Estimating and Costing

Estimating and Costing
The rate of an item of work depends on

Specifications of materials
Proportion of mortar
Specifications of works
All of these

ANSWER DOWNLOAD EXAMIANS APP

Estimating and Costing
The detention period in a septic tank is assumed

20 minutes
40 minutes
30 minutes
25 minutes

ANSWER DOWNLOAD EXAMIANS APP

Estimating and Costing
The expected out turn of 2.5 cm cement concrete floor per mansion per day

7.5 sqm
10 sqm
5.0 sqm
2.5 sqm

ANSWER DOWNLOAD EXAMIANS APP

Estimating and Costing
The item of the brick structure measured in sq.m, is

Broken glass coping
Brick work in arches
Reinforced brick work
Brick edging

ANSWER DOWNLOAD EXAMIANS APP

Estimating and Costing
The rate of payment is made for 100 cu m (per % cu m) in case of

Excavation in trenches for foundation
All of these
Earth work in excavation
Rock cutting

ANSWER DOWNLOAD EXAMIANS APP

Estimating and Costing
The expected out turn of cement concrete 1 : 2 : 4 per mason per day is

1.5 m³
5.0 m³
3.5 m³
2.5 m³

ANSWER DOWNLOAD EXAMIANS APP
MORE MCQ ON Estimating and Costing

DOWNLOAD APP

  • APPLE
    from app store
  • ANDROID
    from play store

SEARCH

LOGIN HERE


  • GOOGLE

FIND US

  • 1.70K
    FOLLOW US
  • EXAMIANSSTUDY FOR YOUR DREAMS.
  • SUPPORT :SUPPORT EMAIL ACCOUNT : examians@yahoo.com

OTHER WEBSITES

  • GUJARATI MCQ
  • ACCOUNTIANS

QUICK LINKS

  • HOME
  • QUIZ
  • PRIVACY POLICY
  • DISCLAIMER
  • TERMS & CONDITIONS
  • CONTACT US
↑