Estimating and Costing The expected out turn of brick work in cement mortar in foundation and plinth per mason per day, is 1.25 m³ 1.75 m³ 1.00 m³ 1.50 m³ 1.25 m³ 1.75 m³ 1.00 m³ 1.50 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The item of steel work which is measured in sq.m, is Collapsible gates All listed here Ventilators and glazing Rolling shutters Collapsible gates All listed here Ventilators and glazing Rolling shutters ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The item of the brick structure measured in sq.m, is Broken glass coping Brick edging Brick work in arches Reinforced brick work Broken glass coping Brick edging Brick work in arches Reinforced brick work ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of half brick partition wall per mason per day is 4.0 m2 5.0 m2 2.0 m2 1.5 m2 4.0 m2 5.0 m2 2.0 m2 1.5 m2 ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The following item of earth work is not measured separately. Steps in deep excavation All listed here Site clearance Setting out of works Steps in deep excavation All listed here Site clearance Setting out of works ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing While estimating a reinforced cement structure, the omitted cover of concrete is assumed At the end of reinforcing bar, not less than 25 mm or twice the diameter of the bar For reinforcing longitudinal bar in a beam 25 mm minimum or diameter of the largest bar which is more All of these In thin slabs, 12 mm minimum or diameter of the bar whichever is more At the end of reinforcing bar, not less than 25 mm or twice the diameter of the bar For reinforcing longitudinal bar in a beam 25 mm minimum or diameter of the largest bar which is more All of these In thin slabs, 12 mm minimum or diameter of the bar whichever is more ANSWER DOWNLOAD EXAMIANS APP