Estimating and Costing The expected out turn of brick work in cement mortar in foundation and plinth per mason per day, is 1.25 m³ 1.50 m³ 1.75 m³ 1.00 m³ 1.25 m³ 1.50 m³ 1.75 m³ 1.00 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Brick walls are measured in sq. m if the thickness of the wall is None of these 10 cm 15 cm 20 cm None of these 10 cm 15 cm 20 cm ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The rate of an item of work depends on Specifications of materials Specifications of works All of these Proportion of mortar Specifications of materials Specifications of works All of these Proportion of mortar ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The minimum width of a septic tank is taken 75 cm 90 cm 70 cm 80 cm 75 cm 90 cm 70 cm 80 cm ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing For 100 sq. m cement concrete (1 : 2: 4) 4 cm thick floor, the quantity of cement required, is 0.94 m³ 0.98 m³ 1.00 m³ 0.90 m³ 0.94 m³ 0.98 m³ 1.00 m³ 0.90 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of cement concrete 1 : 2 : 4 per mason per day is 5.0 m³ 1.5 m³ 2.5 m³ 3.5 m³ 5.0 m³ 1.5 m³ 2.5 m³ 3.5 m³ ANSWER DOWNLOAD EXAMIANS APP