Estimating and Costing The following item of earth work is not measured separately. Site clearance Setting out of works Steps in deep excavation All listed here Site clearance Setting out of works Steps in deep excavation All listed here ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The assumption on which the trapezoidal formula for volumes is based, is The mid-area of a pyramid is half the average area of the ends The volume of the Prismoidal is over-estimated and hence a Prismoidal correction is applied All listed here The end sections are parallel planes The mid-area of a pyramid is half the average area of the ends The volume of the Prismoidal is over-estimated and hence a Prismoidal correction is applied All listed here The end sections are parallel planes ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The 'centre line method' is specially adopted for estimating All of these Hexagonal buildings Octagonal buildings Circular buildings All of these Hexagonal buildings Octagonal buildings Circular buildings ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The ground surface slopes 1 in 50 along a proposed railway embankment 150 m in length. The height of the embankment at zero chainage is 0.5 m, the width is 11 m and side slopes 2:1. If the falling gradient of the embankment is 1 in 150, the quantity of the earthwork calculated by Prismoidal formula, is 3250 m³ 3225 m³ 3300 m³ 3275 m³ 3250 m³ 3225 m³ 3300 m³ 3275 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The most reliable estimate is Cube rate estimate Plinth area estimate Detailed estimate Preliminary estimate Cube rate estimate Plinth area estimate Detailed estimate Preliminary estimate ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The excavation exceeding 1.5 m in width and 10 sq.m in plan area with a depth not exceeding 30 cm, is termed as Excavation Cutting Surface dressing Surface excavation Excavation Cutting Surface dressing Surface excavation ANSWER DOWNLOAD EXAMIANS APP