Construction Planning and Management
Consider the following features/factors:
1. Projects are of the non-repetitive type
2. Time required need not be known
3. Time required is known precisely
4. Events have been established for planning
5. Emphasis is given to activities of projectPERT is preferred for planning because of

1, 2 and 5
1, 2 and 4
3, 4 and 5
1, 3 and 4

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
If the optimistic time, most likely time and pessimistic time for activity A are 4, 6 and 8 respectively and for activity B are 5, 5.5 and 9 respectively, then

expected time of activity B is greater than the expected time of activity A
expected time of activity A is greater than the expected time of activity B
None of these
expected time of both activities A and B are same

ANSWER DOWNLOAD EXAMIANS APP