Construction Planning and Management Pick up the correct statement from the following with regards to C.P.M. network analysis of projects The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity All listed here The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the output of a drag-line for 90° angle of swing at optimum depth of cut is X, then the output for 120° angle of swing at 120 % of optimum depth of cut will be More than X Any of the above Equal to X Less than X More than X Any of the above Equal to X Less than X ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements:In the bar chart planning1. Interdependence of the operations cannot be portrayed.2. Progress of work can be measured.3. Spare time of the activities can be determined.4. Schedule cannot be updated. 1, 2 and 4 are correct 2, 3 and 4 are correct 1, 2 and 3 are correct 1 and 4 are correct 1, 2 and 4 are correct 2, 3 and 4 are correct 1, 2 and 3 are correct 1 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Economic saving of time results by crashing Cheapest critical activity Costliest critical activity Costliest noncritical activity Cheapest noncritical activity Cheapest critical activity Costliest critical activity Costliest noncritical activity Cheapest noncritical activity ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Free float for any activity is defined as the difference between its earliest finish time and latest start time for its successor activity its latest finish time and earliest start time for its successor activity its earliest finish time and earliest start time for its successor activity its latest start time and earliest start time its earliest finish time and latest start time for its successor activity its latest finish time and earliest start time for its successor activity its earliest finish time and earliest start time for its successor activity its latest start time and earliest start time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management An excavator costs Rs. 20,00,000 and has an estimated life of 8 years. It has no salvage value at the end of 8 years. The book value of the excavator at the end of 3 years using general double declining balance method is Rs. 10,50,000 Rs. 8,75,000 Rs. 8,43,750 Rs. 11,56,250 Rs. 10,50,000 Rs. 8,75,000 Rs. 8,43,750 Rs. 11,56,250 ANSWER DOWNLOAD EXAMIANS APP