Estimating and Costing

Estimating and Costing
The rate of an item of work depends on

All of these
Specifications of works
Specifications of materials
Proportion of mortar

ANSWER DOWNLOAD EXAMIANS APP

Estimating and Costing
Carpet area does not include the area of

All of these
Bath room and lavatory
Kitchen and pantry
The walls along with doors and other openings

ANSWER DOWNLOAD EXAMIANS APP

Estimating and Costing
The trap which is provided to disconnect the house drain from the street sewer is called

All listed here
Intercepting trap
Master trap
Interception manhole

ANSWER DOWNLOAD EXAMIANS APP

Estimating and Costing
The weight of an item is measured correct to nearest

1.00 kg
0.50 kg
0.25 kg
0.75 kg

ANSWER DOWNLOAD EXAMIANS APP

Estimating and Costing
The following item of earth work is not measured separately.

Steps in deep excavation
Site clearance
All listed here
Setting out of works

ANSWER DOWNLOAD EXAMIANS APP

Estimating and Costing
While estimating the qualities for the construction of a building, the correct metric unit is

Liter for capacity
Square meters for volume
Cubic metre for area
Meter for length

ANSWER DOWNLOAD EXAMIANS APP
MORE MCQ ON Estimating and Costing

DOWNLOAD APP

  • APPLE
    from app store
  • ANDROID
    from play store

SEARCH

LOGIN HERE


  • GOOGLE

FIND US

  • 1.70K
    FOLLOW US
  • EXAMIANSSTUDY FOR YOUR DREAMS.
  • SUPPORT :SUPPORT EMAIL ACCOUNT : examians@yahoo.com

OTHER WEBSITES

  • GUJARATI MCQ
  • ACCOUNTIANS

QUICK LINKS

  • HOME
  • QUIZ
  • PRIVACY POLICY
  • DISCLAIMER
  • TERMS & CONDITIONS
  • CONTACT US
↑