Construction Planning and Management Pick up the correct statement from the following with regards to C.P.M. network analysis of projects The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity All listed here The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Total float for any activity is defined as the difference between Its latest start time and earliest start time Its earliest finish time and earliest start time for its successor activity Its latest finish time and earliest start time for its successor activity Its latest start time and earliest finish time Its latest start time and earliest start time Its earliest finish time and earliest start time for its successor activity Its latest finish time and earliest start time for its successor activity Its latest start time and earliest finish time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Critical path lies along the activities having total float Same Negative Zero Positive Same Negative Zero Positive ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Interfering float is the difference between Total float and free float Free float and independent float Total float and independent float None of these Total float and free float Free float and independent float Total float and independent float None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If to, tp and tm are the optimistic, pessimistic and most likely time estimates of an activity respectively, the expected time t of the activity will be to + 4tm+ tp/4 to + 4tm+ tp/5 to + 4tm+ tp/6 to + 3tm+ tp/3 to + 4tm+ tp/4 to + 4tm+ tp/5 to + 4tm+ tp/6 to + 3tm+ tp/3 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the output of a drag-line for 90° angle of swing at optimum depth of cut is X, then the output for 120° angle of swing at 120 % of optimum depth of cut will be Less than X Equal to X Any of the above More than X Less than X Equal to X Any of the above More than X ANSWER DOWNLOAD EXAMIANS APP