Construction Planning and Management Pick up the correct statement from the following with regards to C.P.M. network analysis of projects The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time All listed here Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time All listed here Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Pick up the PERT event from the following: Laying of concrete started Digging of foundation started Digging of foundation completed All listed here Laying of concrete started Digging of foundation started Digging of foundation completed All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Assertion (A): Activity 57 is critical.Reason (R): Earliest finish time and latest finish time for events 57 are same Both A and R is incorrect R is correct but A is not correct A is correct but R is not correct Both A and R is correct Both A and R is incorrect R is correct but A is not correct A is correct but R is not correct Both A and R is correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The reduction in project time normally results in Increasing the direct cost and indirect cost both Decreasing the direct cost and increasing indirect cost Increasing the direct cost and decreasing the indirect cost Decreasing the direct cost and indirect cost both Increasing the direct cost and indirect cost both Decreasing the direct cost and increasing indirect cost Increasing the direct cost and decreasing the indirect cost Decreasing the direct cost and indirect cost both ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Optimistic time, most likely time and pessimistic times for the activities of a network in the given figure are written above their arrows. If the contractual obligation time for the project is 75, the latest occurrence time for the event 2, is 25 35 20 15 25 35 20 15 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Crash project duration is obtained by summing the Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities Normal durations for all the activities Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities Crash durations for all activities Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities Normal durations for all the activities Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities Crash durations for all activities ANSWER DOWNLOAD EXAMIANS APP