Estimating and Costing The expected out turn of brick work in cement mortar in foundation and plinth per mason per day, is 1.25 m³ 1.00 m³ 1.50 m³ 1.75 m³ 1.25 m³ 1.00 m³ 1.50 m³ 1.75 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The diameter of a domestic sewer pipe laid at gradient 1 in 100 is recommended 100 mm 150 mm 200 mm 175 mm 100 mm 150 mm 200 mm 175 mm ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing For 100 sq. m cement concrete (1 : 2: 4) 4 cm thick floor, the quantity of cement required, is 0.98 m³ 1.00 m³ 0.94 m³ 0.90 m³ 0.98 m³ 1.00 m³ 0.94 m³ 0.90 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing According to Indian Standards Institute, the actual size of modular bricks is 20 cm x 10 cm x 10 cm 25 cm x 13 cm x 7.5 cm 19 cm x 9 cm x 9 cm 23 cm x 11.5 cm x 7.5 cm 20 cm x 10 cm x 10 cm 25 cm x 13 cm x 7.5 cm 19 cm x 9 cm x 9 cm 23 cm x 11.5 cm x 7.5 cm ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Pick up the incorrect statement regarding a master trap from the following: It is provided a cleaning eye at the top of the trap The water seal is less than that of ordinary traps It is provided in between the lower end of the house drain and the street sewer The mica flap valve which opens inwards only, is fitted at the top of the inlet pipe It is provided a cleaning eye at the top of the trap The water seal is less than that of ordinary traps It is provided in between the lower end of the house drain and the street sewer The mica flap valve which opens inwards only, is fitted at the top of the inlet pipe ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing While estimating the qualities for the construction of a building, the correct metric unit is Meter for length Square meters for volume Liter for capacity Cubic metre for area Meter for length Square meters for volume Liter for capacity Cubic metre for area ANSWER DOWNLOAD EXAMIANS APP