Construction Planning and Management The probability of completion of any activity within its expected time is 1 0.999 0.5 0.841 1 0.999 0.5 0.841 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Whenever an activity has zero total float, then Free float and independent float both need not be zero Independent float must be zero but free float need not be zero Free float of the activity must be zero but independent float need not be zero Free float and independent float both must be zero Free float and independent float both need not be zero Independent float must be zero but free float need not be zero Free float of the activity must be zero but independent float need not be zero Free float and independent float both must be zero ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Military organization is known as Line and staff organization None of these Line organization Functional organization Line and staff organization None of these Line organization Functional organization ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Interfering float is the difference between Total float and independent float None of these Free float and independent float Total float and free float Total float and independent float None of these Free float and independent float Total float and free float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A critical ratio scheduling Is a dynamic system Determines the status of each activity Adjusts automatically changes in activity progress None of these Is a dynamic system Determines the status of each activity Adjusts automatically changes in activity progress None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The three time estimates for the activities of the network shown in the given figure are shown above their arrows. The earliest expected time for the event 4, is 19 14 24 None of these 19 14 24 None of these ANSWER DOWNLOAD EXAMIANS APP