Estimating and Costing The expected out turn of brick work in cement mortar in foundation and plinth per mason per day, is 1.75 m³ 1.50 m³ 1.00 m³ 1.25 m³ 1.75 m³ 1.50 m³ 1.00 m³ 1.25 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The measurement is made in square metre in case of Hollow concrete block wall Cement concrete in foundation R.C.C. structure None of these Hollow concrete block wall Cement concrete in foundation R.C.C. structure None of these ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Berms are provided in canals if these are Fully in embankment Partly in excavation and partly in embankment All of these Fully in excavation Fully in embankment Partly in excavation and partly in embankment All of these Fully in excavation ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The floor area includes the area of the balcony up to 0.75 0.5 1 0.25 0.75 0.5 1 0.25 ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The reduced levels of points, 30 metres apart along the longitudinal section of a road portion between chainages 5 and 9 are shown in the given figure. If there is a uniform up-gradient of the road 120 in 1, the chainage of the point with no filling or cutting is (6 + 18) chains (6 + 12) chains None of these (6 + 15) chains (6 + 18) chains (6 + 12) chains None of these (6 + 15) chains ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The cross-section of a road partly in banking and partly in cutting is shown in the given figure. The area of the shaded portion is ½ × (b + rd)²/(r - s) ⅓ × (b - rd)²/(s - r) ⅓ × (b - rd)²/(r + s) ⅓ × (b - rd)²/(r - s) ½ × (b + rd)²/(r - s) ⅓ × (b - rd)²/(s - r) ⅓ × (b - rd)²/(r + s) ⅓ × (b - rd)²/(r - s) ANSWER DOWNLOAD EXAMIANS APP