Construction Planning and Management
Consider the following statements:In the critical path method of construction planning, Free Float can be.1. Greater than Total Float.2. Greater than Independent Float3. Equal to Total Float.4. Less than Independent Float

1 and 2 are correct
1 and 4 are correct
1 and 4 are correct
2 and 3 are correct