Estimating and Costing The damp proof course (D.P.C.) is measured in Meters Sq. m None of these Cub. m Meters Sq. m None of these Cub. m ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing For 12 mm thick cement plastering 1 : 6 on 100 sq.m new brick work, the quantity of cement required, is 0.295 m³ 0.247 m³ 0.200 m³ 0.274 m³ 0.295 m³ 0.247 m³ 0.200 m³ 0.274 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of cement concrete 1 : 2 : 4 per mason per day is 5.0 m³ 1.5 m³ 2.5 m³ 3.5 m³ 5.0 m³ 1.5 m³ 2.5 m³ 3.5 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The 'centre line method' is specially adopted for estimating Octagonal buildings All of these Circular buildings Hexagonal buildings Octagonal buildings All of these Circular buildings Hexagonal buildings ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of brick work in cement mortar in foundation and plinth per mason per day, is 1.75 m³ 1.00 m³ 1.50 m³ 1.25 m³ 1.75 m³ 1.00 m³ 1.50 m³ 1.25 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing In the mid-section formula All of these The area of mid-sections is calculated by using mean depth The mean depth is the average of depths of two consecutive sections The volume of the earth work is calculated by multiplying the mid-section area by the distance between the two original sections All of these The area of mid-sections is calculated by using mean depth The mean depth is the average of depths of two consecutive sections The volume of the earth work is calculated by multiplying the mid-section area by the distance between the two original sections ANSWER DOWNLOAD EXAMIANS APP