Estimating and Costing If B is the width of formation, d is the height of the embankment, side slope S : 1, for a highway with no transverse slope, the area of cross-section is Bd + Sd2 B + d + Sd B × d - Sd1/2 ½ (Bd + Sd2) Bd + Sd2 B + d + Sd B × d - Sd1/2 ½ (Bd + Sd2) ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The height of the sink of wash basin above floor level is kept 75 cm to 80 cm 70 cm 80 cm 60 cm 75 cm to 80 cm 70 cm 80 cm 60 cm ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Size, capacity and materials need be specified for Ball valves Bib-cocks Stop-cocks All of these Ball valves Bib-cocks Stop-cocks All of these ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The floor area includes the area of the balcony up to 0.5 0.25 0.75 1 0.5 0.25 0.75 1 ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of brick work in cement mortar in foundation and plinth per mason per day, is 1.25 m³ 1.50 m³ 1.00 m³ 1.75 m³ 1.25 m³ 1.50 m³ 1.00 m³ 1.75 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing A cement concrete road is 1000 m long, 8 m wide and 15 cm thick over the sub-base of 10 cm thick gravel. The box cutting in road crust is 1500 m3 500 m3 2000 m3 1000 m3 1500 m3 500 m3 2000 m3 1000 m3 ANSWER DOWNLOAD EXAMIANS APP