Estimating and Costing The expected out turn of brick work in cement mortar in foundation and plinth per mason per day, is 1.75 m³ 1.00 m³ 1.25 m³ 1.50 m³ 1.75 m³ 1.00 m³ 1.25 m³ 1.50 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Pick up the correct statement regarding the centre line method of estimating a building The centre line is worked out separately for different sections of walls of a building All of these The centre line length is reduced by half the layer of main wall joining the partition wall Product of the centre line of the walls and area of cross-section of any item, gives total quantity of the item The centre line is worked out separately for different sections of walls of a building All of these The centre line length is reduced by half the layer of main wall joining the partition wall Product of the centre line of the walls and area of cross-section of any item, gives total quantity of the item ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The measurement is made in square metre in case of None of these R.C.C. structure Hollow concrete block wall Cement concrete in foundation None of these R.C.C. structure Hollow concrete block wall Cement concrete in foundation ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Pick up the excavation where measurements are made in square meters for payment. Both (B) and (C) Surface excavation up to 30 cm depths Surface dressing up to 15 cm depths Ordinary cuttings up to 1 m Both (B) and (C) Surface excavation up to 30 cm depths Surface dressing up to 15 cm depths Ordinary cuttings up to 1 m ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of cement concrete 1 : 2 : 4 per mason per day is 5.0 m³ 3.5 m³ 1.5 m³ 2.5 m³ 5.0 m³ 3.5 m³ 1.5 m³ 2.5 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Anti-siphonage pipe is connected to Side of water closet Main soil pipe Bottom of P trap W.C. Top of P trap W.C. Side of water closet Main soil pipe Bottom of P trap W.C. Top of P trap W.C. ANSWER DOWNLOAD EXAMIANS APP