Construction Planning and Management Total float for any activity is defined as the difference between Its latest start time and earliest start time Its earliest finish time and earliest start time for its successor activity Its latest finish time and earliest start time for its successor activity Its latest start time and earliest finish time Its latest start time and earliest start time Its earliest finish time and earliest start time for its successor activity Its latest finish time and earliest start time for its successor activity Its latest start time and earliest finish time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Interfering float is the difference between Free float and independent float Total float and independent float Total float and free float None of these Free float and independent float Total float and independent float Total float and free float None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Free float for any activity is defined as the difference between its earliest finish time and latest start time for its successor activity its latest start time and earliest start time its latest finish time and earliest start time for its successor activity its earliest finish time and earliest start time for its successor activity its earliest finish time and latest start time for its successor activity its latest start time and earliest start time its latest finish time and earliest start time for its successor activity its earliest finish time and earliest start time for its successor activity ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Assertion A: For a given depth of cut, the output of a power shovel can be increased by decreasing the angle of swing.Reason R: If the angle of swing is decreased, the cycle time will be decreased. Both A and R is true but R is not the correct explanation of A Both A and R is true and R is the correct explanation of A A is true but R is false A is false but R is true Both A and R is true but R is not the correct explanation of A Both A and R is true and R is the correct explanation of A A is true but R is false A is false but R is true ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements: In the critical path method of construction planning, Free Float can be. 1. Greater than Total Float. 2. Greater than Independent Float 3. Equal to Total Float. 4. Less than Independent Float 2 and 3 are correct 1 and 2 are correct 1 and 4 are correct 1 and 4 are correct 2 and 3 are correct 1 and 2 are correct 1 and 4 are correct 1 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP