various activities All listed here Required time for each activity is established ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the excavation of earth is done manually then it costs Rs. 10 per cum. A machine can excavate at a fixed cost of Rs. 4000 plus a variable cost of Rs. 2 per cum. The quantity of earth for which the cost of excavation by machine will be equal to the cost of manual excavation is 1500 cum 500 cum 1000 cum 2000 cum 1500 cum 500 cum 1000 cum 2000 cum ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The part of a derrick crane include (i) Mast (ii) Boom (iii) Bull wheel (iv) Jack which of these statements are correct? (i), (ii) and (iv) are correct (ii), (iii) and (iv) are correct (i), (ii) and (iii) are correct (i), (iii) and (iv) are correct (i), (ii) and (iv) are correct (ii), (iii) and (iv) are correct (i), (ii) and (iii) are correct (i), (iii) and (iv) are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following operations:1. Drilling2. Blasting3. Mucking4. Placing steel5. Placing concreteThe correct sequence of these operations in tunnel construction is 1, 2, 4, 3, 5 1, 3, 2, 4, 5 1, 3, 4, 2, 5 1, 2, 3, 4, 5 1, 2, 4, 3, 5 1, 3, 2, 4, 5 1, 3, 4, 2, 5 1, 2, 3, 4, 5 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Rolling resistance of a wheel depends upon (i) Vehicle load (ii) Grade (iii) Ground conditions (i) and (ii) are correct Only (i) is correct (i) and (iii) are correct (ii) and (iii) are correct (i) and (ii) are correct Only (i) is correct (i) and (iii) are correct (ii) and (iii) are correct ANSWER DOWNLOAD EXAMIANS APP