Estimating and Costing The following item of earth work is not measured separately. Steps in deep excavation All listed here Site clearance Setting out of works Steps in deep excavation All listed here Site clearance Setting out of works ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing In the mid-section formula The area of mid-sections is calculated by using mean depth The volume of the earth work is calculated by multiplying the mid-section area by the distance between the two original sections The mean depth is the average of depths of two consecutive sections All of these The area of mid-sections is calculated by using mean depth The volume of the earth work is calculated by multiplying the mid-section area by the distance between the two original sections The mean depth is the average of depths of two consecutive sections All of these ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The trap which is provided to disconnect the house drain from the street sewer is called Interception manhole Master trap All listed here Intercepting trap Interception manhole Master trap All listed here Intercepting trap ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing As per Indian Standard Specifications, the peak discharge for domestic purposes per capita per minute, is taken 1.20 liters for 15 users 1.80 liters for 5 to 10 users 1.35 for 20 users All of these 1.20 liters for 15 users 1.80 liters for 5 to 10 users 1.35 for 20 users All of these ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The rate of payment is made for 100 cu m (per % cu m) in case of Rock cutting All of these Earth work in excavation Excavation in trenches for foundation Rock cutting All of these Earth work in excavation Excavation in trenches for foundation ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing If tensile stress of a steel rod of diameter ‘D’ is 1400 kg/cm² and bond stress is 6 kg/cm², the required bond length of the rod is 59 D 30 D 39 D 50 D 59 D 30 D 39 D 50 D ANSWER DOWNLOAD EXAMIANS APP