Estimating and Costing A cement concrete road is 1000 m long, 8 m wide and 15 cm thick over the sub-base of 10 cm thick gravel. The box cutting in road crust is 500 m3 1000 m3 2000 m3 1500 m3 500 m3 1000 m3 2000 m3 1500 m3 ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing If tensile stress of a steel rod of diameter ‘D’ is 1400 kg/cm² and bond stress is 6 kg/cm², the required bond length of the rod is 50 D 39 D 30 D 59 D 50 D 39 D 30 D 59 D ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The area of a sloping surface of a protective embankment of mean height‘d’, side slopes S: 1 and length ‘L’ is √[d² × (ds)²] 2 L.D √(1 + s²) d × d × s L.D √(1 + s²) √[d² × (ds)²] 2 L.D √(1 + s²) d × d × s L.D √(1 + s²) ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The ground surface slopes 1 in 50 along a proposed railway embankment 150 m in length. The height of the embankment at zero chainage is 0.5 m, the width is 11 m and side slopes 2:1. If the falling gradient of the embankment is 1 in 150, the quantity of the earthwork calculated by Prismoidal formula, is 3250 m³ 3300 m³ 3275 m³ 3225 m³ 3250 m³ 3300 m³ 3275 m³ 3225 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The slope of the outlet of 'P trap' below the horizontal is kept 8° 10° 12° 14° 8° 10° 12° 14° ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing While preparing a detailed estimate Dimension should be measured correct to 0.01 m All of these Area should be measured correct to 0.01 sqm Volume should be measured correct to 0.01 cum Dimension should be measured correct to 0.01 m All of these Area should be measured correct to 0.01 sqm Volume should be measured correct to 0.01 cum ANSWER DOWNLOAD EXAMIANS APP