Estimating and Costing The damp proof course (D.P.C.) is measured in Cub. m Meters None of these Sq. m Cub. m Meters None of these Sq. m ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The brick work is measured in sq metre, in case of Brick flat soling Honey comb brick work All of these Half brick walls or the partition Brick flat soling Honey comb brick work All of these Half brick walls or the partition ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The rate of an item of work depends on Specifications of works All of these Specifications of materials Proportion of mortar Specifications of works All of these Specifications of materials Proportion of mortar ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing If B is the width of formation, d is the height of the embankment, side slope S : 1, for a highway with no transverse slope, the area of cross-section is Bd + Sd2 B × d - Sd1/2 B + d + Sd ½ (Bd + Sd2) Bd + Sd2 B × d - Sd1/2 B + d + Sd ½ (Bd + Sd2) ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The detention period in a septic tank is assumed 40 minutes 25 minutes 20 minutes 30 minutes 40 minutes 25 minutes 20 minutes 30 minutes ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The ground surface slopes 1 in 50 along a proposed railway embankment 150 m in length. The height of the embankment at zero chainage is 0.5 m, the width is 11 m and side slopes 2:1. If the falling gradient of the embankment is 1 in 150, the quantity of the earthwork calculated by Prismoidal formula, is 3300 m³ 3275 m³ 3250 m³ 3225 m³ 3300 m³ 3275 m³ 3250 m³ 3225 m³ ANSWER DOWNLOAD EXAMIANS APP