Estimating and Costing
According to ISI method of measurement, the order of the sequence is

Length, breadth, height
Breadth, length, height
Height, length, breadth
None of these

ANSWER DOWNLOAD EXAMIANS APP

Estimating and Costing
While estimating a reinforced cement structure, the omitted cover of concrete is assumed

In thin slabs, 12 mm minimum or diameter of the bar whichever is more
At the end of reinforcing bar, not less than 25 mm or twice the diameter of the bar
For reinforcing longitudinal bar in a beam 25 mm minimum or diameter of the largest bar which is more
All of these