Estimating and Costing The measurement is not made in square meters in case of Form works P.C. (Damp proof course) R.C. Chhajja Concrete Jeffries Form works P.C. (Damp proof course) R.C. Chhajja Concrete Jeffries ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The detention period in a septic tank is assumed 20 minutes 40 minutes 25 minutes 30 minutes 20 minutes 40 minutes 25 minutes 30 minutes ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The ground surface slopes 1 in 50 along a proposed railway embankment 150 m in length. The height of the embankment at zero chainage is 0.5 m, the width is 11 m and side slopes 2:1. If the falling gradient of the embankment is 1 in 150, the quantity of the earthwork calculated by Prismoidal formula, is 3225 m³ 3250 m³ 3275 m³ 3300 m³ 3225 m³ 3250 m³ 3275 m³ 3300 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing If tensile stress of a steel rod of diameter ‘D’ is 1400 kg/cm² and bond stress is 6 kg/cm², the required bond length of the rod is 59 D 30 D 39 D 50 D 59 D 30 D 39 D 50 D ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The 'centre line method' is specially adopted for estimating Hexagonal buildings All of these Octagonal buildings Circular buildings Hexagonal buildings All of these Octagonal buildings Circular buildings ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The rate of payment is made for 100 cu m (per % cu m) in case of Excavation in trenches for foundation All of these Rock cutting Earth work in excavation Excavation in trenches for foundation All of these Rock cutting Earth work in excavation ANSWER DOWNLOAD EXAMIANS APP