Construction Planning and Management
Consider the following features/factors:
1. Projects are of the non-repetitive type
2. Time required need not be known
3. Time required is known precisely
4. Events have been established for planning
5. Emphasis is given to activities of projectPERT is preferred for planning because of

1, 2 and 5
3, 4 and 5
1, 2 and 4
1, 3 and 4

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Total float for any activity is defined as the difference between

Its latest start time and earliest finish time
Its latest finish time and earliest start time for its successor activity
Its earliest finish time and earliest start time for its successor activity
Its latest start time and earliest start time

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Free float is mainly used to

Identify the activities, which can be delayed without affecting the total float of succeeding activity
Identify the activities which can be delayed without affecting the total float of preceding activity
Establish priorities
Identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities

ANSWER DOWNLOAD EXAMIANS APP