Construction Planning and Management The probability of completion of any activity within its expected time is 0.999 1 0.5 0.841 0.999 1 0.5 0.841 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements:In the critical path method of construction planning, Free Float can be.1. Greater than Total Float.2. Greater than Independent Float3. Equal to Total Float.4. Less than Independent Float 1 and 2 are correct 2 and 3 are correct 1 and 4 are correct 1 and 4 are correct 1 and 2 are correct 2 and 3 are correct 1 and 4 are correct 1 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The constraints in case of resource smoothening operation would be Project duration time None of these Resources Both resources and project duration time Project duration time None of these Resources Both resources and project duration time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A tractor whose weight is 20 tonnes has a drawbar pull of 2500 kg, when operated on a level road having a rolling resistance of 30 kg per tonne. If this tractor is operated on a level road having a rolling resistance of 40 kg per tonne, then the drawbar pull of the tractor will Increase by 250 kg Reduce by 250 kg Increase by 200 kg Reduce by 200 kg Increase by 250 kg Reduce by 250 kg Increase by 200 kg Reduce by 200 kg ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the optimistic time, most likely time and pessimistic time for activity A are 4, 6 and 8 respectively and for activity B are 5, 5.5 and 9 respectively, then expected time of both activities A and B are same None of these expected time of activity A is greater than the expected time of activity B expected time of activity B is greater than the expected time of activity A expected time of both activities A and B are same None of these expected time of activity A is greater than the expected time of activity B expected time of activity B is greater than the expected time of activity A ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as Interfering float Free float Duration Total float Interfering float Free float Duration Total float ANSWER DOWNLOAD EXAMIANS APP