Construction Planning and Management The process of incorporating changes and rescheduling or replanning is called Updating Resource smoothening Resource levelling Critical path scheduling Updating Resource smoothening Resource levelling Critical path scheduling ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A critical ratio scheduling Is a dynamic system None of these Adjusts automatically changes in activity progress Determines the status of each activity Is a dynamic system None of these Adjusts automatically changes in activity progress Determines the status of each activity ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following earth moving machines has the shortest cycle time? Drag line Hoe Dipper shovel Clam shell Drag line Hoe Dipper shovel Clam shell ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A machine costs Rs. 20000 and its useful life is 8 years. The money is borrowed at 8% interest per annum. The capital recovery factor at 8% interest per annum for 8 years is 0.174. The annual equipment cost of the machine will be Rs. 5220 Rs. 3480 Rs. 6960 Rs. 1740 Rs. 5220 Rs. 3480 Rs. 6960 Rs. 1740 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For completion of a project, the critical path of the network represents Maximum time Minimum cost Minimum time Maximum cost Maximum time Minimum cost Minimum time Maximum cost ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following activities in a building construction:1. Concreting of roof slabs2. Brick-jelly lime concrete terracing3. Erection of form work for slab4. Construction of parapet wall in terraceThe correct sequence of these activities is 1, 3, 4, 2 3, 1, 2, 4 3, 1, 4, 2 1, 3, 2, 4 1, 3, 4, 2 3, 1, 2, 4 3, 1, 4, 2 1, 3, 2, 4 ANSWER DOWNLOAD EXAMIANS APP