Estimating and Costing The area is measured correct to the nearest 0.02 sqm 0.01 sqm 0.04 sqm 0.03 sqm 0.02 sqm 0.01 sqm 0.04 sqm 0.03 sqm ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of cement concrete 1 : 2 : 4 per mason per day is 3.5 m³ 2.5 m³ 5.0 m³ 1.5 m³ 3.5 m³ 2.5 m³ 5.0 m³ 1.5 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Due to change in price level, a revised estimate is prepared if the sanctioned estimate exceeds 0.04 0.05 0.025 0.02 0.04 0.05 0.025 0.02 ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The most reliable estimate is Cube rate estimate Plinth area estimate Detailed estimate Preliminary estimate Cube rate estimate Plinth area estimate Detailed estimate Preliminary estimate ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The ground surface slopes 1 in 50 along a proposed railway embankment 150 m in length. The height of the embankment at zero chainage is 0.5 m, the width is 11 m and side slopes 2:1. If the falling gradient of the embankment is 1 in 150, the quantity of the earthwork calculated by Prismoidal formula, is 3275 m³ 3300 m³ 3250 m³ 3225 m³ 3275 m³ 3300 m³ 3250 m³ 3225 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The floor area includes the area of the balcony up to 0.75 0.25 0.5 1 0.75 0.25 0.5 1 ANSWER DOWNLOAD EXAMIANS APP