Estimating and Costing If B is the width of formation, d is the height of the embankment, side slope S : 1, for a highway with no transverse slope, the area of cross-section is Bd + Sd2 B + d + Sd ½ (Bd + Sd2) B × d - Sd1/2 Bd + Sd2 B + d + Sd ½ (Bd + Sd2) B × d - Sd1/2 ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing In the mid-section formula All of these The area of mid-sections is calculated by using mean depth The mean depth is the average of depths of two consecutive sections The volume of the earth work is calculated by multiplying the mid-section area by the distance between the two original sections All of these The area of mid-sections is calculated by using mean depth The mean depth is the average of depths of two consecutive sections The volume of the earth work is calculated by multiplying the mid-section area by the distance between the two original sections ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of brick work in cement mortar in foundation and plinth per mason per day, is 1.25 m³ 1.75 m³ 1.50 m³ 1.00 m³ 1.25 m³ 1.75 m³ 1.50 m³ 1.00 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Anti-siphonage pipe is connected to Top of P trap W.C. Main soil pipe Bottom of P trap W.C. Side of water closet Top of P trap W.C. Main soil pipe Bottom of P trap W.C. Side of water closet ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The weight of an item is measured correct to nearest 0.75 kg 0.50 kg 0.25 kg 1.00 kg 0.75 kg 0.50 kg 0.25 kg 1.00 kg ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing While estimating the qualities for the construction of a building, the correct metric unit is Square meters for volume Cubic metre for area Meter for length Liter for capacity Square meters for volume Cubic metre for area Meter for length Liter for capacity ANSWER DOWNLOAD EXAMIANS APP