Construction Planning and Management The probability of completion of any activity within its expected time is 0.841 1 0.5 0.999 0.841 1 0.5 0.999 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management PERT analysis is based on Pessimistic time All listed here Most likely time Optimistic time Pessimistic time All listed here Most likely time Optimistic time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In resources levelling Uniform demand of resources is achieved Cost of project is controlled Total duration of project is increased Total duration of project is reduced Uniform demand of resources is achieved Cost of project is controlled Total duration of project is increased Total duration of project is reduced ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A construction schedule is prepared after collecting Output of labour All listed here Output of machinery Number of operations Output of labour All listed here Output of machinery Number of operations ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The part of a derrick crane include (i) Mast (ii) Boom (iii) Bull wheel (iv) Jack which of these statements are correct? (i), (ii) and (iii) are correct (i), (iii) and (iv) are correct (i), (ii) and (iv) are correct (ii), (iii) and (iv) are correct (i), (ii) and (iii) are correct (i), (iii) and (iv) are correct (i), (ii) and (iv) are correct (ii), (iii) and (iv) are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively 3.5 and 5/6 3.5 and 25/36 4 and 5/6 5 and 25/36 3.5 and 5/6 3.5 and 25/36 4 and 5/6 5 and 25/36 ANSWER DOWNLOAD EXAMIANS APP