Estimating and Costing A cement concrete road is 1000 m long, 8 m wide and 15 cm thick over the sub-base of 10 cm thick gravel. The box cutting in road crust is 2000 m3 500 m3 1500 m3 1000 m3 2000 m3 500 m3 1500 m3 1000 m3 ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The following item of earth work is not measured separately. Setting out of works Site clearance Steps in deep excavation All listed here Setting out of works Site clearance Steps in deep excavation All listed here ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing While preparing a detailed estimate Area should be measured correct to 0.01 sqm Dimension should be measured correct to 0.01 m Volume should be measured correct to 0.01 cum All of these Area should be measured correct to 0.01 sqm Dimension should be measured correct to 0.01 m Volume should be measured correct to 0.01 cum All of these ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of cement concrete 1 : 2 : 4 per mason per day is 1.5 m³ 3.5 m³ 2.5 m³ 5.0 m³ 1.5 m³ 3.5 m³ 2.5 m³ 5.0 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The total length of a cranked bar through a distance (d) at 45° in case of a beam of effective length L, is L - (2 × 0.4 d) L + 0.42 d L - (0.42 d) L + (2 × 0.42 d) L - (2 × 0.4 d) L + 0.42 d L - (0.42 d) L + (2 × 0.42 d) ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The trap which is provided to disconnect the house drain from the street sewer is called Master trap Intercepting trap All listed here Interception manhole Master trap Intercepting trap All listed here Interception manhole ANSWER DOWNLOAD EXAMIANS APP