Estimating and Costing The weight of an item is measured correct to nearest 0.75 kg 1.00 kg 0.50 kg 0.25 kg 0.75 kg 1.00 kg 0.50 kg 0.25 kg ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The measurement is made in square metre in case of None of these Hollow concrete block wall Cement concrete in foundation R.C.C. structure None of these Hollow concrete block wall Cement concrete in foundation R.C.C. structure ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The area of a sloping surface of a protective embankment of mean height‘d’, side slopes S: 1 and length ‘L’ is L.D √(1 + s²) d × d × s √[d² × (ds)²] 2 L.D √(1 + s²) L.D √(1 + s²) d × d × s √[d² × (ds)²] 2 L.D √(1 + s²) ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The diameter of a domestic sewer pipe laid at gradient 1 in 100 is recommended 200 mm 150 mm 175 mm 100 mm 200 mm 150 mm 175 mm 100 mm ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of cement concrete 1 : 2 : 4 per mason per day is 3.5 m³ 5.0 m³ 1.5 m³ 2.5 m³ 3.5 m³ 5.0 m³ 1.5 m³ 2.5 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing A portion of an embankment having a uniform up-gradient 1 in 500 is circular with radius 1000 m of the centre line. It subtends 180° at the centre. If the height of the bank is 1 m at the lower end, and side slopes 2:1, the earth work involved. 27,500 m³ 26,500 m³ 27,000 m³ 26,000 m³ 27,500 m³ 26,500 m³ 27,000 m³ 26,000 m³ ANSWER DOWNLOAD EXAMIANS APP