Estimating and Costing The rate of an item of work depends on All of these Specifications of materials Specifications of works Proportion of mortar All of these Specifications of materials Specifications of works Proportion of mortar ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of brick work in cement mortar in foundation and plinth per mason per day, is 1.75 m³ 1.50 m³ 1.00 m³ 1.25 m³ 1.75 m³ 1.50 m³ 1.00 m³ 1.25 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Carpet area does not include the area of All of these Kitchen and pantry The walls along with doors and other openings Bath room and lavatory All of these Kitchen and pantry The walls along with doors and other openings Bath room and lavatory ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The floor area includes the area of the balcony up to 0.25 0.75 1 0.5 0.25 0.75 1 0.5 ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The following item of earth work is not measured separately. Steps in deep excavation All listed here Site clearance Setting out of works Steps in deep excavation All listed here Site clearance Setting out of works ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Size, capacity and materials need be specified for Stop-cocks Bib-cocks Ball valves All of these Stop-cocks Bib-cocks Ball valves All of these ANSWER DOWNLOAD EXAMIANS APP