Estimating and Costing A cement concrete road is 1000 m long, 8 m wide and 15 cm thick over the sub-base of 10 cm thick gravel. The box cutting in road crust is 1500 m3 1000 m3 2000 m3 500 m3 1500 m3 1000 m3 2000 m3 500 m3 ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Pick up the excavation where measurements are made in square meters for payment. Surface excavation up to 30 cm depths Both (B) and (C) Surface dressing up to 15 cm depths Ordinary cuttings up to 1 m Surface excavation up to 30 cm depths Both (B) and (C) Surface dressing up to 15 cm depths Ordinary cuttings up to 1 m ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of half brick partition wall per mason per day is 5.0 m2 1.5 m2 4.0 m2 2.0 m2 5.0 m2 1.5 m2 4.0 m2 2.0 m2 ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The ground surface slopes 1 in 50 along a proposed railway embankment 150 m in length. The height of the embankment at zero chainage is 0.5 m, the width is 11 m and side slopes 2:1. If the falling gradient of the embankment is 1 in 150, the quantity of the earthwork calculated by Prismoidal formula, is 3275 m³ 3250 m³ 3225 m³ 3300 m³ 3275 m³ 3250 m³ 3225 m³ 3300 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Berms are provided in canals if these are Partly in excavation and partly in embankment All of these Fully in excavation Fully in embankment Partly in excavation and partly in embankment All of these Fully in excavation Fully in embankment ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing For 12 mm thick cement plastering 1 : 6 on 100 sq.m new brick work, the quantity of cement required, is 0.247 m³ 0.295 m³ 0.274 m³ 0.200 m³ 0.247 m³ 0.295 m³ 0.274 m³ 0.200 m³ ANSWER DOWNLOAD EXAMIANS APP