Construction Planning and Management
Consider the following statements:In the critical path method of construction planning, Free Float can be.1. Greater than Total Float.2. Greater than Independent Float3. Equal to Total Float.4. Less than Independent Float

2 and 3 are correct
1 and 2 are correct
1 and 4 are correct
1 and 4 are correct

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Pick up the correct statement from the following with regards to C.P.M. network analysis of projects

The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time
All listed here
The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time
Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity

ANSWER DOWNLOAD EXAMIANS APP