Estimating and Costing The concrete work for the following part of the building of specified thickness is measured in square meters Root slabs Wall panels Floors All of these Root slabs Wall panels Floors All of these ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of half brick partition wall per mason per day is 1.5 m2 5.0 m2 2.0 m2 4.0 m2 1.5 m2 5.0 m2 2.0 m2 4.0 m2 ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The total length of a cranked bar through a distance (d) at 45° in case of a beam of effective length L, is L - (0.42 d) L + (2 × 0.42 d) L + 0.42 d L - (2 × 0.4 d) L - (0.42 d) L + (2 × 0.42 d) L + 0.42 d L - (2 × 0.4 d) ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The item of the brick structure measured in sq.m, is Brick edging Reinforced brick work Broken glass coping Brick work in arches Brick edging Reinforced brick work Broken glass coping Brick work in arches ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of 12 mm plastering with cement mortar is 6.0 sq m 2.5 sq m 4.0 sq m 8.0 sq m 6.0 sq m 2.5 sq m 4.0 sq m 8.0 sq m ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of cement concrete 1 : 2 : 4 per mason per day is 3.5 m³ 5.0 m³ 2.5 m³ 1.5 m³ 3.5 m³ 5.0 m³ 2.5 m³ 1.5 m³ ANSWER DOWNLOAD EXAMIANS APP