Construction Planning and Management Power stations are generally treated as Industrial construction Light construction Heavy construction Electrical construction Industrial construction Light construction Heavy construction Electrical construction ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Critical path lies along the activities having total float Negative Positive Same Zero Negative Positive Same Zero ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following operations: 1. Drilling 2. Blasting 3. Mucking 4. Placing steel 5. Placing concrete The correct sequence of these operations in tunnel construction is 1, 2, 3, 4, 5 1, 3, 2, 4, 5 1, 3, 4, 2, 5 1, 2, 4, 3, 5 1, 2, 3, 4, 5 1, 3, 2, 4, 5 1, 3, 4, 2, 5 1, 2, 4, 3, 5 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The area under the Beta distribution curve is divided into two equal parts by Optimistic time Most likely time Pessimistic time Expected time Optimistic time Most likely time Pessimistic time Expected time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements:In the bar chart planning1. Interdependence of the operations cannot be portrayed.2. Progress of work can be measured.3. Spare time of the activities can be determined.4. Schedule cannot be updated. 1, 2 and 3 are correct 1, 2 and 4 are correct 1 and 4 are correct 2, 3 and 4 are correct 1, 2 and 3 are correct 1, 2 and 4 are correct 1 and 4 are correct 2, 3 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as Dummy Event Free float Constraint Dummy Event Free float Constraint ANSWER DOWNLOAD EXAMIANS APP