Estimating and Costing The weight of an item is measured correct to nearest 1.00 kg 0.25 kg 0.50 kg 0.75 kg 1.00 kg 0.25 kg 0.50 kg 0.75 kg ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Berms are provided in canals if these are Partly in excavation and partly in embankment Fully in excavation Fully in embankment All of these Partly in excavation and partly in embankment Fully in excavation Fully in embankment All of these ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing According to ISI method of measurement, the order of the sequence is Height, length, breadth None of these Length, breadth, height Breadth, length, height Height, length, breadth None of these Length, breadth, height Breadth, length, height ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of cement concrete 1 : 2 : 4 per mason per day is 3.5 m³ 5.0 m³ 1.5 m³ 2.5 m³ 3.5 m³ 5.0 m³ 1.5 m³ 2.5 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing If tensile stress of a steel rod of diameter ‘D’ is 1400 kg/cm² and bond stress is 6 kg/cm², the required bond length of the rod is 59 D 30 D 50 D 39 D 59 D 30 D 50 D 39 D ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The brick work is measured in sq metre, in case of Brick flat soling Honey comb brick work All of these Half brick walls or the partition Brick flat soling Honey comb brick work All of these Half brick walls or the partition ANSWER DOWNLOAD EXAMIANS APP