Estimating and Costing The damp proof course (D.P.C.) is measured in Cub. m Sq. m Meters None of these Cub. m Sq. m Meters None of these ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing For the construction of buildings, the subheads of the estimate are Earthwork, Concrete work, Brick work Brickwork Flooring, Wood work, Steel work Brickwork, Stone work, Roofing All of these Earthwork, Concrete work, Brick work Brickwork Flooring, Wood work, Steel work Brickwork, Stone work, Roofing All of these ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The brick work is measured in sq metre, in case of All of these Honey comb brick work Half brick walls or the partition Brick flat soling All of these Honey comb brick work Half brick walls or the partition Brick flat soling ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The inspection pit or chamber is a manhole provided in a base drainage system All of these At every 30 m intervals At every change of gradient At every change of direction All of these At every 30 m intervals At every change of gradient At every change of direction ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing For 100 sq. m cement concrete (1 : 2: 4) 4 cm thick floor, the quantity of cement required, is 1.00 m³ 0.90 m³ 0.98 m³ 0.94 m³ 1.00 m³ 0.90 m³ 0.98 m³ 0.94 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of brick work in cement mortar in foundation and plinth per mason per day, is 1.00 m³ 1.50 m³ 1.25 m³ 1.75 m³ 1.00 m³ 1.50 m³ 1.25 m³ 1.75 m³ ANSWER DOWNLOAD EXAMIANS APP