Estimating and Costing If B is the width of formation, d is the height of the embankment, side slope S : 1, for a highway with no transverse slope, the area of cross-section is Bd + Sd2 B + d + Sd B × d - Sd1/2 ½ (Bd + Sd2) Bd + Sd2 B + d + Sd B × d - Sd1/2 ½ (Bd + Sd2) ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The measurement is made in square metre in case of Cement concrete in foundation Hollow concrete block wall R.C.C. structure None of these Cement concrete in foundation Hollow concrete block wall R.C.C. structure None of these ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn for earth work in excavation in ordinary soil per workman per day is 1.00 cum 2.00 cum 4.00 cum 3.00 cum 1.00 cum 2.00 cum 4.00 cum 3.00 cum ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing In long and short wall method of estimation, the length of long wall is the centre to centre distance between the walls and One fourth breadth of wall on each side None of these Half breadth of wall on each side Breadth of the wall One fourth breadth of wall on each side None of these Half breadth of wall on each side Breadth of the wall ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The plinth area of a building not includes Area of the walls at the floor level Lift and wall including landing Area of cantilevered porch Internal shaft for sanitary installations up to 2 sq m. in area Area of the walls at the floor level Lift and wall including landing Area of cantilevered porch Internal shaft for sanitary installations up to 2 sq m. in area ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The item of steel work which is measured in sq.m, is Rolling shutters Ventilators and glazing Collapsible gates All listed here Rolling shutters Ventilators and glazing Collapsible gates All listed here ANSWER DOWNLOAD EXAMIANS APP