Estimating and Costing For 100 sq. m cement concrete (1 : 2: 4) 4 cm thick floor, the quantity of cement required, is 1.00 m³ 0.90 m³ 0.98 m³ 0.94 m³ 1.00 m³ 0.90 m³ 0.98 m³ 0.94 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing A portion of an embankment having a uniform up-gradient 1 in 500 is circular with radius 1000 m of the centre line. It subtends 180° at the centre. If the height of the bank is 1 m at the lower end, and side slopes 2:1, the earth work involved. 27,000 m³ 26,500 m³ 27,500 m³ 26,000 m³ 27,000 m³ 26,500 m³ 27,500 m³ 26,000 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The weight of an item is measured correct to nearest 0.75 kg 1.00 kg 0.25 kg 0.50 kg 0.75 kg 1.00 kg 0.25 kg 0.50 kg ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of cement concrete 1 : 2 : 4 per mason per day is 5.0 m³ 3.5 m³ 1.5 m³ 2.5 m³ 5.0 m³ 3.5 m³ 1.5 m³ 2.5 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing While estimating a reinforced cement structure, the omitted cover of concrete is assumed At the end of reinforcing bar, not less than 25 mm or twice the diameter of the bar All of these In thin slabs, 12 mm minimum or diameter of the bar whichever is more For reinforcing longitudinal bar in a beam 25 mm minimum or diameter of the largest bar which is more At the end of reinforcing bar, not less than 25 mm or twice the diameter of the bar All of these In thin slabs, 12 mm minimum or diameter of the bar whichever is more For reinforcing longitudinal bar in a beam 25 mm minimum or diameter of the largest bar which is more ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Carpet area does not include the area of Kitchen and pantry Bath room and lavatory The walls along with doors and other openings All of these Kitchen and pantry Bath room and lavatory The walls along with doors and other openings All of these ANSWER DOWNLOAD EXAMIANS APP