Estimating and Costing For 100 sq. m cement concrete (1 : 2: 4) 4 cm thick floor, the quantity of cement required, is 0.98 m³ 0.90 m³ 1.00 m³ 0.94 m³ 0.98 m³ 0.90 m³ 1.00 m³ 0.94 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing If tensile stress of a steel rod of diameter ‘D’ is 1400 kg/cm² and bond stress is 6 kg/cm², the required bond length of the rod is 50 D 30 D 59 D 39 D 50 D 30 D 59 D 39 D ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The inspection pit or chamber is a manhole provided in a base drainage system At every change of direction All of these At every change of gradient At every 30 m intervals At every change of direction All of these At every change of gradient At every 30 m intervals ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The order of booking dimensions is Breadth, length, height Height, breadth, length Length, breadth, height None of these Breadth, length, height Height, breadth, length Length, breadth, height None of these ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn for earth work in excavation in ordinary soil per workman per day is 4.00 cum 1.00 cum 3.00 cum 2.00 cum 4.00 cum 1.00 cum 3.00 cum 2.00 cum ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The rate of payment is made for 100 cu m (per % cu m) in case of Excavation in trenches for foundation All of these Earth work in excavation Rock cutting Excavation in trenches for foundation All of these Earth work in excavation Rock cutting ANSWER DOWNLOAD EXAMIANS APP