Estimating and Costing For 100 sq. m cement concrete (1 : 2: 4) 4 cm thick floor, the quantity of cement required, is 1.00 m³ 0.98 m³ 0.94 m³ 0.90 m³ 1.00 m³ 0.98 m³ 0.94 m³ 0.90 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of half brick partition wall per mason per day is 2.0 m2 1.5 m2 5.0 m2 4.0 m2 2.0 m2 1.5 m2 5.0 m2 4.0 m2 ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Pick up the item whose weight is added to the weight of respective item, is Cleats All listed here Bolts Brackets Cleats All listed here Bolts Brackets ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The floor area includes the area of the balcony up to 0.75 0.5 1 0.25 0.75 0.5 1 0.25 ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Referring of given figure, pick up the correct statement from the following: Length of long wall out-to-out is 6.80 m The total length of centre line of four walls is 20 m Length of short walls in-to-in is 3.20 m All listed here Length of long wall out-to-out is 6.80 m The total length of centre line of four walls is 20 m Length of short walls in-to-in is 3.20 m All listed here ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Due to change in price level, a revised estimate is prepared if the sanctioned estimate exceeds 0.05 0.02 0.04 0.025 0.05 0.02 0.04 0.025 ANSWER DOWNLOAD EXAMIANS APP