Estimating and Costing A cement concrete road is 1000 m long, 8 m wide and 15 cm thick over the sub-base of 10 cm thick gravel. The box cutting in road crust is 500 m3 1500 m3 1000 m3 2000 m3 500 m3 1500 m3 1000 m3 2000 m3 ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Carpet area does not include the area of The walls along with doors and other openings Bath room and lavatory Kitchen and pantry All of these The walls along with doors and other openings Bath room and lavatory Kitchen and pantry All of these ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The trap which is provided to disconnect the house drain from the street sewer is called Interception manhole Master trap All listed here Intercepting trap Interception manhole Master trap All listed here Intercepting trap ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of brick work in cement mortar in foundation and plinth per mason per day, is 1.25 m³ 1.75 m³ 1.00 m³ 1.50 m³ 1.25 m³ 1.75 m³ 1.00 m³ 1.50 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The ground surface slopes 1 in 50 along a proposed railway embankment 150 m in length. The height of the embankment at zero chainage is 0.5 m, the width is 11 m and side slopes 2:1. If the falling gradient of the embankment is 1 in 150, the quantity of the earthwork calculated by Prismoidal formula, is 3225 m³ 3275 m³ 3300 m³ 3250 m³ 3225 m³ 3275 m³ 3300 m³ 3250 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of 12 mm plastering with cement mortar is 6.0 sq m 4.0 sq m 2.5 sq m 8.0 sq m 6.0 sq m 4.0 sq m 2.5 sq m 8.0 sq m ANSWER DOWNLOAD EXAMIANS APP