Construction Planning and Management
Consider the following statements:In the critical path method of construction planning, Free Float can be.1. Greater than Total Float.2. Greater than Independent Float3. Equal to Total Float.4. Less than Independent Float

2 and 3 are correct
1 and 4 are correct
1 and 2 are correct
1 and 4 are correct

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
The reduction in project time normally results in

Decreasing the direct cost and indirect cost both
Increasing the direct cost and decreasing the indirect cost
Decreasing the direct cost and increasing indirect cost
Increasing the direct cost and indirect cost both

ANSWER DOWNLOAD EXAMIANS APP