Estimating and Costing The expected out turn of brick work in cement mortar in foundation and plinth per mason per day, is 1.75 m³ 1.00 m³ 1.50 m³ 1.25 m³ 1.75 m³ 1.00 m³ 1.50 m³ 1.25 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The brick work is measured in sq metre, in case of All of these Honey comb brick work Half brick walls or the partition Brick flat soling All of these Honey comb brick work Half brick walls or the partition Brick flat soling ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The slope of the outlet of 'P trap' below the horizontal is kept 12° 10° 8° 14° 12° 10° 8° 14° ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Anti-siphonage pipe is connected to Top of P trap W.C. Main soil pipe Bottom of P trap W.C. Side of water closet Top of P trap W.C. Main soil pipe Bottom of P trap W.C. Side of water closet ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of half brick partition wall per mason per day is 4.0 m2 1.5 m2 2.0 m2 5.0 m2 4.0 m2 1.5 m2 2.0 m2 5.0 m2 ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The weight of an item is measured correct to nearest 0.50 kg 1.00 kg 0.75 kg 0.25 kg 0.50 kg 1.00 kg 0.75 kg 0.25 kg ANSWER DOWNLOAD EXAMIANS APP