Estimating and Costing The rate of an item of work depends on Specifications of works All of these Specifications of materials Proportion of mortar Specifications of works All of these Specifications of materials Proportion of mortar ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The area is measured correct to the nearest 0.01 sqm 0.03 sqm 0.04 sqm 0.02 sqm 0.01 sqm 0.03 sqm 0.04 sqm 0.02 sqm ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing For 100 sq. m cement concrete (1 : 2: 4) 4 cm thick floor, the quantity of cement required, is 1.00 m³ 0.90 m³ 0.98 m³ 0.94 m³ 1.00 m³ 0.90 m³ 0.98 m³ 0.94 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of brick work in cement mortar in foundation and plinth per mason per day, is 1.75 m³ 1.25 m³ 1.00 m³ 1.50 m³ 1.75 m³ 1.25 m³ 1.00 m³ 1.50 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The cross-sections for a highway is taken at 30 meters apart Intermediate points having abrupt change in gradient All of these Right angle to the centre line 30 meters apart Intermediate points having abrupt change in gradient All of these Right angle to the centre line ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing A cement concrete road is 1000 m long, 8 m wide and 15 cm thick over the sub-base of 10 cm thick gravel. The box cutting in road crust is 500 m3 1000 m3 2000 m3 1500 m3 500 m3 1000 m3 2000 m3 1500 m3 ANSWER DOWNLOAD EXAMIANS APP