Estimating and Costing The expected out turn of brick work in cement mortar in foundation and plinth per mason per day, is 1.00 m³ 1.75 m³ 1.50 m³ 1.25 m³ 1.00 m³ 1.75 m³ 1.50 m³ 1.25 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing If tensile stress of a steel rod of diameter ‘D’ is 1400 kg/cm² and bond stress is 6 kg/cm², the required bond length of the rod is 30 D 39 D 59 D 50 D 30 D 39 D 59 D 50 D ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The rate of an item of work depends on Proportion of mortar Specifications of works All of these Specifications of materials Proportion of mortar Specifications of works All of these Specifications of materials ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The correct Prismoidal formula for volume is D/3 [first area + last area + 2 Ʃ Even area + 4 Ʃ odd areas] D [first area + last area + Ʃ Even area + 2 Ʃ odd areas] D/3 [first area + last area + 4 Ʃ Even area + 2 Ʃ odd areas] D/6 [first area + last area + 2 ∑ Even area + 4 ∑ odd areas] D/3 [first area + last area + 2 Ʃ Even area + 4 Ʃ odd areas] D [first area + last area + Ʃ Even area + 2 Ʃ odd areas] D/3 [first area + last area + 4 Ʃ Even area + 2 Ʃ odd areas] D/6 [first area + last area + 2 ∑ Even area + 4 ∑ odd areas] ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The volume is measured correct to the nearest 0.01 cum 0.03 cum 0.02 cum 0.04 cum 0.01 cum 0.03 cum 0.02 cum 0.04 cum ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of cement concrete 1 : 2 : 4 per mason per day is 2.5 m³ 1.5 m³ 3.5 m³ 5.0 m³ 2.5 m³ 1.5 m³ 3.5 m³ 5.0 m³ ANSWER DOWNLOAD EXAMIANS APP