Estimating and Costing The correct Prismoidal formula for volume is D/3 [first area + last area + 2 Ʃ Even area + 4 Ʃ odd areas] D/6 [first area + last area + 2 ∑ Even area + 4 ∑ odd areas] D [first area + last area + Ʃ Even area + 2 Ʃ odd areas] D/3 [first area + last area + 4 Ʃ Even area + 2 Ʃ odd areas] D/3 [first area + last area + 2 Ʃ Even area + 4 Ʃ odd areas] D/6 [first area + last area + 2 ∑ Even area + 4 ∑ odd areas] D [first area + last area + Ʃ Even area + 2 Ʃ odd areas] D/3 [first area + last area + 4 Ʃ Even area + 2 Ʃ odd areas] ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of 12 mm plastering with cement mortar is 6.0 sq m 8.0 sq m 2.5 sq m 4.0 sq m 6.0 sq m 8.0 sq m 2.5 sq m 4.0 sq m ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The 'centre line method' is specially adopted for estimating Circular buildings Hexagonal buildings Octagonal buildings All of these Circular buildings Hexagonal buildings Octagonal buildings All of these ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing For 100 sq. m cement concrete (1 : 2: 4) 4 cm thick floor, the quantity of cement required, is 0.94 m³ 1.00 m³ 0.98 m³ 0.90 m³ 0.94 m³ 1.00 m³ 0.98 m³ 0.90 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The unit of measurement is per quintal for the following: M.S. reinforcement of R.C.C. works Rolling shutters Expanded metal wire netting Collapsible gates with rails M.S. reinforcement of R.C.C. works Rolling shutters Expanded metal wire netting Collapsible gates with rails ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of 2.5 cm cement concrete floor per mansion per day 7.5 sqm 5.0 sqm 10 sqm 2.5 sqm 7.5 sqm 5.0 sqm 10 sqm 2.5 sqm ANSWER DOWNLOAD EXAMIANS APP