Construction Planning and Management
In India, are prefabricated components costlier than those of traditional cast-in-situ items that the prefabricated components replace?

No, because of savings in site labour
No, because of repetitive manufacture of a number of elements
Yes, because of heavier overheads and handling cost
Yes, because of the very high order of quality control for the factory made components

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Mobilization advance up to 10% of the cost of work is given to a contractor

For the payment of advances to labour and other staff
For all activities required to start the work at site on finalization of the contract document
For the purchase of construction materials
On commencement of work at site for payment of loan taken by him

ANSWER DOWNLOAD EXAMIANS APP