Estimating and Costing The damp proof course (D.P.C.) is measured in Meters Cub. m Sq. m None of these Meters Cub. m Sq. m None of these ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing While preparing a detailed estimate Volume should be measured correct to 0.01 cum Dimension should be measured correct to 0.01 m All of these Area should be measured correct to 0.01 sqm Volume should be measured correct to 0.01 cum Dimension should be measured correct to 0.01 m All of these Area should be measured correct to 0.01 sqm ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing For 12 mm thick cement plastering 1 : 6 on 100 sq.m new brick work, the quantity of cement required, is 0.274 m³ 0.200 m³ 0.295 m³ 0.247 m³ 0.274 m³ 0.200 m³ 0.295 m³ 0.247 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn for earth work in excavation in ordinary soil per workman per day is 3.00 cum 2.00 cum 1.00 cum 4.00 cum 3.00 cum 2.00 cum 1.00 cum 4.00 cum ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The minimum width of a septic tank is taken 75 cm 70 cm 90 cm 80 cm 75 cm 70 cm 90 cm 80 cm ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The following item of earth work is not measured separately. All listed here Site clearance Setting out of works Steps in deep excavation All listed here Site clearance Setting out of works Steps in deep excavation ANSWER DOWNLOAD EXAMIANS APP