Estimating and Costing The expected out turn of brick work in cement mortar in foundation and plinth per mason per day, is 1.50 m³ 1.75 m³ 1.25 m³ 1.00 m³ 1.50 m³ 1.75 m³ 1.25 m³ 1.00 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The slope of the outlet of 'P trap' below the horizontal is kept 12° 8° 14° 10° 12° 8° 14° 10° ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The concrete work for the following part of the building of specified thickness is measured in square meters Wall panels Root slabs Floors All of these Wall panels Root slabs Floors All of these ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The unit of measurement is per quintal for the following: Collapsible gates with rails Expanded metal wire netting M.S. reinforcement of R.C.C. works Rolling shutters Collapsible gates with rails Expanded metal wire netting M.S. reinforcement of R.C.C. works Rolling shutters ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The height of the sink of wash basin above floor level is kept 80 cm 75 cm to 80 cm 70 cm 60 cm 80 cm 75 cm to 80 cm 70 cm 60 cm ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing While estimating the qualities for the construction of a building, the correct metric unit is Liter for capacity Square meters for volume Cubic metre for area Meter for length Liter for capacity Square meters for volume Cubic metre for area Meter for length ANSWER DOWNLOAD EXAMIANS APP