Construction Planning and Management Pick up the correct statement from the following with regards to C.P.M. network analysis of projects All listed here The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time All listed here The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A contractor has two options;(l) : Invest his money in project A or (II) : Invest his money in project B. If he decides to invest in A, for every rupee invested, he is assured of doubling his money in ten years. If he decides to invest in B, he is assured of making his money 1.5 times in 5 years. If the contractor values his money at 10% interest rate, he could invest in either of the two projects should invest in project B should invest in project A should invest in neither of the two projects could invest in either of the two projects should invest in project B should invest in project A should invest in neither of the two projects ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The direct cost of a project with respect to normal time is Minimum Zero Maximum Infinite Minimum Zero Maximum Infinite ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following operations:1. Drilling2. Blasting3. Mucking4. Placing steel5. Placing concreteThe correct sequence of these operations in tunnel construction is 1, 2, 3, 4, 5 1, 2, 4, 3, 5 1, 3, 2, 4, 5 1, 3, 4, 2, 5 1, 2, 3, 4, 5 1, 2, 4, 3, 5 1, 3, 2, 4, 5 1, 3, 4, 2, 5 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The reduction in project time normally results in Increasing the direct cost and indirect cost both Decreasing the direct cost and indirect cost both Decreasing the direct cost and increasing indirect cost Increasing the direct cost and decreasing the indirect cost Increasing the direct cost and indirect cost both Decreasing the direct cost and indirect cost both Decreasing the direct cost and increasing indirect cost Increasing the direct cost and decreasing the indirect cost ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A wheeled tractor hauling unit is working on firm earth. The total loaded weight distribution of this unit is:Drive wheels: 25000 kgScraper wheels: 10000 kgIf the coefficient of traction for wheeled tractor on firm earth is 0.5, the rimpull which this tractor can exert without slipping is 12500 kg 10000 kg 22500 kg 5000 kg 12500 kg 10000 kg 22500 kg 5000 kg ANSWER DOWNLOAD EXAMIANS APP