Construction Planning and Management
Consider the following statements:In the critical path method of construction planning, Free Float can be.1. Greater than Total Float.2. Greater than Independent Float3. Equal to Total Float.4. Less than Independent Float

1 and 2 are correct
1 and 4 are correct
1 and 4 are correct
2 and 3 are correct

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Crash project duration is obtained by summing the

Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities
Crash durations for all activities
Normal durations for all the activities
Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Total float for any activity is defined as the difference between

Its earliest finish time and earliest start time for its successor activity
Its latest finish time and earliest start time for its successor activity
Its latest start time and earliest start time
Its latest start time and earliest finish time