Estimating and Costing The expected out turn of brick work in cement mortar in foundation and plinth per mason per day, is 1.00 m³ 1.50 m³ 1.75 m³ 1.25 m³ 1.00 m³ 1.50 m³ 1.75 m³ 1.25 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The most reliable estimate is Cube rate estimate Preliminary estimate Detailed estimate Plinth area estimate Cube rate estimate Preliminary estimate Detailed estimate Plinth area estimate ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The cross-section of a road partly in banking and partly in cutting is shown in the given figure. The area of the shaded portion is ⅓ × (b - rd)²/(s - r) ⅓ × (b - rd)²/(r + s) ⅓ × (b - rd)²/(r - s) ½ × (b + rd)²/(r - s) ⅓ × (b - rd)²/(s - r) ⅓ × (b - rd)²/(r + s) ⅓ × (b - rd)²/(r - s) ½ × (b + rd)²/(r - s) ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Due to change in price level, a revised estimate is prepared if the sanctioned estimate exceeds 0.04 0.05 0.025 0.02 0.04 0.05 0.025 0.02 ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Size, capacity and materials need be specified for Stop-cocks All of these Bib-cocks Ball valves Stop-cocks All of these Bib-cocks Ball valves ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The ground surface slopes 1 in 50 along a proposed railway embankment 150 m in length. The height of the embankment at zero chainage is 0.5 m, the width is 11 m and side slopes 2:1. If the falling gradient of the embankment is 1 in 150, the quantity of the earthwork calculated by Prismoidal formula, is 3300 m³ 3275 m³ 3250 m³ 3225 m³ 3300 m³ 3275 m³ 3250 m³ 3225 m³ ANSWER DOWNLOAD EXAMIANS APP