Construction Planning and Management Sinking fund is The fund for rebuilding a structure when its economic life is over Raised to meet maintenance costs A part of the money kept in reserve for providing additional structures and structural modifications The total sum to be paid to the municipal authorities by the tenants The fund for rebuilding a structure when its economic life is over Raised to meet maintenance costs A part of the money kept in reserve for providing additional structures and structural modifications The total sum to be paid to the municipal authorities by the tenants ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The independent float affects only None of these Succeeding activities The particular activity involved Preceding activities None of these Succeeding activities The particular activity involved Preceding activities ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the optimistic time, most likely time and pessimistic time for activity A are 4, 6 and 8 respectively and for activity B are 5, 5.5 and 9 respectively, then None of these expected time of activity A is greater than the expected time of activity B expected time of activity B is greater than the expected time of activity A expected time of both activities A and B are same None of these expected time of activity A is greater than the expected time of activity B expected time of activity B is greater than the expected time of activity A expected time of both activities A and B are same ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following operations:1. Drilling2. Blasting3. Mucking4. Placing steel5. Placing concreteThe correct sequence of these operations in tunnel construction is 1, 3, 2, 4, 5 1, 3, 4, 2, 5 1, 2, 3, 4, 5 1, 2, 4, 3, 5 1, 3, 2, 4, 5 1, 3, 4, 2, 5 1, 2, 3, 4, 5 1, 2, 4, 3, 5 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management CPM is All listed here Synthesising in concepts Is based on time estimate Is built of activities oriented programme All listed here Synthesising in concepts Is based on time estimate Is built of activities oriented programme ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Rolling resistance of a wheel depends upon(i) Vehicle load(ii) Grade(iii) Ground conditions Only (i) is correct (i) and (iii) are correct (i) and (ii) are correct (ii) and (iii) are correct Only (i) is correct (i) and (iii) are correct (i) and (ii) are correct (ii) and (iii) are correct ANSWER DOWNLOAD EXAMIANS APP