Construction Planning and Management
Latest start of an activity is always

equal to latest event time of preceding node
less than latest event time of preceding node
greater than or equal to latest event time of preceding node
less than or equal to latest event time of preceding node

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Mobilization advance up to 10% of the cost of work is given to a contractor

For the purchase of construction materials
For the payment of advances to labour and other staff
For all activities required to start the work at site on finalization of the contract document
On commencement of work at site for payment of loan taken by him

ANSWER DOWNLOAD EXAMIANS APP