Estimating and Costing The expected out turn of brick work in cement mortar in foundation and plinth per mason per day, is 1.25 m³ 1.00 m³ 1.50 m³ 1.75 m³ 1.25 m³ 1.00 m³ 1.50 m³ 1.75 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The following item of earth work is not measured separately. Setting out of works Steps in deep excavation All listed here Site clearance Setting out of works Steps in deep excavation All listed here Site clearance ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Brick walls are measured in sq. m if the thickness of the wall is 20 cm 10 cm None of these 15 cm 20 cm 10 cm None of these 15 cm ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The concrete work for the following part of the building of specified thickness is measured in square meters All of these Root slabs Floors Wall panels All of these Root slabs Floors Wall panels ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing While preparing a detailed estimate Dimension should be measured correct to 0.01 m Area should be measured correct to 0.01 sqm All of these Volume should be measured correct to 0.01 cum Dimension should be measured correct to 0.01 m Area should be measured correct to 0.01 sqm All of these Volume should be measured correct to 0.01 cum ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing If B is the width of formation, d is the height of the embankment, side slope S : 1, for a highway with no transverse slope, the area of cross-section is B × d - Sd1/2 ½ (Bd + Sd2) Bd + Sd2 B + d + Sd B × d - Sd1/2 ½ (Bd + Sd2) Bd + Sd2 B + d + Sd ANSWER DOWNLOAD EXAMIANS APP