CONSTRUCTION PLANNING AND MANAGEMENT

Construction Planning and Management
The difference between the time avail-to do a job and the time required to do the job, is known as

Duration
Float
Event
Constraint

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
The Overall in-charge of an organization at the site responsible for the execution of the works, is

Junior Engineer
Engineer
Executive Engineer
Assistant Engineer

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
For the supply of materials for concrete, form work reinforcing and placing of concrete, removal of form work and curing of concrete, number of bar(s) required on bar chart, is

3
2
4
1

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Various activities of a project, are shown on bar charts by

Vertical lines
Dots
Horizontal lines
Crosses

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
The main disadvantage of line organization, is

All listed here
Top level executions over work
Rigid structure
Extraordinary delay in communications

ANSWER DOWNLOAD EXAMIANS APP
  • «
  • 1
  • 2
  • 3
  • 4
  • 5
  • ...
  • 31
  • »

GO TO PAGE

DOWNLOAD APP

  • APPLE
    from app store
  • ANDROID
    from play store

SEARCH

LOGIN HERE


  • GOOGLE

FIND US

  • 1.70K
    FOLLOW US
  • EXAMIANSSTUDY FOR YOUR DREAMS.
  • SUPPORT :SUPPORT EMAIL ACCOUNT : examians@yahoo.com

OTHER WEBSITES

  • GUJARATI MCQ
  • ACCOUNTIANS

QUICK LINKS

  • HOME
  • QUIZ
  • PRIVACY POLICY
  • DISCLAIMER
  • TERMS & CONDITIONS
  • CONTACT US
↑