Estimating and Costing The rate of an item of work depends on Specifications of materials Proportion of mortar Specifications of works All of these Specifications of materials Proportion of mortar Specifications of works All of these ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The detention period in a septic tank is assumed 20 minutes 40 minutes 30 minutes 25 minutes 20 minutes 40 minutes 30 minutes 25 minutes ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of 2.5 cm cement concrete floor per mansion per day 7.5 sqm 10 sqm 5.0 sqm 2.5 sqm 7.5 sqm 10 sqm 5.0 sqm 2.5 sqm ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The item of the brick structure measured in sq.m, is Broken glass coping Brick work in arches Reinforced brick work Brick edging Broken glass coping Brick work in arches Reinforced brick work Brick edging ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The rate of payment is made for 100 cu m (per % cu m) in case of Excavation in trenches for foundation All of these Earth work in excavation Rock cutting Excavation in trenches for foundation All of these Earth work in excavation Rock cutting ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of cement concrete 1 : 2 : 4 per mason per day is 1.5 m³ 5.0 m³ 3.5 m³ 2.5 m³ 1.5 m³ 5.0 m³ 3.5 m³ 2.5 m³ ANSWER DOWNLOAD EXAMIANS APP