Construction Planning and Management The probability of completion of any activity within its expected time is 0.999 1 0.841 0.5 0.999 1 0.841 0.5 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In India, are prefabricated components costlier than those of traditional cast-in-situ items that the prefabricated components replace? No, because of savings in site labour Yes, because of the very high order of quality control for the factory made components Yes, because of heavier overheads and handling cost No, because of repetitive manufacture of a number of elements No, because of savings in site labour Yes, because of the very high order of quality control for the factory made components Yes, because of heavier overheads and handling cost No, because of repetitive manufacture of a number of elements ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The maximum rimpull in the first gear of a tractor while towing a load is 6300 kg. The tractor weighs 12.5 tonnes and is operating along a 2 percent upgrade and the rolling resistance is 45 kg/tonne. Pull available for towing the load is 5515 kg 3425 kg 4350 kg 2975 kg 5515 kg 3425 kg 4350 kg 2975 kg ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The process of incorporating changes and rescheduling or replanning is called Updating Resource smoothening Resource levelling Critical path scheduling Updating Resource smoothening Resource levelling Critical path scheduling ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Total float for any activity is defined as the difference between Its latest start time and earliest finish time Its latest start time and earliest start time Its earliest finish time and earliest start time for its successor activity Its latest finish time and earliest start time for its successor activity Its latest start time and earliest finish time Its latest start time and earliest start time Its earliest finish time and earliest start time for its successor activity Its latest finish time and earliest start time for its successor activity ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Optimistic time, most likely time and pessimistic times for the activities of a network in the given figure are written above their arrows. If the contractual obligation time for the project is 75, the latest occurrence time for the event 2, is 20 25 35 15 20 25 35 15 ANSWER DOWNLOAD EXAMIANS APP