Estimating and Costing The expected out turn of brick work in cement mortar in foundation and plinth per mason per day, is 1.00 m³ 1.75 m³ 1.25 m³ 1.50 m³ 1.00 m³ 1.75 m³ 1.25 m³ 1.50 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Cost of fittings and their fixing is specified for the following sanitary fittings Lavatory basins Water closets All listed here Flushing pipes Lavatory basins Water closets All listed here Flushing pipes ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The area of a sloping surface of a protective embankment of mean height‘d’, side slopes S: 1 and length ‘L’ is L.D √(1 + s²) √[d² × (ds)²] d × d × s 2 L.D √(1 + s²) L.D √(1 + s²) √[d² × (ds)²] d × d × s 2 L.D √(1 + s²) ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing In the mid-section formula The area of mid-sections is calculated by using mean depth The mean depth is the average of depths of two consecutive sections The volume of the earth work is calculated by multiplying the mid-section area by the distance between the two original sections All of these The area of mid-sections is calculated by using mean depth The mean depth is the average of depths of two consecutive sections The volume of the earth work is calculated by multiplying the mid-section area by the distance between the two original sections All of these ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing While estimating the qualities for the construction of a building, the correct metric unit is Square meters for volume Cubic metre for area Liter for capacity Meter for length Square meters for volume Cubic metre for area Liter for capacity Meter for length ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing A cement concrete road is 1000 m long, 8 m wide and 15 cm thick over the sub-base of 10 cm thick gravel. The box cutting in road crust is 1000 m3 2000 m3 1500 m3 500 m3 1000 m3 2000 m3 1500 m3 500 m3 ANSWER DOWNLOAD EXAMIANS APP