Estimating and Costing The total length of a cranked bar through a distance (d) at 45° in case of a beam of effective length L, is L + (2 × 0.42 d) L + 0.42 d L - (2 × 0.4 d) L - (0.42 d) L + (2 × 0.42 d) L + 0.42 d L - (2 × 0.4 d) L - (0.42 d) ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Pick up the correct statement in case of water supply. Pipes laid in trenches and pipes fixed to walls are measured separately Pipes are classified according to their sizes and quality All of these Cutting through walls and floors are included with the item Pipes laid in trenches and pipes fixed to walls are measured separately Pipes are classified according to their sizes and quality All of these Cutting through walls and floors are included with the item ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The brick work is not measured in cu m in case of Half brick wall Brick work in arches Reinforced brick work One or more than one brick wall Half brick wall Brick work in arches Reinforced brick work One or more than one brick wall ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The rate of an item of work depends on Proportion of mortar All of these Specifications of works Specifications of materials Proportion of mortar All of these Specifications of works Specifications of materials ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing In case of laying gullies, siphons, intercepting traps, the cost includes Connection to drains Bed concreting All of these Setting and laying Connection to drains Bed concreting All of these Setting and laying ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The order of booking dimensions is Breadth, length, height Height, breadth, length Length, breadth, height None of these Breadth, length, height Height, breadth, length Length, breadth, height None of these ANSWER DOWNLOAD EXAMIANS APP