Construction Planning and Management The probability of completion of any activity within its expected time is 1 0.841 0.5 0.999 1 0.841 0.5 0.999 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Crash project duration is obtained by summing the Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities Normal durations for all the activities Crash durations for all activities Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities Normal durations for all the activities Crash durations for all activities ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following activities in a building construction:1. Concreting of roof slabs2. Brick-jelly lime concrete terracing3. Erection of form work for slab4. Construction of parapet wall in terraceThe correct sequence of these activities is 1, 3, 4, 2 1, 3, 2, 4 3, 1, 2, 4 3, 1, 4, 2 1, 3, 4, 2 1, 3, 2, 4 3, 1, 2, 4 3, 1, 4, 2 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is 10 days 9 days 15 days 8 days 10 days 9 days 15 days 8 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The three time estimates for the activities of the network shown in the given figure are shown above their arrows. The earliest expected time for the event 4, is None of these 14 24 19 None of these 14 24 19 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following surfaces will give highest rolling resistance for a rubber tyred vehicle? Asphalt Concrete Firm earth Loose sand Asphalt Concrete Firm earth Loose sand ANSWER DOWNLOAD EXAMIANS APP