Estimating and Costing Due to change in price level, a revised estimate is prepared if the sanctioned estimate exceeds 0.025 0.04 0.05 0.02 0.025 0.04 0.05 0.02 ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing In case of laying gullies, siphons, intercepting traps, the cost includes Bed concreting All of these Setting and laying Connection to drains Bed concreting All of these Setting and laying Connection to drains ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The most reliable estimate is Preliminary estimate Plinth area estimate Detailed estimate Cube rate estimate Preliminary estimate Plinth area estimate Detailed estimate Cube rate estimate ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The reduced levels of points, 30 metres apart along the longitudinal section of a road portion between chainages 5 and 9 are shown in the given figure. If there is a uniform up-gradient of the road 120 in 1, the chainage of the point with no filling or cutting is (6 + 15) chains None of these (6 + 12) chains (6 + 18) chains (6 + 15) chains None of these (6 + 12) chains (6 + 18) chains ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The measurement is made in square metre in case of None of these Hollow concrete block wall Cement concrete in foundation R.C.C. structure None of these Hollow concrete block wall Cement concrete in foundation R.C.C. structure ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of brick work in cement mortar in foundation and plinth per mason per day, is 1.00 m³ 1.50 m³ 1.75 m³ 1.25 m³ 1.00 m³ 1.50 m³ 1.75 m³ 1.25 m³ ANSWER DOWNLOAD EXAMIANS APP