Estimating and Costing The expected out turn of brick work in cement mortar in foundation and plinth per mason per day, is 1.00 m³ 1.25 m³ 1.50 m³ 1.75 m³ 1.00 m³ 1.25 m³ 1.50 m³ 1.75 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn for earth work in excavation in ordinary soil per workman per day is 1.00 cum 2.00 cum 4.00 cum 3.00 cum 1.00 cum 2.00 cum 4.00 cum 3.00 cum ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing If tensile stress of a steel rod of diameter ‘D’ is 1400 kg/cm² and bond stress is 6 kg/cm², the required bond length of the rod is 30 D 50 D 59 D 39 D 30 D 50 D 59 D 39 D ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Pick up the item of work not included in the plinth area estimate Room area W' Area Courtyard area Wall thickness Room area W' Area Courtyard area Wall thickness ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The cross-section of a road partly in banking and partly in cutting is shown in the given figure. The area of the shaded portion is ⅓ × (b - rd)²/(s - r) ⅓ × (b - rd)²/(r - s) ⅓ × (b - rd)²/(r + s) ½ × (b + rd)²/(r - s) ⅓ × (b - rd)²/(s - r) ⅓ × (b - rd)²/(r - s) ⅓ × (b - rd)²/(r + s) ½ × (b + rd)²/(r - s) ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The ground surface slopes 1 in 50 along a proposed railway embankment 150 m in length. The height of the embankment at zero chainage is 0.5 m, the width is 11 m and side slopes 2:1. If the falling gradient of the embankment is 1 in 150, the quantity of the earthwork calculated by Prismoidal formula, is 3250 m³ 3300 m³ 3225 m³ 3275 m³ 3250 m³ 3300 m³ 3225 m³ 3275 m³ ANSWER DOWNLOAD EXAMIANS APP