Estimating and Costing Referring of given figure, pick up the correct statement from the following: The total length of centre line of four walls is 20 m Length of short walls in-to-in is 3.20 m Length of long wall out-to-out is 6.80 m All listed here The total length of centre line of four walls is 20 m Length of short walls in-to-in is 3.20 m Length of long wall out-to-out is 6.80 m All listed here ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The most reliable estimate is Detailed estimate Cube rate estimate Preliminary estimate Plinth area estimate Detailed estimate Cube rate estimate Preliminary estimate Plinth area estimate ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing If B is the width of formation, d is the height of the embankment, side slope S : 1, for a highway with no transverse slope, the area of cross-section is B × d - Sd1/2 Bd + Sd2 B + d + Sd ½ (Bd + Sd2) B × d - Sd1/2 Bd + Sd2 B + d + Sd ½ (Bd + Sd2) ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The unit of measurement is per quintal for the following: Rolling shutters M.S. reinforcement of R.C.C. works Expanded metal wire netting Collapsible gates with rails Rolling shutters M.S. reinforcement of R.C.C. works Expanded metal wire netting Collapsible gates with rails ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The weight of an item is measured correct to nearest 0.50 kg 0.75 kg 0.25 kg 1.00 kg 0.50 kg 0.75 kg 0.25 kg 1.00 kg ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of 2.5 cm cement concrete floor per mansion per day 10 sqm 5.0 sqm 2.5 sqm 7.5 sqm 10 sqm 5.0 sqm 2.5 sqm 7.5 sqm ANSWER DOWNLOAD EXAMIANS APP