Estimating and Costing Due to change in price level, a revised estimate is prepared if the sanctioned estimate exceeds 0.025 0.02 0.05 0.04 0.025 0.02 0.05 0.04 ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing While estimating the qualities for the construction of a building, the correct metric unit is Cubic metre for area Meter for length Square meters for volume Liter for capacity Cubic metre for area Meter for length Square meters for volume Liter for capacity ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The floor area includes the area of the balcony up to 0.25 0.75 1 0.5 0.25 0.75 1 0.5 ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing If the formation level of a highway has a uniform gradient for a particular length, and the ground is also having a longitudinal slope, the earthwork may be calculated by All of these Mid-section formula Prismoidal formula Trapezoidal formula All of these Mid-section formula Prismoidal formula Trapezoidal formula ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The slope of the outlet of 'P trap' below the horizontal is kept 14° 12° 10° 8° 14° 12° 10° 8° ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing A portion of an embankment having a uniform up-gradient 1 in 500 is circular with radius 1000 m of the centre line. It subtends 180° at the centre. If the height of the bank is 1 m at the lower end, and side slopes 2:1, the earth work involved. 26,000 m³ 26,500 m³ 27,000 m³ 27,500 m³ 26,000 m³ 26,500 m³ 27,000 m³ 27,500 m³ ANSWER DOWNLOAD EXAMIANS APP