Estimating and Costing The correct Prismoidal formula for volume is D/3 [first area + last area + 2 Ʃ Even area + 4 Ʃ odd areas] D [first area + last area + Ʃ Even area + 2 Ʃ odd areas] D/3 [first area + last area + 4 Ʃ Even area + 2 Ʃ odd areas] D/6 [first area + last area + 2 ∑ Even area + 4 ∑ odd areas] D/3 [first area + last area + 2 Ʃ Even area + 4 Ʃ odd areas] D [first area + last area + Ʃ Even area + 2 Ʃ odd areas] D/3 [first area + last area + 4 Ʃ Even area + 2 Ʃ odd areas] D/6 [first area + last area + 2 ∑ Even area + 4 ∑ odd areas] ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The rate of payment is made for 100 cu m (per % cu m) in case of All of these Earth work in excavation Excavation in trenches for foundation Rock cutting All of these Earth work in excavation Excavation in trenches for foundation Rock cutting ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The diameter of a domestic sewer pipe laid at gradient 1 in 100 is recommended 175 mm 100 mm 150 mm 200 mm 175 mm 100 mm 150 mm 200 mm ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The area of a sloping surface of a protective embankment of mean height‘d’, side slopes S: 1 and length ‘L’ is d × d × s L.D √(1 + s²) 2 L.D √(1 + s²) √[d² × (ds)²] d × d × s L.D √(1 + s²) 2 L.D √(1 + s²) √[d² × (ds)²] ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing If B is the width of formation, d is the height of the embankment, side slope S : 1, for a highway with no transverse slope, the area of cross-section is Bd + Sd2 B + d + Sd B × d - Sd1/2 ½ (Bd + Sd2) Bd + Sd2 B + d + Sd B × d - Sd1/2 ½ (Bd + Sd2) ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The excavation exceeding 1.5 m in width and 10 sq.m in plan area with a depth not exceeding 30 cm, is termed as Surface dressing Surface excavation Excavation Cutting Surface dressing Surface excavation Excavation Cutting ANSWER DOWNLOAD EXAMIANS APP