Estimating and Costing The rate of an item of work depends on Specifications of works All of these Proportion of mortar Specifications of materials Specifications of works All of these Proportion of mortar Specifications of materials ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The measurement is made in square metre in case of Cement concrete in foundation Hollow concrete block wall None of these R.C.C. structure Cement concrete in foundation Hollow concrete block wall None of these R.C.C. structure ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing A portion of an embankment having a uniform up-gradient 1 in 500 is circular with radius 1000 m of the centre line. It subtends 180° at the centre. If the height of the bank is 1 m at the lower end, and side slopes 2:1, the earth work involved. 27,500 m³ 26,500 m³ 27,000 m³ 26,000 m³ 27,500 m³ 26,500 m³ 27,000 m³ 26,000 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The diameter of a domestic sewer pipe laid at gradient 1 in 100 is recommended 175 mm 100 mm 150 mm 200 mm 175 mm 100 mm 150 mm 200 mm ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of 12 mm plastering with cement mortar is 8.0 sq m 2.5 sq m 4.0 sq m 6.0 sq m 8.0 sq m 2.5 sq m 4.0 sq m 6.0 sq m ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing According to ISI method of measurement, the order of the sequence is Height, length, breadth None of these Length, breadth, height Breadth, length, height Height, length, breadth None of these Length, breadth, height Breadth, length, height ANSWER DOWNLOAD EXAMIANS APP