Estimating and Costing According to ISI method of measurement, the order of the sequence is Breadth, length, height Length, breadth, height None of these Height, length, breadth Breadth, length, height Length, breadth, height None of these Height, length, breadth ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing In long and short wall method of estimation, the length of long wall is the centre to centre distance between the walls and Breadth of the wall Half breadth of wall on each side One fourth breadth of wall on each side None of these Breadth of the wall Half breadth of wall on each side One fourth breadth of wall on each side None of these ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing In case of laying gullies, siphons, intercepting traps, the cost includes Setting and laying Connection to drains Bed concreting All of these Setting and laying Connection to drains Bed concreting All of these ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The area of a sloping surface of a protective embankment of mean height‘d’, side slopes S: 1 and length ‘L’ is d × d × s L.D √(1 + s²) √[d² × (ds)²] 2 L.D √(1 + s²) d × d × s L.D √(1 + s²) √[d² × (ds)²] 2 L.D √(1 + s²) ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Brick walls are measured in sq. m if the thickness of the wall is None of these 15 cm 10 cm 20 cm None of these 15 cm 10 cm 20 cm ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The inspection pit or chamber is a manhole provided in a base drainage system All of these At every change of direction At every 30 m intervals At every change of gradient All of these At every change of direction At every 30 m intervals At every change of gradient ANSWER DOWNLOAD EXAMIANS APP