Construction Planning and Management The difference between the time avail-to do a job and the time required to do the job, is known as Constraint Event Duration Float Constraint Event Duration Float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The Overall in-charge of an organization at the site responsible for the execution of the works, is Junior Engineer Assistant Engineer Engineer Executive Engineer Junior Engineer Assistant Engineer Engineer Executive Engineer ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For the supply of materials for concrete, form work reinforcing and placing of concrete, removal of form work and curing of concrete, number of bar(s) required on bar chart, is 3 4 1 2 3 4 1 2 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Various activities of a project, are shown on bar charts by Vertical lines Dots Crosses Horizontal lines Vertical lines Dots Crosses Horizontal lines ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The main disadvantage of line organization, is Extraordinary delay in communications All listed here Top level executions over work Rigid structure Extraordinary delay in communications All listed here Top level executions over work Rigid structure ANSWER DOWNLOAD EXAMIANS APP