Construction Planning and Management If the expected time for completion of a project is 10 days with a standard deviation of 2 days, the expected time of completion of the project with 99.9% probability is 10 days 6 days 16 days 4 days 10 days 6 days 16 days 4 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Power stations are generally treated as Electrical construction Light construction Heavy construction Industrial construction Electrical construction Light construction Heavy construction Industrial construction ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is 8 days 9 days 10 days 15 days 8 days 9 days 10 days 15 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Construction team means All listed here An architect An owner An engineer All listed here An architect An owner An engineer ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A contractor has two options;(l) : Invest his money in project A or (II) : Invest his money in project B. If he decides to invest in A, for every rupee invested, he is assured of doubling his money in ten years. If he decides to invest in B, he is assured of making his money 1.5 times in 5 years. If the contractor values his money at 10% interest rate, he should invest in project A should invest in project B should invest in neither of the two projects could invest in either of the two projects should invest in project A should invest in project B should invest in neither of the two projects could invest in either of the two projects ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as Free float Duration Total float Interfering float Free float Duration Total float Interfering float ANSWER DOWNLOAD EXAMIANS APP