Construction Planning and Management The probability of completion of any activity within its expected time is 0.5 0.841 0.999 1 0.5 0.841 0.999 1 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the optimistic time, most likely time and pessimistic time for activity A are 4, 6 and 8 respectively and for activity B are 5, 5.5 and 9 respectively, then None of these expected time of activity A is greater than the expected time of activity B expected time of both activities A and B are same expected time of activity B is greater than the expected time of activity A None of these expected time of activity A is greater than the expected time of activity B expected time of both activities A and B are same expected time of activity B is greater than the expected time of activity A ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be Performed at slower rate in 15 days Started 5 days later Completed 5 days later All listed here Performed at slower rate in 15 days Started 5 days later Completed 5 days later All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The difference between the time avail-to do a job and the time required to do the job, is known as Constraint Duration Float Event Constraint Duration Float Event ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which one of the following surfaces will give highest coefficient of traction while using crawler track tractors? Ice Concrete Loose sand Earth Ice Concrete Loose sand Earth ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management What estimate would you give for the variance in above problem ? 54 36 9 81 54 36 9 81 ANSWER DOWNLOAD EXAMIANS APP