Construction Planning and Management
The reduction in project time normally results in

Increasing the direct cost and indirect cost both
Decreasing the direct cost and increasing indirect cost
Increasing the direct cost and decreasing the indirect cost
Decreasing the direct cost and indirect cost both

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Mobilization advance up to 10% of the cost of work is given to a contractor

On commencement of work at site for payment of loan taken by him
For all activities required to start the work at site on finalization of the contract document
For the purchase of construction materials
For the payment of advances to labour and other staff

ANSWER DOWNLOAD EXAMIANS APP