Construction Planning and Management The probability of completion of any activity within its expected time is 0.841 0.999 0.5 1 0.841 0.999 0.5 1 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Assertion (A): Activity 57 is critical.Reason (R): Earliest finish time and latest finish time for events 57 are same Both A and R is correct A is correct but R is not correct Both A and R is incorrect R is correct but A is not correct Both A and R is correct A is correct but R is not correct Both A and R is incorrect R is correct but A is not correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Critical path Is always shortest May be longest Is always longest May be shortest Is always shortest May be longest Is always longest May be shortest ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which one of the following surfaces will give highest coefficient of traction while using crawler track tractors? Earth Loose sand Concrete Ice Earth Loose sand Concrete Ice ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the excavation of earth is done manually then it costs Rs. 10 per cum. A machine can excavate at a fixed cost of Rs. 4000 plus a variable cost of Rs. 2 per cum. The quantity of earth for which the cost of excavation by machine will be equal to the cost of manual excavation is 2000 cum 500 cum 1000 cum 1500 cum 2000 cum 500 cum 1000 cum 1500 cum ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time with which direct cost does not reduce with the increase in time is known as Crash time Optimistic time Normal time Standard time Crash time Optimistic time Normal time Standard time ANSWER DOWNLOAD EXAMIANS APP