Construction Planning and Management The process of incorporating changes and rescheduling or replanning is called Resource levelling Updating Critical path scheduling Resource smoothening Resource levelling Updating Critical path scheduling Resource smoothening ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Pick up the correct statement from the following with regards to C.P.M. network analysis of projects All listed here Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time All listed here Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements:In the critical path method of construction planning, Free Float can be.1. Greater than Total Float.2. Greater than Independent Float3. Equal to Total Float.4. Less than Independent Float 1 and 2 are correct 2 and 3 are correct 1 and 4 are correct 1 and 4 are correct 1 and 2 are correct 2 and 3 are correct 1 and 4 are correct 1 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the expected time of completion of a project is 60 weeks with a standard deviation of 5 weeks, the probability of completing the project in 50 weeks and 65 weeks respectively will be 97.7% and 84.1% 2.3% and 84.1% 15.9% and 97.7% 97.7 % and 15.9% 97.7% and 84.1% 2.3% and 84.1% 15.9% and 97.7% 97.7 % and 15.9% ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A contractor has two options;(l) : Invest his money in project A or (II) : Invest his money in project B. If he decides to invest in A, for every rupee invested, he is assured of doubling his money in ten years. If he decides to invest in B, he is assured of making his money 1.5 times in 5 years. If the contractor values his money at 10% interest rate, he should invest in project A could invest in either of the two projects should invest in project B should invest in neither of the two projects should invest in project A could invest in either of the two projects should invest in project B should invest in neither of the two projects ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Works costing less than Rs. 20,000 are treated as Minor projects All listed here Major projects Any project Minor projects All listed here Major projects Any project ANSWER DOWNLOAD EXAMIANS APP