Construction Planning and Management
Consider the following features/factors:
1. Projects are of the non-repetitive type
2. Time required need not be known
3. Time required is known precisely
4. Events have been established for planning
5. Emphasis is given to activities of projectPERT is preferred for planning because of

1, 3 and 4
1, 2 and 5
3, 4 and 5
1, 2 and 4

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
The reduction in project time normally results in

Increasing the direct cost and decreasing the indirect cost
Decreasing the direct cost and indirect cost both
Decreasing the direct cost and increasing indirect cost
Increasing the direct cost and indirect cost both

ANSWER DOWNLOAD EXAMIANS APP