Construction Planning and Management The probability of completion of any activity within its expected time is 0.841 0.5 1 0.999 0.841 0.5 1 0.999 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management While scheduling a project by C.P.M. Required time for each activity is established Net work is drawn by connecting the activities and the events All listed here A project is divided into various activities Required time for each activity is established Net work is drawn by connecting the activities and the events All listed here A project is divided into various activities ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Mile Stone charts were invented in the year of 1930 1920 1940 1910 1930 1920 1940 1910 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following activities in a building construction: 1. Concreting of roof slabs 2. Brick-jelly lime concrete terracing 3. Erection of form work for slab 4. Construction of parapet wall in terrace The correct sequence of these activities is 1, 3, 4, 2 3, 1, 2, 4 1, 3, 2, 4 3, 1, 4, 2 1, 3, 4, 2 3, 1, 2, 4 1, 3, 2, 4 3, 1, 4, 2 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time with which direct cost does not reduce with the increase in time is known as Optimistic time Standard time Crash time Normal time Optimistic time Standard time Crash time Normal time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For the execution of a project, a contractor is An agency A person A firm All listed here An agency A person A firm All listed here ANSWER DOWNLOAD EXAMIANS APP