Estimating and Costing For 100 sq. m cement concrete (1 : 2: 4) 4 cm thick floor, the quantity of cement required, is 1.00 m³ 0.90 m³ 0.94 m³ 0.98 m³ 1.00 m³ 0.90 m³ 0.94 m³ 0.98 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of half brick partition wall per mason per day is 5.0 m2 2.0 m2 4.0 m2 1.5 m2 5.0 m2 2.0 m2 4.0 m2 1.5 m2 ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The item of steel work which is measured in sq.m, is Collapsible gates All listed here Ventilators and glazing Rolling shutters Collapsible gates All listed here Ventilators and glazing Rolling shutters ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing If tensile stress of a steel rod of diameter ‘D’ is 1400 kg/cm² and bond stress is 6 kg/cm², the required bond length of the rod is 30 D 50 D 59 D 39 D 30 D 50 D 59 D 39 D ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The area of a sloping surface of a protective embankment of mean height‘d’, side slopes S: 1 and length ‘L’ is 2 L.D √(1 + s²) √[d² × (ds)²] L.D √(1 + s²) d × d × s 2 L.D √(1 + s²) √[d² × (ds)²] L.D √(1 + s²) d × d × s ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing If B is the width of formation, d is the height of the embankment, side slope S : 1, for a highway with no transverse slope, the area of cross-section is ½ (Bd + Sd2) Bd + Sd2 B × d - Sd1/2 B + d + Sd ½ (Bd + Sd2) Bd + Sd2 B × d - Sd1/2 B + d + Sd ANSWER DOWNLOAD EXAMIANS APP