Construction Planning and Management Railway projects are treated as None of these Light construction Heavy construction Industrial construction None of these Light construction Heavy construction Industrial construction ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the excavation of earth is done manually then it costs Rs. 10 per cum. A machine can excavate at a fixed cost of Rs. 4000 plus a variable cost of Rs. 2 per cum. The quantity of earth for which the cost of excavation by machine will be equal to the cost of manual excavation is 1500 cum 1000 cum 2000 cum 500 cum 1500 cum 1000 cum 2000 cum 500 cum ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Construction team means An engineer An architect An owner All listed here An engineer An architect An owner All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Assertion (A): Activity 57 is critical.Reason (R): Earliest finish time and latest finish time for events 57 are same A is correct but R is not correct Both A and R is correct Both A and R is incorrect R is correct but A is not correct A is correct but R is not correct Both A and R is correct Both A and R is incorrect R is correct but A is not correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time which results in the least possible construction cost of an activity, is known as Normal time Crash time Slow time Standard time Normal time Crash time Slow time Standard time ANSWER DOWNLOAD EXAMIANS APP