Construction Planning and Management The process of incorporating changes and rescheduling or replanning is called Resource levelling Resource smoothening Updating Critical path scheduling Resource levelling Resource smoothening Updating Critical path scheduling ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the expected time for completion of a project is 10 days with a standard deviation of 2 days, the expected time of completion of the project with 99.9% probability is 6 days 10 days 16 days 4 days 6 days 10 days 16 days 4 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For the execution of a project, a contractor is An agency A firm All listed here A person An agency A firm All listed here A person ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements:In the critical path method of construction planning, Free Float can be.1. Greater than Total Float.2. Greater than Independent Float3. Equal to Total Float.4. Less than Independent Float 1 and 2 are correct 1 and 4 are correct 2 and 3 are correct 1 and 4 are correct 1 and 2 are correct 1 and 4 are correct 2 and 3 are correct 1 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management While scheduling a project by C.P.M. Required time for each activity is established Net work is drawn by connecting the activities and the events All listed here A project is divided into various activities Required time for each activity is established Net work is drawn by connecting the activities and the events All listed here A project is divided into various activities ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management PERT technique of network analysis is mainly useful for Large and complex projects Small projects Research and development projects Deterministic activities Large and complex projects Small projects Research and development projects Deterministic activities ANSWER DOWNLOAD EXAMIANS APP