Construction Planning and Management Preliminary project report for a road project must contain The contract documents for inviting tenders The several alternatives of the project that have been considered The detailed estimated cost based on detailed design The soil survey, traffic survey, concept design and approximate cost The contract documents for inviting tenders The several alternatives of the project that have been considered The detailed estimated cost based on detailed design The soil survey, traffic survey, concept design and approximate cost ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following operations: 1. Drilling 2. Blasting 3. Mucking 4. Placing steel 5. Placing concrete The correct sequence of these operations in tunnel construction is 1, 2, 4, 3, 5 1, 2, 3, 4, 5 1, 3, 4, 2, 5 1, 3, 2, 4, 5 1, 2, 4, 3, 5 1, 2, 3, 4, 5 1, 3, 4, 2, 5 1, 3, 2, 4, 5 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The salient feature of functional organization is All listed here Each individual maintains functional efficiency Strict adherence to specifications Separation of planning and design part All listed here Each individual maintains functional efficiency Strict adherence to specifications Separation of planning and design part ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time corresponding to minimum total project cost is Crash time Between normal time and crash time Optimistic time Normal time Crash time Between normal time and crash time Optimistic time Normal time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The process of incorporating changes and rescheduling or replanning is called Resource smoothening Updating Critical path scheduling Resource levelling Resource smoothening Updating Critical path scheduling Resource levelling ANSWER DOWNLOAD EXAMIANS APP