Estimating and Costing The damp proof course (D.P.C.) is measured in None of these Cub. m Meters Sq. m None of these Cub. m Meters Sq. m ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing If the formation level of a highway has a uniform gradient for a particular length, and the ground is also having a longitudinal slope, the earthwork may be calculated by Trapezoidal formula All of these Prismoidal formula Mid-section formula Trapezoidal formula All of these Prismoidal formula Mid-section formula ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of brick work in cement mortar in foundation and plinth per mason per day, is 1.25 m³ 1.50 m³ 1.75 m³ 1.00 m³ 1.25 m³ 1.50 m³ 1.75 m³ 1.00 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Pick up the item of work not included in the plinth area estimate Courtyard area Wall thickness W' Area Room area Courtyard area Wall thickness W' Area Room area ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing If B is the width of formation, d is the height of the embankment, side slope S : 1, for a highway with no transverse slope, the area of cross-section is B + d + Sd ½ (Bd + Sd2) Bd + Sd2 B × d - Sd1/2 B + d + Sd ½ (Bd + Sd2) Bd + Sd2 B × d - Sd1/2 ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing According to ISI method of measurement, the order of the sequence is None of these Breadth, length, height Height, length, breadth Length, breadth, height None of these Breadth, length, height Height, length, breadth Length, breadth, height ANSWER DOWNLOAD EXAMIANS APP