Estimating and Costing The item of the brick structure measured in sq.m, is Reinforced brick work Brick work in arches Broken glass coping Brick edging Reinforced brick work Brick work in arches Broken glass coping Brick edging ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The reduced levels of points, 30 metres apart along the longitudinal section of a road portion between chainages 5 and 9 are shown in the given figure. If there is a uniform up-gradient of the road 120 in 1, the chainage of the point with no filling or cutting is (6 + 18) chains (6 + 15) chains None of these (6 + 12) chains (6 + 18) chains (6 + 15) chains None of these (6 + 12) chains ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The volume is measured correct to the nearest 0.02 cum 0.03 cum 0.01 cum 0.04 cum 0.02 cum 0.03 cum 0.01 cum 0.04 cum ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing A cement concrete road is 1000 m long, 8 m wide and 15 cm thick over the sub-base of 10 cm thick gravel. The box cutting in road crust is 1500 m3 1000 m3 2000 m3 500 m3 1500 m3 1000 m3 2000 m3 500 m3 ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing For the construction of buildings, the subheads of the estimate are Earthwork, Concrete work, Brick work Brickwork, Stone work, Roofing All of these Brickwork Flooring, Wood work, Steel work Earthwork, Concrete work, Brick work Brickwork, Stone work, Roofing All of these Brickwork Flooring, Wood work, Steel work ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing According to Indian Standards Institute, the actual size of modular bricks is 25 cm x 13 cm x 7.5 cm 19 cm x 9 cm x 9 cm 23 cm x 11.5 cm x 7.5 cm 20 cm x 10 cm x 10 cm 25 cm x 13 cm x 7.5 cm 19 cm x 9 cm x 9 cm 23 cm x 11.5 cm x 7.5 cm 20 cm x 10 cm x 10 cm ANSWER DOWNLOAD EXAMIANS APP