Estimating and Costing A cement concrete road is 1000 m long, 8 m wide and 15 cm thick over the sub-base of 10 cm thick gravel. The box cutting in road crust is 1500 m3 500 m3 1000 m3 2000 m3 1500 m3 500 m3 1000 m3 2000 m3 ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The slope of the outlet of 'P trap' below the horizontal is kept 8° 10° 12° 14° 8° 10° 12° 14° ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The ground surface slopes 1 in 50 along a proposed railway embankment 150 m in length. The height of the embankment at zero chainage is 0.5 m, the width is 11 m and side slopes 2:1. If the falling gradient of the embankment is 1 in 150, the quantity of the earthwork calculated by Prismoidal formula, is 3225 m³ 3250 m³ 3275 m³ 3300 m³ 3225 m³ 3250 m³ 3275 m³ 3300 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Brick walls are measured in sq. m if the thickness of the wall is 15 cm 10 cm None of these 20 cm 15 cm 10 cm None of these 20 cm ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The detention period in a septic tank is assumed 30 minutes 20 minutes 40 minutes 25 minutes 30 minutes 20 minutes 40 minutes 25 minutes ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The following item of earth work is not measured separately. All listed here Setting out of works Steps in deep excavation Site clearance All listed here Setting out of works Steps in deep excavation Site clearance ANSWER DOWNLOAD EXAMIANS APP