Estimating and Costing For 100 sq. m cement concrete (1 : 2: 4) 4 cm thick floor, the quantity of cement required, is 0.94 m³ 1.00 m³ 0.98 m³ 0.90 m³ 0.94 m³ 1.00 m³ 0.98 m³ 0.90 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing In the mid-section formula The mean depth is the average of depths of two consecutive sections All of these The volume of the earth work is calculated by multiplying the mid-section area by the distance between the two original sections The area of mid-sections is calculated by using mean depth The mean depth is the average of depths of two consecutive sections All of these The volume of the earth work is calculated by multiplying the mid-section area by the distance between the two original sections The area of mid-sections is calculated by using mean depth ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing A cement concrete road is 1000 m long, 8 m wide and 15 cm thick over the sub-base of 10 cm thick gravel. The box cutting in road crust is 1000 m3 1500 m3 2000 m3 500 m3 1000 m3 1500 m3 2000 m3 500 m3 ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Carpet area does not include the area of Kitchen and pantry The walls along with doors and other openings All of these Bath room and lavatory Kitchen and pantry The walls along with doors and other openings All of these Bath room and lavatory ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The cross-section of a road partly in banking and partly in cutting is shown in the given figure. The area of the shaded portion is ½ × (b + rd)²/(r - s) ⅓ × (b - rd)²/(r + s) ⅓ × (b - rd)²/(r - s) ⅓ × (b - rd)²/(s - r) ½ × (b + rd)²/(r - s) ⅓ × (b - rd)²/(r + s) ⅓ × (b - rd)²/(r - s) ⅓ × (b - rd)²/(s - r) ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The trap which is provided to disconnect the house drain from the street sewer is called Intercepting trap Interception manhole Master trap All listed here Intercepting trap Interception manhole Master trap All listed here ANSWER DOWNLOAD EXAMIANS APP