Estimating and Costing Referring of given figure, pick up the correct statement from the following: Length of long wall out-to-out is 6.80 m The total length of centre line of four walls is 20 m Length of short walls in-to-in is 3.20 m All listed here Length of long wall out-to-out is 6.80 m The total length of centre line of four walls is 20 m Length of short walls in-to-in is 3.20 m All listed here ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The item of the brick structure measured in sq.m, is Reinforced brick work Brick edging Broken glass coping Brick work in arches Reinforced brick work Brick edging Broken glass coping Brick work in arches ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Pick up the item of work not included in the plinth area estimate Room area Wall thickness Courtyard area W' Area Room area Wall thickness Courtyard area W' Area ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing For 100 sq. m cement concrete (1 : 2: 4) 4 cm thick floor, the quantity of cement required, is 0.90 m³ 1.00 m³ 0.94 m³ 0.98 m³ 0.90 m³ 1.00 m³ 0.94 m³ 0.98 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing If tensile stress of a steel rod of diameter ‘D’ is 1400 kg/cm² and bond stress is 6 kg/cm², the required bond length of the rod is 59 D 39 D 30 D 50 D 59 D 39 D 30 D 50 D ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The minimum width of a septic tank is taken 70 cm 75 cm 90 cm 80 cm 70 cm 75 cm 90 cm 80 cm ANSWER DOWNLOAD EXAMIANS APP