Estimating and Costing A cement concrete road is 1000 m long, 8 m wide and 15 cm thick over the sub-base of 10 cm thick gravel. The box cutting in road crust is 500 m3 1000 m3 1500 m3 2000 m3 500 m3 1000 m3 1500 m3 2000 m3 ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Carpet area does not include the area of The walls along with doors and other openings Bath room and lavatory Kitchen and pantry All of these The walls along with doors and other openings Bath room and lavatory Kitchen and pantry All of these ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing For 100 sq. m cement concrete (1 : 2: 4) 4 cm thick floor, the quantity of cement required, is 0.94 m³ 0.90 m³ 0.98 m³ 1.00 m³ 0.94 m³ 0.90 m³ 0.98 m³ 1.00 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The detention period in a septic tank is assumed 25 minutes 40 minutes 30 minutes 20 minutes 25 minutes 40 minutes 30 minutes 20 minutes ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The ground surface slopes 1 in 50 along a proposed railway embankment 150 m in length. The height of the embankment at zero chainage is 0.5 m, the width is 11 m and side slopes 2:1. If the falling gradient of the embankment is 1 in 150, the quantity of the earthwork calculated by Prismoidal formula, is 3250 m³ 3275 m³ 3225 m³ 3300 m³ 3250 m³ 3275 m³ 3225 m³ 3300 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing While preparing a detailed estimate Area should be measured correct to 0.01 sqm Dimension should be measured correct to 0.01 m Volume should be measured correct to 0.01 cum All of these Area should be measured correct to 0.01 sqm Dimension should be measured correct to 0.01 m Volume should be measured correct to 0.01 cum All of these ANSWER DOWNLOAD EXAMIANS APP