Construction Planning and Management The normal time required for the completion of project in the above problem is 13 days 19 days 14 days 9 days 13 days 19 days 14 days 9 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If to, tp and tm are the optimistic, pessimistic and most likely time estimates of an activity respectively, the expected time t of the activity will be to + 3tm+ tp/3 to + 4tm+ tp/6 to + 4tm+ tp/4 to + 4tm+ tp/5 to + 3tm+ tp/3 to + 4tm+ tp/6 to + 4tm+ tp/4 to + 4tm+ tp/5 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A construction schedule is prepared after collecting All listed here Output of labour Number of operations Output of machinery All listed here Output of labour Number of operations Output of machinery ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively 4 and 5/6 3.5 and 5/6 5 and 25/36 3.5 and 25/36 4 and 5/6 3.5 and 5/6 5 and 25/36 3.5 and 25/36 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The first stage of a construction, is Preparation of estimate Preparation of tender Survey of the site Initiation of proposal Preparation of estimate Preparation of tender Survey of the site Initiation of proposal ANSWER DOWNLOAD EXAMIANS APP