Estimating and Costing The damp proof course (D.P.C.) is measured in Meters Sq. m None of these Cub. m Meters Sq. m None of these Cub. m ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing According to ISI method of measurement, the order of the sequence is Length, breadth, height None of these Height, length, breadth Breadth, length, height Length, breadth, height None of these Height, length, breadth Breadth, length, height ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The measurement is made for stone work in square metre in case of Columns, lintels, copings Building work Wall facing (A) and (B) of the above Columns, lintels, copings Building work Wall facing (A) and (B) of the above ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing For 12 mm thick cement plastering 1 : 6 on 100 sq.m new brick work, the quantity of cement required, is 0.274 m³ 0.200 m³ 0.247 m³ 0.295 m³ 0.274 m³ 0.200 m³ 0.247 m³ 0.295 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The diameter of a domestic sewer pipe laid at gradient 1 in 100 is recommended 150 mm 175 mm 100 mm 200 mm 150 mm 175 mm 100 mm 200 mm ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn for earth work in excavation in ordinary soil per workman per day is 3.00 cum 1.00 cum 4.00 cum 2.00 cum 3.00 cum 1.00 cum 4.00 cum 2.00 cum ANSWER DOWNLOAD EXAMIANS APP