Construction Planning and Management The probability of completion of any activity within its expected time is 0.5 0.841 1 0.999 0.5 0.841 1 0.999 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following is not a PERT event? Sessional work completed Class is being attended Site investigation started Bus starts from Jaipur Sessional work completed Class is being attended Site investigation started Bus starts from Jaipur ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Critical path May be longest Is always longest May be shortest Is always shortest May be longest Is always longest May be shortest Is always shortest ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For the execution of a project, a contractor is A firm All listed here A person An agency A firm All listed here A person An agency ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements:In the critical path method of construction planning, Free Float can be.1. Greater than Total Float.2. Greater than Independent Float3. Equal to Total Float.4. Less than Independent Float 1 and 4 are correct 1 and 2 are correct 2 and 3 are correct 1 and 4 are correct 1 and 4 are correct 1 and 2 are correct 2 and 3 are correct 1 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The maximum rimpull in the first gear of a tractor while towing a load is 6300 kg. The tractor weighs 12.5 tonnes and is operating along a 2 percent upgrade and the rolling resistance is 45 kg/tonne. Pull available for towing the load is 3425 kg 2975 kg 5515 kg 4350 kg 3425 kg 2975 kg 5515 kg 4350 kg ANSWER DOWNLOAD EXAMIANS APP