Construction Planning and Management
Sinking fund is

Raised to meet maintenance costs
The total sum to be paid to the municipal authorities by the tenants
The fund for rebuilding a structure when its economic life is over
A part of the money kept in reserve for providing additional structures and structural modifications

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Latest start of an activity is always

less than latest event time of preceding node
greater than or equal to latest event time of preceding node
less than or equal to latest event time of preceding node
equal to latest event time of preceding node

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
A contractor has two options;(l) : Invest his money in project A or (II) : Invest his money in project B. If he decides to invest in A, for every rupee invested, he is assured of doubling his money in ten years. If he decides to invest in B, he is assured of making his money 1.5 times in 5 years. If the contractor values his money at 10% interest rate, he

could invest in either of the two projects
should invest in project A
should invest in neither of the two projects
should invest in project B

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Crash project duration is obtained by summing the

Normal durations for all the activities
Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities
Crash durations for all activities
Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities

ANSWER DOWNLOAD EXAMIANS APP