Estimating and Costing The expected out turn of brick work in cement mortar in foundation and plinth per mason per day, is 1.25 m³ 1.75 m³ 1.00 m³ 1.50 m³ 1.25 m³ 1.75 m³ 1.00 m³ 1.50 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The ground surface slopes 1 in 50 along a proposed railway embankment 150 m in length. The height of the embankment at zero chainage is 0.5 m, the width is 11 m and side slopes 2:1. If the falling gradient of the embankment is 1 in 150, the quantity of the earthwork calculated by Prismoidal formula, is 3225 m³ 3275 m³ 3250 m³ 3300 m³ 3225 m³ 3275 m³ 3250 m³ 3300 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Brick walls are measured in sq. m if the thickness of the wall is 10 cm 15 cm 20 cm None of these 10 cm 15 cm 20 cm None of these ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The concrete work for the following part of the building of specified thickness is measured in square meters All of these Root slabs Wall panels Floors All of these Root slabs Wall panels Floors ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of 12 mm plastering with cement mortar is 4.0 sq m 8.0 sq m 6.0 sq m 2.5 sq m 4.0 sq m 8.0 sq m 6.0 sq m 2.5 sq m ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The weight of an item is measured correct to nearest 1.00 kg 0.75 kg 0.50 kg 0.25 kg 1.00 kg 0.75 kg 0.50 kg 0.25 kg ANSWER DOWNLOAD EXAMIANS APP