Construction Planning and Management The probability of completion of any activity within its expected time is 0.841 1 0.999 0.5 0.841 1 0.999 0.5 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The critical activity has None of these Minimum float Zero float Maximum float None of these Minimum float Zero float Maximum float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In the given figure, the network of a project represents Activity of an excavation which starts at event No. 1 and ends at even No. 2 Activity of an excavation of a footing Activity of excavation which takes 8 units of time None of these Activity of an excavation which starts at event No. 1 and ends at even No. 2 Activity of an excavation of a footing Activity of excavation which takes 8 units of time None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as Interfering float Free float Duration Total float Interfering float Free float Duration Total float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A contractor has two options;(l) : Invest his money in project A or (II) : Invest his money in project B. If he decides to invest in A, for every rupee invested, he is assured of doubling his money in ten years. If he decides to invest in B, he is assured of making his money 1.5 times in 5 years. If the contractor values his money at 10% interest rate, he should invest in neither of the two projects could invest in either of the two projects should invest in project A should invest in project B should invest in neither of the two projects could invest in either of the two projects should invest in project A should invest in project B ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements:In the critical path method of construction planning, Free Float can be.1. Greater than Total Float.2. Greater than Independent Float3. Equal to Total Float.4. Less than Independent Float 1 and 2 are correct 1 and 4 are correct 2 and 3 are correct 1 and 4 are correct 1 and 2 are correct 1 and 4 are correct 2 and 3 are correct 1 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP