Construction Planning and Management If the expected time for completion of a project is 10 days with a standard deviation of 2 days, the expected time of completion of the project with 99.9% probability is 6 days 10 days 4 days 16 days 6 days 10 days 4 days 16 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following features/factors:1. Projects are of the non-repetitive type2. Time required need not be known3. Time required is known precisely4. Events have been established for planning5. Emphasis is given to activities of projectPERT is preferred for planning because of 1, 3 and 4 1, 2 and 5 3, 4 and 5 1, 2 and 4 1, 3 and 4 1, 2 and 5 3, 4 and 5 1, 2 and 4 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management PERT analysis is based on All listed here Pessimistic time Optimistic time Most likely time All listed here Pessimistic time Optimistic time Most likely time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following features/factors: 1. Projects are of the non-repetitive type 2. Time required need not be known 3. Time required is known precisely 4. Events have been established for planning 5. Emphasis is given to activities of project PERT is preferred for planning because of 1, 2 and 4 1, 3 and 4 3, 4 and 5 1, 2 and 5 1, 2 and 4 1, 3 and 4 3, 4 and 5 1, 2 and 5 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Residential buildings are treated as Private construction Industrial construction Light construction Heavy construction Private construction Industrial construction Light construction Heavy construction ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For the network shown in the given figure, the expected time for the activity 3-4 is 8 All listed here 1-2 is 4 2-3 is 7 3-4 is 8 All listed here 1-2 is 4 2-3 is 7 ANSWER DOWNLOAD EXAMIANS APP