Construction Planning and Management Sinking fund is A part of the money kept in reserve for providing additional structures and structural modifications The fund for rebuilding a structure when its economic life is over Raised to meet maintenance costs The total sum to be paid to the municipal authorities by the tenants A part of the money kept in reserve for providing additional structures and structural modifications The fund for rebuilding a structure when its economic life is over Raised to meet maintenance costs The total sum to be paid to the municipal authorities by the tenants ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which one of the following surfaces will give highest coefficient of traction while using crawler track tractors? Ice Concrete Loose sand Earth Ice Concrete Loose sand Earth ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management At a work site, statistical quality control of concrete means Measurement of risks to eliminate failures Reduction in wastage of inspection costs Applying the theory' of probability to sample testing or inspection Reduction in costs for the removal of defects Measurement of risks to eliminate failures Reduction in wastage of inspection costs Applying the theory' of probability to sample testing or inspection Reduction in costs for the removal of defects ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A machine costs Rs. 20000 and its useful life is 8 years. The money is borrowed at 8% interest per annum. The capital recovery factor at 8% interest per annum for 8 years is 0.174. The annual equipment cost of the machine will be Rs. 1740 Rs. 6960 Rs. 5220 Rs. 3480 Rs. 1740 Rs. 6960 Rs. 5220 Rs. 3480 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the optimistic time, most likely time and pessimistic time for activity A are 4, 6 and 8 respectively and for activity B are 5, 5.5 and 9 respectively, then expected time of activity B is greater than the expected time of activity A None of these expected time of both activities A and B are same expected time of activity A is greater than the expected time of activity B expected time of activity B is greater than the expected time of activity A None of these expected time of both activities A and B are same expected time of activity A is greater than the expected time of activity B ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time with which direct cost does not reduce with the increase in time is known as Normal time Optimistic time Standard time Crash time Normal time Optimistic time Standard time Crash time ANSWER DOWNLOAD EXAMIANS APP