Estimating and Costing
Pick up the correct statement regarding the centre line method of estimating a building

Product of the centre line of the walls and area of cross-section of any item, gives total quantity of the item
All of these
The centre line is worked out separately for different sections of walls of a building
The centre line length is reduced by half the layer of main wall joining the partition wall