Estimating and Costing The expected out turn of brick work in cement mortar in foundation and plinth per mason per day, is 1.00 m³ 1.25 m³ 1.75 m³ 1.50 m³ 1.00 m³ 1.25 m³ 1.75 m³ 1.50 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Berms are provided in canals if these are Partly in excavation and partly in embankment Fully in embankment All of these Fully in excavation Partly in excavation and partly in embankment Fully in embankment All of these Fully in excavation ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Brick walls are measured in sq. m if the thickness of the wall is None of these 20 cm 15 cm 10 cm None of these 20 cm 15 cm 10 cm ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing In the mid-section formula All of these The volume of the earth work is calculated by multiplying the mid-section area by the distance between the two original sections The area of mid-sections is calculated by using mean depth The mean depth is the average of depths of two consecutive sections All of these The volume of the earth work is calculated by multiplying the mid-section area by the distance between the two original sections The area of mid-sections is calculated by using mean depth The mean depth is the average of depths of two consecutive sections ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The 'centre line method' is specially adopted for estimating Octagonal buildings Circular buildings Hexagonal buildings All of these Octagonal buildings Circular buildings Hexagonal buildings All of these ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The weight of an item is measured correct to nearest 0.50 kg 1.00 kg 0.75 kg 0.25 kg 0.50 kg 1.00 kg 0.75 kg 0.25 kg ANSWER DOWNLOAD EXAMIANS APP