Estimating and Costing The damp proof course (D.P.C.) is measured in Sq. m Meters Cub. m None of these Sq. m Meters Cub. m None of these ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing According to Indian Standards Institute, the actual size of modular bricks is 19 cm x 9 cm x 9 cm 23 cm x 11.5 cm x 7.5 cm 20 cm x 10 cm x 10 cm 25 cm x 13 cm x 7.5 cm 19 cm x 9 cm x 9 cm 23 cm x 11.5 cm x 7.5 cm 20 cm x 10 cm x 10 cm 25 cm x 13 cm x 7.5 cm ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of brick work in cement mortar in foundation and plinth per mason per day, is 1.50 m³ 1.25 m³ 1.75 m³ 1.00 m³ 1.50 m³ 1.25 m³ 1.75 m³ 1.00 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing For 12 mm thick cement plastering 1 : 6 on 100 sq.m new brick work, the quantity of cement required, is 0.200 m³ 0.247 m³ 0.274 m³ 0.295 m³ 0.200 m³ 0.247 m³ 0.274 m³ 0.295 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The inspection pit or chamber is a manhole provided in a base drainage system At every 30 m intervals All of these At every change of gradient At every change of direction At every 30 m intervals All of these At every change of gradient At every change of direction ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing In the mid-section formula The mean depth is the average of depths of two consecutive sections The area of mid-sections is calculated by using mean depth The volume of the earth work is calculated by multiplying the mid-section area by the distance between the two original sections All of these The mean depth is the average of depths of two consecutive sections The area of mid-sections is calculated by using mean depth The volume of the earth work is calculated by multiplying the mid-section area by the distance between the two original sections All of these ANSWER DOWNLOAD EXAMIANS APP