Estimating and Costing The item of steel work which is measured in sq.m, is Collapsible gates Rolling shutters Ventilators and glazing All listed here Collapsible gates Rolling shutters Ventilators and glazing All listed here ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Pick up the item of work not included in the plinth area estimate Courtyard area W' Area Wall thickness Room area Courtyard area W' Area Wall thickness Room area ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The reduced levels of points, 30 metres apart along the longitudinal section of a road portion between chainages 5 and 9 are shown in the given figure. If there is a uniform up-gradient of the road 120 in 1, the chainage of the point with no filling or cutting is (6 + 12) chains None of these (6 + 15) chains (6 + 18) chains (6 + 12) chains None of these (6 + 15) chains (6 + 18) chains ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Size, capacity and materials need be specified for Ball valves All of these Bib-cocks Stop-cocks Ball valves All of these Bib-cocks Stop-cocks ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing For 100 sq. m cement concrete (1 : 2: 4) 4 cm thick floor, the quantity of cement required, is 0.98 m³ 0.90 m³ 0.94 m³ 1.00 m³ 0.98 m³ 0.90 m³ 0.94 m³ 1.00 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of brick work in cement mortar in foundation and plinth per mason per day, is 1.00 m³ 1.25 m³ 1.75 m³ 1.50 m³ 1.00 m³ 1.25 m³ 1.75 m³ 1.50 m³ ANSWER DOWNLOAD EXAMIANS APP