Construction Planning and Management Sinking fund is The fund for rebuilding a structure when its economic life is over The total sum to be paid to the municipal authorities by the tenants Raised to meet maintenance costs A part of the money kept in reserve for providing additional structures and structural modifications The fund for rebuilding a structure when its economic life is over The total sum to be paid to the municipal authorities by the tenants Raised to meet maintenance costs A part of the money kept in reserve for providing additional structures and structural modifications ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The original cost of an equipment is Rs.10,000. Its salvage value at the end of its total useful life of five years is Rs. 1,000. Its book value at the end of two years of its useful life (as per straight line method of evaluation of depreciation) will be Rs. 6,400 Rs. 5,000 Rs. 8,800 Rs. 7,600 Rs. 6,400 Rs. 5,000 Rs. 8,800 Rs. 7,600 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In time-cost optimization of a project, crashing is done. On all the activities lying on the critical path On original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope Only on activities lying on the original critical path and having flatter cost slopes On all the activities On all the activities lying on the critical path On original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope Only on activities lying on the original critical path and having flatter cost slopes On all the activities ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Grader is used mainly for Shaping and trimming Finishing and shaping Finishing, shaping and trimming Trimming and finishing Shaping and trimming Finishing and shaping Finishing, shaping and trimming Trimming and finishing ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the expected time for completion of a project is 10 days with a standard deviation of 2 days, the expected time of completion of the project with 99.9% probability is 16 days 6 days 10 days 4 days 16 days 6 days 10 days 4 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A CPM family includes MCE (Minimum Cost Expenditure) CPA (Critical Path Analysis) CPP (Critical Path Plotted) All listed here MCE (Minimum Cost Expenditure) CPA (Critical Path Analysis) CPP (Critical Path Plotted) All listed here ANSWER DOWNLOAD EXAMIANS APP