Estimating and Costing The item of steel work which is measured in sq.m, is Rolling shutters Collapsible gates Ventilators and glazing All listed here Rolling shutters Collapsible gates Ventilators and glazing All listed here ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The rate of an item of work depends on Proportion of mortar Specifications of works All of these Specifications of materials Proportion of mortar Specifications of works All of these Specifications of materials ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The item of the brick structure measured in sq.m, is Reinforced brick work Broken glass coping Brick edging Brick work in arches Reinforced brick work Broken glass coping Brick edging Brick work in arches ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn for earth work in excavation in ordinary soil per workman per day is 1.00 cum 4.00 cum 2.00 cum 3.00 cum 1.00 cum 4.00 cum 2.00 cum 3.00 cum ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The correct Prismoidal formula for volume is D [first area + last area + Ʃ Even area + 2 Ʃ odd areas] D/3 [first area + last area + 4 Ʃ Even area + 2 Ʃ odd areas] D/3 [first area + last area + 2 Ʃ Even area + 4 Ʃ odd areas] D/6 [first area + last area + 2 ∑ Even area + 4 ∑ odd areas] D [first area + last area + Ʃ Even area + 2 Ʃ odd areas] D/3 [first area + last area + 4 Ʃ Even area + 2 Ʃ odd areas] D/3 [first area + last area + 2 Ʃ Even area + 4 Ʃ odd areas] D/6 [first area + last area + 2 ∑ Even area + 4 ∑ odd areas] ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The reduced levels of points, 30 metres apart along the longitudinal section of a road portion between chainages 5 and 9 are shown in the given figure. If there is a uniform up-gradient of the road 120 in 1, the chainage of the point with no filling or cutting is (6 + 15) chains None of these (6 + 12) chains (6 + 18) chains (6 + 15) chains None of these (6 + 12) chains (6 + 18) chains ANSWER DOWNLOAD EXAMIANS APP