Construction Planning and Management The probability of completion of any activity within its expected time is 0.5 0.999 0.841 1 0.5 0.999 0.841 1 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then the following relation holds good LF = LS + D LS = LF - D All listed here EF = ES + D LF = LS + D LS = LF - D All listed here EF = ES + D ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements: In the critical path method of construction planning, Free Float can be. 1. Greater than Total Float. 2. Greater than Independent Float 3. Equal to Total Float. 4. Less than Independent Float 1 and 4 are correct 1 and 4 are correct 1 and 2 are correct 2 and 3 are correct 1 and 4 are correct 1 and 4 are correct 1 and 2 are correct 2 and 3 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Interfering float is the difference between Free float and independent float Total float and free float Total float and independent float None of these Free float and independent float Total float and free float Total float and independent float None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time which results in the least possible construction cost of an activity, is known as Standard time Crash time Normal time Slow time Standard time Crash time Normal time Slow time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the expected time for completion of a project is 10 days with a standard deviation of 2 days, the expected time of completion of the project with 99.9% probability is 10 days 16 days 4 days 6 days 10 days 16 days 4 days 6 days ANSWER DOWNLOAD EXAMIANS APP