Estimating and Costing The expected out turn of brick work in cement mortar in foundation and plinth per mason per day, is 1.25 m³ 1.50 m³ 1.00 m³ 1.75 m³ 1.25 m³ 1.50 m³ 1.00 m³ 1.75 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Pick up the correct statement in case of water supply. Pipes laid in trenches and pipes fixed to walls are measured separately All of these Pipes are classified according to their sizes and quality Cutting through walls and floors are included with the item Pipes laid in trenches and pipes fixed to walls are measured separately All of these Pipes are classified according to their sizes and quality Cutting through walls and floors are included with the item ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Due to change in price level, a revised estimate is prepared if the sanctioned estimate exceeds 0.05 0.025 0.04 0.02 0.05 0.025 0.04 0.02 ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The volume is measured correct to the nearest 0.03 cum 0.01 cum 0.04 cum 0.02 cum 0.03 cum 0.01 cum 0.04 cum 0.02 cum ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing A portion of an embankment having a uniform up-gradient 1 in 500 is circular with radius 1000 m of the centre line. It subtends 180° at the centre. If the height of the bank is 1 m at the lower end, and side slopes 2:1, the earth work involved. 27,000 m³ 26,500 m³ 26,000 m³ 27,500 m³ 27,000 m³ 26,500 m³ 26,000 m³ 27,500 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The trap which is provided to disconnect the house drain from the street sewer is called Master trap Intercepting trap Interception manhole All listed here Master trap Intercepting trap Interception manhole All listed here ANSWER DOWNLOAD EXAMIANS APP