Estimating and Costing The item of the brick structure measured in sq.m, is Reinforced brick work Broken glass coping Brick work in arches Brick edging Reinforced brick work Broken glass coping Brick work in arches Brick edging ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The area of a sloping surface of a protective embankment of mean height‘d’, side slopes S: 1 and length ‘L’ is √[d² × (ds)²] L.D √(1 + s²) d × d × s 2 L.D √(1 + s²) √[d² × (ds)²] L.D √(1 + s²) d × d × s 2 L.D √(1 + s²) ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The measurement is made in square metre in case of Cement concrete in foundation R.C.C. structure None of these Hollow concrete block wall Cement concrete in foundation R.C.C. structure None of these Hollow concrete block wall ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing While preparing a detailed estimate Volume should be measured correct to 0.01 cum Dimension should be measured correct to 0.01 m Area should be measured correct to 0.01 sqm All of these Volume should be measured correct to 0.01 cum Dimension should be measured correct to 0.01 m Area should be measured correct to 0.01 sqm All of these ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing A portion of an embankment having a uniform up-gradient 1 in 500 is circular with radius 1000 m of the centre line. It subtends 180° at the centre. If the height of the bank is 1 m at the lower end, and side slopes 2:1, the earth work involved. 26,000 m³ 27,500 m³ 26,500 m³ 27,000 m³ 26,000 m³ 27,500 m³ 26,500 m³ 27,000 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing A cement concrete road is 1000 m long, 8 m wide and 15 cm thick over the sub-base of 10 cm thick gravel. The box cutting in road crust is 500 m3 1500 m3 1000 m3 2000 m3 500 m3 1500 m3 1000 m3 2000 m3 ANSWER DOWNLOAD EXAMIANS APP