Estimating and Costing The expected out turn of brick work in cement mortar in foundation and plinth per mason per day, is 1.00 m³ 1.25 m³ 1.50 m³ 1.75 m³ 1.00 m³ 1.25 m³ 1.50 m³ 1.75 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The height of the sink of wash basin above floor level is kept 70 cm 60 cm 80 cm 75 cm to 80 cm 70 cm 60 cm 80 cm 75 cm to 80 cm ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Pick up the item of work not included in the plinth area estimate Courtyard area W' Area Room area Wall thickness Courtyard area W' Area Room area Wall thickness ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing For the construction of buildings, the subheads of the estimate are Earthwork, Concrete work, Brick work All of these Brickwork, Stone work, Roofing Brickwork Flooring, Wood work, Steel work Earthwork, Concrete work, Brick work All of these Brickwork, Stone work, Roofing Brickwork Flooring, Wood work, Steel work ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The reduced levels of points, 30 metres apart along the longitudinal section of a road portion between chainages 5 and 9 are shown in the given figure. If there is a uniform up-gradient of the road 120 in 1, the chainage of the point with no filling or cutting is None of these (6 + 18) chains (6 + 15) chains (6 + 12) chains None of these (6 + 18) chains (6 + 15) chains (6 + 12) chains ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The area of a sloping surface of a protective embankment of mean height‘d’, side slopes S: 1 and length ‘L’ is d × d × s √[d² × (ds)²] L.D √(1 + s²) 2 L.D √(1 + s²) d × d × s √[d² × (ds)²] L.D √(1 + s²) 2 L.D √(1 + s²) ANSWER DOWNLOAD EXAMIANS APP