For 100 sq. m cement concrete (1 : 2: 4) 4 cm thick floor, the quantity of cement required, is

0.90 m³
0.98 m³
0.94 m³
1.00 m³

ANSWER DOWNLOAD EXAMIANS APP

Estimating and Costing
In case of laying gullies, siphons, intercepting traps, the cost includes

Connection to drains
Setting and laying
Bed concreting
All of these

ANSWER DOWNLOAD EXAMIANS APP

Estimating and Costing
Anti-siphonage pipe is connected to

Bottom of P trap W.C.
Top of P trap W.C.
Side of water closet
Main soil pipe

ANSWER DOWNLOAD EXAMIANS APP

Estimating and Costing
The measurement is not made in square meters in case of

Concrete Jeffries
R.C. Chhajja
P.C. (Damp proof course)
Form works

ANSWER DOWNLOAD EXAMIANS APP

Estimating and Costing
Due to change in price level, a revised estimate is prepared if the sanctioned estimate exceeds

0.04
0.025
0.05
0.02

ANSWER DOWNLOAD EXAMIANS APP

Estimating and Costing
The item of the brick structure measured in sq.m, is

Brick edging
Broken glass coping
Brick work in arches
Reinforced brick work

ANSWER DOWNLOAD EXAMIANS APP
MORE MCQ ON Estimating and Costing

DOWNLOAD APP

  • APPLE
    from app store
  • ANDROID
    from play store

SEARCH

LOGIN HERE


  • GOOGLE

FIND US

  • 1.70K
    FOLLOW US
  • EXAMIANSSTUDY FOR YOUR DREAMS.
  • SUPPORT :SUPPORT EMAIL ACCOUNT : examians@yahoo.com

OTHER WEBSITES

  • GUJARATI MCQ
  • ACCOUNTIANS

QUICK LINKS

  • HOME
  • QUIZ
  • PRIVACY POLICY
  • DISCLAIMER
  • TERMS & CONDITIONS
  • CONTACT US
↑