Estimating and Costing The total length of a cranked bar through a distance (d) at 45° in case of a beam of effective length L, is L + 0.42 d L - (0.42 d) L + (2 × 0.42 d) L - (2 × 0.4 d) L + 0.42 d L - (0.42 d) L + (2 × 0.42 d) L - (2 × 0.4 d) ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing While estimating the qualities for the construction of a building, the correct metric unit is Square meters for volume Cubic metre for area Meter for length Liter for capacity Square meters for volume Cubic metre for area Meter for length Liter for capacity ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn for earth work in excavation in ordinary soil per workman per day is 3.00 cum 2.00 cum 1.00 cum 4.00 cum 3.00 cum 2.00 cum 1.00 cum 4.00 cum ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of 2.5 cm cement concrete floor per mansion per day 10 sqm 2.5 sqm 7.5 sqm 5.0 sqm 10 sqm 2.5 sqm 7.5 sqm 5.0 sqm ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Carpet area does not include the area of The walls along with doors and other openings All of these Kitchen and pantry Bath room and lavatory The walls along with doors and other openings All of these Kitchen and pantry Bath room and lavatory ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The excavation exceeding 1.5 m in width and 10 sq.m in plan area with a depth not exceeding 30 cm, is termed as Cutting Excavation Surface excavation Surface dressing Cutting Excavation Surface excavation Surface dressing ANSWER DOWNLOAD EXAMIANS APP