Estimating and Costing The item of steel work which is measured in sq.m, is All listed here Collapsible gates Ventilators and glazing Rolling shutters All listed here Collapsible gates Ventilators and glazing Rolling shutters ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The slope of the outlet of 'P trap' below the horizontal is kept 10° 12° 8° 14° 10° 12° 8° 14° ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The height of the sink of wash basin above floor level is kept 80 cm 60 cm 70 cm 75 cm to 80 cm 80 cm 60 cm 70 cm 75 cm to 80 cm ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of brick work in cement mortar in foundation and plinth per mason per day, is 1.00 m³ 1.75 m³ 1.50 m³ 1.25 m³ 1.00 m³ 1.75 m³ 1.50 m³ 1.25 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The brick work is measured in sq metre, in case of All of these Honey comb brick work Half brick walls or the partition Brick flat soling All of these Honey comb brick work Half brick walls or the partition Brick flat soling ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing A cement concrete road is 1000 m long, 8 m wide and 15 cm thick over the sub-base of 10 cm thick gravel. The box cutting in road crust is 1000 m3 500 m3 2000 m3 1500 m3 1000 m3 500 m3 2000 m3 1500 m3 ANSWER DOWNLOAD EXAMIANS APP