Estimating and Costing The damp proof course (D.P.C.) is measured in Cub. m Meters None of these Sq. m Cub. m Meters None of these Sq. m ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of brick work in cement mortar in foundation and plinth per mason per day, is 1.50 m³ 1.25 m³ 1.00 m³ 1.75 m³ 1.50 m³ 1.25 m³ 1.00 m³ 1.75 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The 'centre line method' is specially adopted for estimating Hexagonal buildings All of these Circular buildings Octagonal buildings Hexagonal buildings All of these Circular buildings Octagonal buildings ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The brick work is measured in sq metre, in case of Brick flat soling Honey comb brick work Half brick walls or the partition All of these Brick flat soling Honey comb brick work Half brick walls or the partition All of these ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The item of the brick structure measured in sq.m, is Broken glass coping Reinforced brick work Brick work in arches Brick edging Broken glass coping Reinforced brick work Brick work in arches Brick edging ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Due to change in price level, a revised estimate is prepared if the sanctioned estimate exceeds 0.02 0.025 0.05 0.04 0.02 0.025 0.05 0.04 ANSWER DOWNLOAD EXAMIANS APP