Construction Planning and Management Sinking fund is A part of the money kept in reserve for providing additional structures and structural modifications The fund for rebuilding a structure when its economic life is over Raised to meet maintenance costs The total sum to be paid to the municipal authorities by the tenants A part of the money kept in reserve for providing additional structures and structural modifications The fund for rebuilding a structure when its economic life is over Raised to meet maintenance costs The total sum to be paid to the municipal authorities by the tenants ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The area under the Beta distribution curve is divided into two equal parts by Optimistic time Pessimistic time Most likely time Expected time Optimistic time Pessimistic time Most likely time Expected time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Crash project duration is obtained by summing the Normal durations for all the activities Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities Crash durations for all activities Normal durations for all the activities Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities Crash durations for all activities ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Construction team means An engineer All listed here An owner An architect An engineer All listed here An owner An architect ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management During the construction period, price variation clause in contracts caters to Increase in rates of only important materials Variation in cost in materials element, labour element and petrol-oil-lubricant element Rate of inflation Variation in total cost of the project on an ad hoc basis Increase in rates of only important materials Variation in cost in materials element, labour element and petrol-oil-lubricant element Rate of inflation Variation in total cost of the project on an ad hoc basis ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management An earth moving equipment costs Rs. 5,00,000 and has an estimated life of 10 years and a salvage value of Rs. 50,000. What uniform annual amount must be set aside at the end of each of the 10 years for replacement if the interest rate is 8% per annum and if the sinking fund factor at 8% per annum interest rate for 10 years is 0.069? Rs. 34500 Rs. 37950 Rs. 50000 Rs. 31050 Rs. 34500 Rs. 37950 Rs. 50000 Rs. 31050 ANSWER DOWNLOAD EXAMIANS APP