Construction Planning and Management Site order book is used for recording Issue of store equipments Instructions by the executive engineers Names of the casual labour Construction measurements Issue of store equipments Instructions by the executive engineers Names of the casual labour Construction measurements ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The three time estimates for the activities of the network shown in the given figure are shown above their arrows. The earliest expected time for the event 4, is None of these 14 24 19 None of these 14 24 19 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The maximum rimpull in the first gear of a tractor while towing a load is 6300 kg. The tractor weighs 12.5 tonnes and is operating along a 2 percent upgrade and the rolling resistance is 45 kg/tonne. Pull available for towing the load is 3425 kg 2975 kg 4350 kg 5515 kg 3425 kg 2975 kg 4350 kg 5515 kg ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Economic saving of time results by crashing Cheapest critical activity Costliest noncritical activity Costliest critical activity Cheapest noncritical activity Cheapest critical activity Costliest noncritical activity Costliest critical activity Cheapest noncritical activity ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A contractor has two options;(l) : Invest his money in project A or (II) : Invest his money in project B. If he decides to invest in A, for every rupee invested, he is assured of doubling his money in ten years. If he decides to invest in B, he is assured of making his money 1.5 times in 5 years. If the contractor values his money at 10% interest rate, he could invest in either of the two projects should invest in neither of the two projects should invest in project B should invest in project A could invest in either of the two projects should invest in neither of the two projects should invest in project B should invest in project A ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Final technical authority of a project lies with Executive Engineer Assistant Engineer Chief Engineer Superintending Engineer Executive Engineer Assistant Engineer Chief Engineer Superintending Engineer ANSWER DOWNLOAD EXAMIANS APP