Construction Planning and Management The probability of completion of any activity within its expected time is 0.999 0.841 0.5 1 0.999 0.841 0.5 1 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the excavation of earth is done manually then it costs Rs. 10 per cum. A machine can excavate at a fixed cost of Rs. 4000 plus a variable cost of Rs. 2 per cum. The quantity of earth for which the cost of excavation by machine will be equal to the cost of manual excavation is 1000 cum 2000 cum 1500 cum 500 cum 1000 cum 2000 cum 1500 cum 500 cum ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following operations: 1. Drilling 2. Blasting 3. Mucking 4. Placing steel 5. Placing concrete The correct sequence of these operations in tunnel construction is 1, 3, 4, 2, 5 1, 2, 4, 3, 5 1, 2, 3, 4, 5 1, 3, 2, 4, 5 1, 3, 4, 2, 5 1, 2, 4, 3, 5 1, 2, 3, 4, 5 1, 3, 2, 4, 5 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Preliminary project report for a road project must contain The contract documents for inviting tenders The several alternatives of the project that have been considered The detailed estimated cost based on detailed design The soil survey, traffic survey, concept design and approximate cost The contract documents for inviting tenders The several alternatives of the project that have been considered The detailed estimated cost based on detailed design The soil survey, traffic survey, concept design and approximate cost ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The reduction in project time normally results in Increasing the direct cost and decreasing the indirect cost Decreasing the direct cost and indirect cost both Increasing the direct cost and indirect cost both Decreasing the direct cost and increasing indirect cost Increasing the direct cost and decreasing the indirect cost Decreasing the direct cost and indirect cost both Increasing the direct cost and indirect cost both Decreasing the direct cost and increasing indirect cost ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A father notes that when his teenage daughter uses the telephone, she takes not less than 6 minutes for a call and som? times as much as an hour. Fifteen minutes call are more frequent than calls of any other duration. If these phone calls were an activity in PERT project, then phone calls expected duration will be 20.143 minutes 15 minutes 27 minutes 21 minutes 20.143 minutes 15 minutes 27 minutes 21 minutes ANSWER DOWNLOAD EXAMIANS APP