Estimating and Costing The most reliable estimate is Detailed estimate Preliminary estimate Plinth area estimate Cube rate estimate Detailed estimate Preliminary estimate Plinth area estimate Cube rate estimate ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The main factor to be considered while preparing a detailed estimate, is All of these Transportation of materials Availability of materials Quantity of the materials All of these Transportation of materials Availability of materials Quantity of the materials ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The order of booking dimensions is None of these Height, breadth, length Breadth, length, height Length, breadth, height None of these Height, breadth, length Breadth, length, height Length, breadth, height ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of brick work in cement mortar in foundation and plinth per mason per day, is 1.00 m³ 1.75 m³ 1.50 m³ 1.25 m³ 1.00 m³ 1.75 m³ 1.50 m³ 1.25 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Pick up the correct statement regarding the centre line method of estimating a building Product of the centre line of the walls and area of cross-section of any item, gives total quantity of the item The centre line length is reduced by half the layer of main wall joining the partition wall All of these The centre line is worked out separately for different sections of walls of a building Product of the centre line of the walls and area of cross-section of any item, gives total quantity of the item The centre line length is reduced by half the layer of main wall joining the partition wall All of these The centre line is worked out separately for different sections of walls of a building ANSWER DOWNLOAD EXAMIANS APP