Construction Planning and Management The probability of completion of any activity within its expected time is 0.841 0.999 1 0.5 0.841 0.999 1 0.5 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Sinking fund is Raised to meet maintenance costs A part of the money kept in reserve for providing additional structures and structural modifications The total sum to be paid to the municipal authorities by the tenants The fund for rebuilding a structure when its economic life is over Raised to meet maintenance costs A part of the money kept in reserve for providing additional structures and structural modifications The total sum to be paid to the municipal authorities by the tenants The fund for rebuilding a structure when its economic life is over ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is 9 days 10 days 8 days 15 days 9 days 10 days 8 days 15 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is (a + 4m + b)/6 (a + m + b)/6 (a + 5m + b)/6 (a + 2m + b)/6 (a + 4m + b)/6 (a + m + b)/6 (a + 5m + b)/6 (a + 2m + b)/6 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements for a power shovel: (i) Output can be increased by reducing the angle of swing for a given depth of cut. (ii) For a given angle of swing, output will be maximum at optimum depth of cut. (iii) Output can be increased by keeping the depth of cut less than optimum depth. (iv) Output can be increased by increasing the size of shovel. (i), (iii) and (iv) are correct (ii), (iii) and (iv) are correct (i) and (iv) are correct (i), (ii) and (iv) are correct (i), (iii) and (iv) are correct (ii), (iii) and (iv) are correct (i) and (iv) are correct (i), (ii) and (iv) are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Crash project duration is obtained by summing the Normal durations for all the activities Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities Crash durations for all activities Normal durations for all the activities Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities Crash durations for all activities ANSWER DOWNLOAD EXAMIANS APP