Estimating and Costing The expected out turn of brick work in cement mortar in foundation and plinth per mason per day, is 1.00 m³ 1.50 m³ 1.25 m³ 1.75 m³ 1.00 m³ 1.50 m³ 1.25 m³ 1.75 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The excavation exceeding 1.5 m in width and 10 sq.m in plan area with a depth not exceeding 30 cm, is termed as Surface dressing Cutting Surface excavation Excavation Surface dressing Cutting Surface excavation Excavation ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing While preparing a detailed estimate Dimension should be measured correct to 0.01 m Volume should be measured correct to 0.01 cum All of these Area should be measured correct to 0.01 sqm Dimension should be measured correct to 0.01 m Volume should be measured correct to 0.01 cum All of these Area should be measured correct to 0.01 sqm ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The trap which is provided to disconnect the house drain from the street sewer is called Intercepting trap All listed here Master trap Interception manhole Intercepting trap All listed here Master trap Interception manhole ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing For 12 mm thick cement plastering 1 : 6 on 100 sq.m new brick work, the quantity of cement required, is 0.247 m³ 0.274 m³ 0.295 m³ 0.200 m³ 0.247 m³ 0.274 m³ 0.295 m³ 0.200 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Pick up the incorrect statement regarding a master trap from the following: It is provided a cleaning eye at the top of the trap It is provided in between the lower end of the house drain and the street sewer The mica flap valve which opens inwards only, is fitted at the top of the inlet pipe The water seal is less than that of ordinary traps It is provided a cleaning eye at the top of the trap It is provided in between the lower end of the house drain and the street sewer The mica flap valve which opens inwards only, is fitted at the top of the inlet pipe The water seal is less than that of ordinary traps ANSWER DOWNLOAD EXAMIANS APP