Estimating and Costing The measurement is not made in square meters in case of Form works R.C. Chhajja P.C. (Damp proof course) Concrete Jeffries Form works R.C. Chhajja P.C. (Damp proof course) Concrete Jeffries ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of half brick partition wall per mason per day is 4.0 m2 2.0 m2 1.5 m2 5.0 m2 4.0 m2 2.0 m2 1.5 m2 5.0 m2 ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Pick up the correct statement regarding the centre line method of estimating a building Product of the centre line of the walls and area of cross-section of any item, gives total quantity of the item The centre line is worked out separately for different sections of walls of a building The centre line length is reduced by half the layer of main wall joining the partition wall All of these Product of the centre line of the walls and area of cross-section of any item, gives total quantity of the item The centre line is worked out separately for different sections of walls of a building The centre line length is reduced by half the layer of main wall joining the partition wall All of these ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The cross-sections for a highway is taken at Right angle to the centre line Intermediate points having abrupt change in gradient All of these 30 meters apart Right angle to the centre line Intermediate points having abrupt change in gradient All of these 30 meters apart ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of 12 mm plastering with cement mortar is 6.0 sq m 4.0 sq m 2.5 sq m 8.0 sq m 6.0 sq m 4.0 sq m 2.5 sq m 8.0 sq m ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The unit of measurement is per quintal for the following: M.S. reinforcement of R.C.C. works Rolling shutters Expanded metal wire netting Collapsible gates with rails M.S. reinforcement of R.C.C. works Rolling shutters Expanded metal wire netting Collapsible gates with rails ANSWER DOWNLOAD EXAMIANS APP