Construction Planning and Management Power stations are generally treated as Electrical construction Industrial construction Heavy construction Light construction Electrical construction Industrial construction Heavy construction Light construction ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as Total float Free float Duration Interfering float Total float Free float Duration Interfering float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following operations: 1. Drilling 2. Blasting 3. Mucking 4. Placing steel 5. Placing concrete The correct sequence of these operations in tunnel construction is 1, 3, 2, 4, 5 1, 3, 4, 2, 5 1, 2, 4, 3, 5 1, 2, 3, 4, 5 1, 3, 2, 4, 5 1, 3, 4, 2, 5 1, 2, 4, 3, 5 1, 2, 3, 4, 5 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the expected time of completion of a project is 60 weeks with a standard deviation of 5 weeks, the probability of completing the project in 50 weeks and 65 weeks respectively will be 97.7 % and 15.9% 97.7% and 84.1% 2.3% and 84.1% 15.9% and 97.7% 97.7 % and 15.9% 97.7% and 84.1% 2.3% and 84.1% 15.9% and 97.7% ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Critical path Is always longest Is always shortest May be shortest May be longest Is always longest Is always shortest May be shortest May be longest ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Various activities of a project, are shown on bar charts by Vertical lines Dots Crosses Horizontal lines Vertical lines Dots Crosses Horizontal lines ANSWER DOWNLOAD EXAMIANS APP