Estimating and Costing The rate of an item of work depends on Proportion of mortar Specifications of works All of these Specifications of materials Proportion of mortar Specifications of works All of these Specifications of materials ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The diameter of a domestic sewer pipe laid at gradient 1 in 100 is recommended 200 mm 100 mm 175 mm 150 mm 200 mm 100 mm 175 mm 150 mm ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing While estimating a reinforced cement structure, the omitted cover of concrete is assumed In thin slabs, 12 mm minimum or diameter of the bar whichever is more At the end of reinforcing bar, not less than 25 mm or twice the diameter of the bar All of these For reinforcing longitudinal bar in a beam 25 mm minimum or diameter of the largest bar which is more In thin slabs, 12 mm minimum or diameter of the bar whichever is more At the end of reinforcing bar, not less than 25 mm or twice the diameter of the bar All of these For reinforcing longitudinal bar in a beam 25 mm minimum or diameter of the largest bar which is more ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The order of booking dimensions is Breadth, length, height Height, breadth, length None of these Length, breadth, height Breadth, length, height Height, breadth, length None of these Length, breadth, height ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The damp proof course (D.P.C.) is measured in None of these Sq. m Meters Cub. m None of these Sq. m Meters Cub. m ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of cement concrete 1 : 2 : 4 per mason per day is 2.5 m³ 5.0 m³ 1.5 m³ 3.5 m³ 2.5 m³ 5.0 m³ 1.5 m³ 3.5 m³ ANSWER DOWNLOAD EXAMIANS APP