Construction Planning and Management
Consider the following statements:In the critical path method of construction planning, Free Float can be.1. Greater than Total Float.2. Greater than Independent Float3. Equal to Total Float.4. Less than Independent Float

1 and 4 are correct
1 and 2 are correct
2 and 3 are correct
1 and 4 are correct

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Free float is mainly used to

Identify the activities, which can be delayed without affecting the total float of succeeding activity
Identify the activities which can be delayed without affecting the total float of preceding activity
Establish priorities
Identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Preliminary project report for a road project must contain

The soil survey, traffic survey, concept design and approximate cost
The several alternatives of the project that have been considered
The detailed estimated cost based on detailed design
The contract documents for inviting tenders

ANSWER DOWNLOAD EXAMIANS APP