Estimating and Costing For 100 sq. m cement concrete (1 : 2: 4) 4 cm thick floor, the quantity of cement required, is 0.98 m³ 0.90 m³ 0.94 m³ 1.00 m³ 0.98 m³ 0.90 m³ 0.94 m³ 1.00 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The assumption on which the trapezoidal formula for volumes is based, is The end sections are parallel planes All listed here The mid-area of a pyramid is half the average area of the ends The volume of the Prismoidal is over-estimated and hence a Prismoidal correction is applied The end sections are parallel planes All listed here The mid-area of a pyramid is half the average area of the ends The volume of the Prismoidal is over-estimated and hence a Prismoidal correction is applied ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn for earth work in excavation in ordinary soil per workman per day is 4.00 cum 3.00 cum 1.00 cum 2.00 cum 4.00 cum 3.00 cum 1.00 cum 2.00 cum ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing While preparing a detailed estimate Volume should be measured correct to 0.01 cum All of these Area should be measured correct to 0.01 sqm Dimension should be measured correct to 0.01 m Volume should be measured correct to 0.01 cum All of these Area should be measured correct to 0.01 sqm Dimension should be measured correct to 0.01 m ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The order of booking dimensions is Length, breadth, height Breadth, length, height Height, breadth, length None of these Length, breadth, height Breadth, length, height Height, breadth, length None of these ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The damp proof course (D.P.C.) is measured in Cub. m None of these Meters Sq. m Cub. m None of these Meters Sq. m ANSWER DOWNLOAD EXAMIANS APP