Construction Planning and Management Power stations are generally treated as Heavy construction Light construction Industrial construction Electrical construction Heavy construction Light construction Industrial construction Electrical construction ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as Free float Event Constraint Dummy Free float Event Constraint Dummy ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the excavation of earth is done manually then it costs Rs. 10 per cum. A machine can excavate at a fixed cost of Rs. 4000 plus a variable cost of Rs. 2 per cum. The quantity of earth for which the cost of excavation by machine will be equal to the cost of manual excavation is 2000 cum 500 cum 1500 cum 1000 cum 2000 cum 500 cum 1500 cum 1000 cum ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Output of a bulldozer is (i) Increased if drawbar HP of the tractor is increased for a given hauling distance (ii) Decreased if drawbar HP of the tractor is increased for a given hauling distance (iii) Increased if the hauling distance is increased for a given drawbar HP of the tractor (iv) Decreased if the hauling distance is increased for a given drawbar HP of the tractor (i) and (iv) are correct (i) and (iii) are correct (ii) and (iii) are correct (ii) and (iv) are correct (i) and (iv) are correct (i) and (iii) are correct (ii) and (iii) are correct (ii) and (iv) are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time with which direct cost does not reduce with the increase in time is known as Optimistic time Standard time Normal time Crash time Optimistic time Standard time Normal time Crash time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The three time estimates for the activities of the network shown in the given figure are shown above their arrows. The earliest expected time for the event 4, is 14 24 None of these 19 14 24 None of these 19 ANSWER DOWNLOAD EXAMIANS APP