Estimating and Costing The area is measured correct to the nearest 0.02 sqm 0.03 sqm 0.01 sqm 0.04 sqm 0.02 sqm 0.03 sqm 0.01 sqm 0.04 sqm ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The following item of earth work is not measured separately. Steps in deep excavation All listed here Site clearance Setting out of works Steps in deep excavation All listed here Site clearance Setting out of works ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing For 100 sq. m cement concrete (1 : 2: 4) 4 cm thick floor, the quantity of cement required, is 0.98 m³ 0.90 m³ 0.94 m³ 1.00 m³ 0.98 m³ 0.90 m³ 0.94 m³ 1.00 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing While estimating a reinforced cement structure, the omitted cover of concrete is assumed At the end of reinforcing bar, not less than 25 mm or twice the diameter of the bar For reinforcing longitudinal bar in a beam 25 mm minimum or diameter of the largest bar which is more In thin slabs, 12 mm minimum or diameter of the bar whichever is more All of these At the end of reinforcing bar, not less than 25 mm or twice the diameter of the bar For reinforcing longitudinal bar in a beam 25 mm minimum or diameter of the largest bar which is more In thin slabs, 12 mm minimum or diameter of the bar whichever is more All of these ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The total length of a cranked bar through a distance (d) at 45° in case of a beam of effective length L, is L - (2 × 0.4 d) L + 0.42 d L - (0.42 d) L + (2 × 0.42 d) L - (2 × 0.4 d) L + 0.42 d L - (0.42 d) L + (2 × 0.42 d) ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Pick up the correct statement regarding the centre line method of estimating a building Product of the centre line of the walls and area of cross-section of any item, gives total quantity of the item The centre line is worked out separately for different sections of walls of a building All of these The centre line length is reduced by half the layer of main wall joining the partition wall Product of the centre line of the walls and area of cross-section of any item, gives total quantity of the item The centre line is worked out separately for different sections of walls of a building All of these The centre line length is reduced by half the layer of main wall joining the partition wall ANSWER DOWNLOAD EXAMIANS APP