Estimating and Costing The area is measured correct to the nearest 0.03 sqm 0.02 sqm 0.01 sqm 0.04 sqm 0.03 sqm 0.02 sqm 0.01 sqm 0.04 sqm ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing In the mid-section formula All of these The area of mid-sections is calculated by using mean depth The volume of the earth work is calculated by multiplying the mid-section area by the distance between the two original sections The mean depth is the average of depths of two consecutive sections All of these The area of mid-sections is calculated by using mean depth The volume of the earth work is calculated by multiplying the mid-section area by the distance between the two original sections The mean depth is the average of depths of two consecutive sections ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Anti-siphonage pipe is connected to Main soil pipe Top of P trap W.C. Side of water closet Bottom of P trap W.C. Main soil pipe Top of P trap W.C. Side of water closet Bottom of P trap W.C. ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing For the construction of buildings, the subheads of the estimate are Earthwork, Concrete work, Brick work Brickwork, Stone work, Roofing Brickwork Flooring, Wood work, Steel work All of these Earthwork, Concrete work, Brick work Brickwork, Stone work, Roofing Brickwork Flooring, Wood work, Steel work All of these ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of 2.5 cm cement concrete floor per mansion per day 10 sqm 5.0 sqm 7.5 sqm 2.5 sqm 10 sqm 5.0 sqm 7.5 sqm 2.5 sqm ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of cement concrete 1 : 2 : 4 per mason per day is 1.5 m³ 5.0 m³ 3.5 m³ 2.5 m³ 1.5 m³ 5.0 m³ 3.5 m³ 2.5 m³ ANSWER DOWNLOAD EXAMIANS APP