Construction Planning and Management Power stations are generally treated as Electrical construction Heavy construction Light construction Industrial construction Electrical construction Heavy construction Light construction Industrial construction ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The grade resistance factor for an earth moving machine can be obtained by multiplying grade percentage by a factor approximately equal to 20 kg/tonne 2 kg/tonne 6 kg/tonne 9 kg/tonne 20 kg/tonne 2 kg/tonne 6 kg/tonne 9 kg/tonne ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For the supply of materials for concrete, form work reinforcing and placing of concrete, removal of form work and curing of concrete, number of bar(s) required on bar chart, is 3 2 4 1 3 2 4 1 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Preliminary project report for a road project must contain The contract documents for inviting tenders The soil survey, traffic survey, concept design and approximate cost The detailed estimated cost based on detailed design The several alternatives of the project that have been considered The contract documents for inviting tenders The soil survey, traffic survey, concept design and approximate cost The detailed estimated cost based on detailed design The several alternatives of the project that have been considered ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the optimistic time, most likely time and pessimistic time for activity A are 4, 6 and 8 respectively and for activity B are 5, 5.5 and 9 respectively, then None of these expected time of activity A is greater than the expected time of activity B expected time of both activities A and B are same expected time of activity B is greater than the expected time of activity A None of these expected time of activity A is greater than the expected time of activity B expected time of both activities A and B are same expected time of activity B is greater than the expected time of activity A ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Assertion (A): Activity 57 is critical.Reason (R): Earliest finish time and latest finish time for events 57 are same Both A and R is correct Both A and R is incorrect A is correct but R is not correct R is correct but A is not correct Both A and R is correct Both A and R is incorrect A is correct but R is not correct R is correct but A is not correct ANSWER DOWNLOAD EXAMIANS APP