Estimating and Costing If the formation level of a highway has a uniform gradient for a particular length, and the ground is also having a longitudinal slope, the earthwork may be calculated by Mid-section formula Prismoidal formula Trapezoidal formula All of these Mid-section formula Prismoidal formula Trapezoidal formula All of these ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Size, capacity and materials need be specified for Stop-cocks Bib-cocks All of these Ball valves Stop-cocks Bib-cocks All of these Ball valves ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of 12 mm plastering with cement mortar is 4.0 sq m 6.0 sq m 2.5 sq m 8.0 sq m 4.0 sq m 6.0 sq m 2.5 sq m 8.0 sq m ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The excavation exceeding 1.5 m in width and 10 sq.m in plan area with a depth not exceeding 30 cm, is termed as Cutting Excavation Surface excavation Surface dressing Cutting Excavation Surface excavation Surface dressing ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing If B is the width of formation, d is the height of the embankment, side slope S : 1, for a highway with no transverse slope, the area of cross-section is B × d - Sd1/2 Bd + Sd2 ½ (Bd + Sd2) B + d + Sd B × d - Sd1/2 Bd + Sd2 ½ (Bd + Sd2) B + d + Sd ANSWER DOWNLOAD EXAMIANS APP