Estimating and Costing The expected out turn of brick work in cement mortar in foundation and plinth per mason per day, is 1.25 m³ 1.50 m³ 1.00 m³ 1.75 m³ 1.25 m³ 1.50 m³ 1.00 m³ 1.75 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Berms are provided in canals if these are Partly in excavation and partly in embankment Fully in excavation All of these Fully in embankment Partly in excavation and partly in embankment Fully in excavation All of these Fully in embankment ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The ground surface slopes 1 in 50 along a proposed railway embankment 150 m in length. The height of the embankment at zero chainage is 0.5 m, the width is 11 m and side slopes 2:1. If the falling gradient of the embankment is 1 in 150, the quantity of the earthwork calculated by Prismoidal formula, is 3225 m³ 3275 m³ 3300 m³ 3250 m³ 3225 m³ 3275 m³ 3300 m³ 3250 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The plinth area of a building not includes Area of the walls at the floor level Area of cantilevered porch Internal shaft for sanitary installations up to 2 sq m. in area Lift and wall including landing Area of the walls at the floor level Area of cantilevered porch Internal shaft for sanitary installations up to 2 sq m. in area Lift and wall including landing ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing While estimating the qualities for the construction of a building, the correct metric unit is Cubic metre for area Meter for length Liter for capacity Square meters for volume Cubic metre for area Meter for length Liter for capacity Square meters for volume ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The weight of an item is measured correct to nearest 0.50 kg 0.75 kg 1.00 kg 0.25 kg 0.50 kg 0.75 kg 1.00 kg 0.25 kg ANSWER DOWNLOAD EXAMIANS APP