Estimating and Costing The expected out turn of brick work in cement mortar in foundation and plinth per mason per day, is 1.25 m³ 1.75 m³ 1.00 m³ 1.50 m³ 1.25 m³ 1.75 m³ 1.00 m³ 1.50 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The concrete work for the following part of the building of specified thickness is measured in square meters All of these Floors Root slabs Wall panels All of these Floors Root slabs Wall panels ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing If tensile stress of a steel rod of diameter ‘D’ is 1400 kg/cm² and bond stress is 6 kg/cm², the required bond length of the rod is 30 D 39 D 50 D 59 D 30 D 39 D 50 D 59 D ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Brick walls are measured in sq. m if the thickness of the wall is 20 cm 15 cm 10 cm None of these 20 cm 15 cm 10 cm None of these ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing In case of laying gullies, siphons, intercepting traps, the cost includes Connection to drains All of these Setting and laying Bed concreting Connection to drains All of these Setting and laying Bed concreting ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The diameter of a domestic sewer pipe laid at gradient 1 in 100 is recommended 150 mm 100 mm 200 mm 175 mm 150 mm 100 mm 200 mm 175 mm ANSWER DOWNLOAD EXAMIANS APP