Construction Planning and Management
Consider the following features/factors:
1. Projects are of the non-repetitive type
2. Time required need not be known
3. Time required is known precisely
4. Events have been established for planning
5. Emphasis is given to activities of projectPERT is preferred for planning because of

1, 2 and 5
1, 2 and 4
1, 3 and 4
3, 4 and 5

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Assertion A: For a given depth of cut, the output of a power shovel can be increased by decreasing the angle of swing.Reason R: If the angle of swing is decreased, the cycle time will be decreased.

A is false but R is true
Both A and R is true and R is the correct explanation of A
Both A and R is true but R is not the correct explanation of A
A is true but R is false

ANSWER DOWNLOAD EXAMIANS APP