Estimating and Costing Due to change in price level, a revised estimate is prepared if the sanctioned estimate exceeds 0.04 0.05 0.025 0.02 0.04 0.05 0.025 0.02 ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The trap which is provided to disconnect the house drain from the street sewer is called Intercepting trap Interception manhole All listed here Master trap Intercepting trap Interception manhole All listed here Master trap ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Anti-siphonage pipe is connected to Bottom of P trap W.C. Main soil pipe Top of P trap W.C. Side of water closet Bottom of P trap W.C. Main soil pipe Top of P trap W.C. Side of water closet ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The excavation exceeding 1.5 m in width and 10 sq.m in plan area with a depth not exceeding 30 cm, is termed as Cutting Excavation Surface excavation Surface dressing Cutting Excavation Surface excavation Surface dressing ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing For 100 sq. m cement concrete (1 : 2: 4) 4 cm thick floor, the quantity of cement required, is 0.90 m³ 0.98 m³ 1.00 m³ 0.94 m³ 0.90 m³ 0.98 m³ 1.00 m³ 0.94 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The cross-section of a road partly in banking and partly in cutting is shown in the given figure. The area of the shaded portion is ⅓ × (b - rd)²/(s - r) ⅓ × (b - rd)²/(r - s) ½ × (b + rd)²/(r - s) ⅓ × (b - rd)²/(r + s) ⅓ × (b - rd)²/(s - r) ⅓ × (b - rd)²/(r - s) ½ × (b + rd)²/(r - s) ⅓ × (b - rd)²/(r + s) ANSWER DOWNLOAD EXAMIANS APP