Estimating and Costing For 100 sq. m cement concrete (1 : 2: 4) 4 cm thick floor, the quantity of cement required, is 0.94 m³ 0.98 m³ 1.00 m³ 0.90 m³ 0.94 m³ 0.98 m³ 1.00 m³ 0.90 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of half brick partition wall per mason per day is 1.5 m2 4.0 m2 2.0 m2 5.0 m2 1.5 m2 4.0 m2 2.0 m2 5.0 m2 ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of 12 mm plastering with cement mortar is 6.0 sq m 2.5 sq m 8.0 sq m 4.0 sq m 6.0 sq m 2.5 sq m 8.0 sq m 4.0 sq m ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing While preparing a detailed estimate All of these Volume should be measured correct to 0.01 cum Dimension should be measured correct to 0.01 m Area should be measured correct to 0.01 sqm All of these Volume should be measured correct to 0.01 cum Dimension should be measured correct to 0.01 m Area should be measured correct to 0.01 sqm ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The measurement is not made in square meters in case of Concrete Jeffries P.C. (Damp proof course) Form works R.C. Chhajja Concrete Jeffries P.C. (Damp proof course) Form works R.C. Chhajja ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Brick walls are measured in sq. m if the thickness of the wall is 15 cm None of these 20 cm 10 cm 15 cm None of these 20 cm 10 cm ANSWER DOWNLOAD EXAMIANS APP