Construction Planning and Management Latest start of an activity is always less than or equal to latest event time of preceding node greater than or equal to latest event time of preceding node equal to latest event time of preceding node less than latest event time of preceding node less than or equal to latest event time of preceding node greater than or equal to latest event time of preceding node equal to latest event time of preceding node less than latest event time of preceding node ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the excavation of earth is done manually then it costs Rs. 10 per cum. A machine can excavate at a fixed cost of Rs. 4000 plus a variable cost of Rs. 2 per cum. The quantity of earth for which the cost of excavation by machine will be equal to the cost of manual excavation is 1500 cum 500 cum 2000 cum 1000 cum 1500 cum 500 cum 2000 cum 1000 cum ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following earth moving machines has the shortest cycle time? Dipper shovel Clam shell Drag line Hoe Dipper shovel Clam shell Drag line Hoe ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time by which a particular activity can be delayed without affecting the preceding and succeeding activities is known as Free float Independent float Total float Interfering float Free float Independent float Total float Interfering float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For the network shown in the given figure, the expected time for the activity 1-2 is 4 2-3 is 7 3-4 is 8 All listed here 1-2 is 4 2-3 is 7 3-4 is 8 All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Critical path lies along the activities having total float Negative Same Zero Positive Negative Same Zero Positive ANSWER DOWNLOAD EXAMIANS APP