Estimating and Costing The expected out turn of brick work in cement mortar in foundation and plinth per mason per day, is 1.25 m³ 1.00 m³ 1.75 m³ 1.50 m³ 1.25 m³ 1.00 m³ 1.75 m³ 1.50 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The following item of earth work is not measured separately. All listed here Setting out of works Site clearance Steps in deep excavation All listed here Setting out of works Site clearance Steps in deep excavation ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing If B is the width of formation, d is the height of the embankment, side slope S : 1, for a highway with no transverse slope, the area of cross-section is B + d + Sd B × d - Sd1/2 ½ (Bd + Sd2) Bd + Sd2 B + d + Sd B × d - Sd1/2 ½ (Bd + Sd2) Bd + Sd2 ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Brick walls are measured in sq. m if the thickness of the wall is 15 cm None of these 20 cm 10 cm 15 cm None of these 20 cm 10 cm ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The ground surface slopes 1 in 50 along a proposed railway embankment 150 m in length. The height of the embankment at zero chainage is 0.5 m, the width is 11 m and side slopes 2:1. If the falling gradient of the embankment is 1 in 150, the quantity of the earthwork calculated by Prismoidal formula, is 3275 m³ 3225 m³ 3300 m³ 3250 m³ 3275 m³ 3225 m³ 3300 m³ 3250 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The height of the sink of wash basin above floor level is kept 70 cm 60 cm 80 cm 75 cm to 80 cm 70 cm 60 cm 80 cm 75 cm to 80 cm ANSWER DOWNLOAD EXAMIANS APP