Construction Planning and Management Latest start of an activity is always less than latest event time of preceding node greater than or equal to latest event time of preceding node less than or equal to latest event time of preceding node equal to latest event time of preceding node less than latest event time of preceding node greater than or equal to latest event time of preceding node less than or equal to latest event time of preceding node equal to latest event time of preceding node ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Free float is mainly used to Identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities Establish priorities Identify the activities which can be delayed without affecting the total float of preceding activity Identify the activities, which can be delayed without affecting the total float of succeeding activity Identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities Establish priorities Identify the activities which can be delayed without affecting the total float of preceding activity Identify the activities, which can be delayed without affecting the total float of succeeding activity ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Pick up the correct statement from the following with regards to C.P.M. network analysis of projects The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity All listed here The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity All listed here The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Critical path method Is an improvement upon bar chart method All listed here Avoids delays which are very common in bar charts Provides a realistic approach to daily problems Is an improvement upon bar chart method All listed here Avoids delays which are very common in bar charts Provides a realistic approach to daily problems ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements for a power shovel:(i) Output can be increased by reducing the angle of swing for a given depth of cut.(ii) For a given angle of swing, output will be maximum at optimum depth of cut.(iii) Output can be increased by keeping the depth of cut less than optimum depth.(iv) Output can be increased by increasing the size of shovel. (ii), (iii) and (iv) are correct (i), (iii) and (iv) are correct (i) and (iv) are correct (i), (ii) and (iv) are correct (ii), (iii) and (iv) are correct (i), (iii) and (iv) are correct (i) and (iv) are correct (i), (ii) and (iv) are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A golden rule for the procurement of construction stones, suggests 67% at the site and 33% under procurement 33% at the site and 67% under procurement 50% at the site and 50% under procurement 100% at the site 67% at the site and 33% under procurement 33% at the site and 67% under procurement 50% at the site and 50% under procurement 100% at the site ANSWER DOWNLOAD EXAMIANS APP