Construction Planning and Management
Consider the following features/factors:
1. Projects are of the non-repetitive type
2. Time required need not be known
3. Time required is known precisely
4. Events have been established for planning
5. Emphasis is given to activities of projectPERT is preferred for planning because of

1, 3 and 4
1, 2 and 4
1, 2 and 5
3, 4 and 5

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
A contractor has two options;(l) : Invest his money in project A or (II) : Invest his money in project B. If he decides to invest in A, for every rupee invested, he is assured of doubling his money in ten years. If he decides to invest in B, he is assured of making his money 1.5 times in 5 years. If the contractor values his money at 10% interest rate, he

should invest in project A
could invest in either of the two projects
should invest in neither of the two projects
should invest in project B

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Preliminary project report for a road project must contain

The detailed estimated cost based on detailed design
The soil survey, traffic survey, concept design and approximate cost
The contract documents for inviting tenders
The several alternatives of the project that have been considered

ANSWER DOWNLOAD EXAMIANS APP