Estimating and Costing A cement concrete road is 1000 m long, 8 m wide and 15 cm thick over the sub-base of 10 cm thick gravel. The box cutting in road crust is 2000 m3 500 m3 1000 m3 1500 m3 2000 m3 500 m3 1000 m3 1500 m3 ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing According to ISI method of measurement, the order of the sequence is Length, breadth, height None of these Height, length, breadth Breadth, length, height Length, breadth, height None of these Height, length, breadth Breadth, length, height ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of cement concrete 1 : 2 : 4 per mason per day is 5.0 m³ 3.5 m³ 1.5 m³ 2.5 m³ 5.0 m³ 3.5 m³ 1.5 m³ 2.5 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing In the mid-section formula The volume of the earth work is calculated by multiplying the mid-section area by the distance between the two original sections All of these The mean depth is the average of depths of two consecutive sections The area of mid-sections is calculated by using mean depth The volume of the earth work is calculated by multiplying the mid-section area by the distance between the two original sections All of these The mean depth is the average of depths of two consecutive sections The area of mid-sections is calculated by using mean depth ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of brick work in cement mortar in foundation and plinth per mason per day, is 1.75 m³ 1.25 m³ 1.50 m³ 1.00 m³ 1.75 m³ 1.25 m³ 1.50 m³ 1.00 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The rate of an item of work depends on Proportion of mortar All of these Specifications of works Specifications of materials Proportion of mortar All of these Specifications of works Specifications of materials ANSWER DOWNLOAD EXAMIANS APP