Estimating and Costing The expected out turn of brick work in cement mortar in foundation and plinth per mason per day, is 1.50 m³ 1.00 m³ 1.75 m³ 1.25 m³ 1.50 m³ 1.00 m³ 1.75 m³ 1.25 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The height of the sink of wash basin above floor level is kept 75 cm to 80 cm 60 cm 80 cm 70 cm 75 cm to 80 cm 60 cm 80 cm 70 cm ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The excavation exceeding 1.5 m in width and 10 sq.m in plan area with a depth not exceeding 30 cm, is termed as Cutting Surface excavation Excavation Surface dressing Cutting Surface excavation Excavation Surface dressing ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Pick up the incorrect statement regarding a master trap from the following: The mica flap valve which opens inwards only, is fitted at the top of the inlet pipe The water seal is less than that of ordinary traps It is provided a cleaning eye at the top of the trap It is provided in between the lower end of the house drain and the street sewer The mica flap valve which opens inwards only, is fitted at the top of the inlet pipe The water seal is less than that of ordinary traps It is provided a cleaning eye at the top of the trap It is provided in between the lower end of the house drain and the street sewer ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing For 12 mm thick cement plastering 1 : 6 on 100 sq.m new brick work, the quantity of cement required, is 0.247 m³ 0.274 m³ 0.200 m³ 0.295 m³ 0.247 m³ 0.274 m³ 0.200 m³ 0.295 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Carpet area does not include the area of All of these Bath room and lavatory The walls along with doors and other openings Kitchen and pantry All of these Bath room and lavatory The walls along with doors and other openings Kitchen and pantry ANSWER DOWNLOAD EXAMIANS APP