Estimating and Costing

Estimating and Costing
For 100 sq. m cement concrete (1 : 2: 4) 4 cm thick floor, the quantity of cement required, is

0.90 m³
0.98 m³
1.00 m³
0.94 m³

ANSWER DOWNLOAD EXAMIANS APP

Estimating and Costing
The detention period in a septic tank is assumed

25 minutes
20 minutes
30 minutes
40 minutes

ANSWER DOWNLOAD EXAMIANS APP

Estimating and Costing
The height of the sink of wash basin above floor level is kept

80 cm
60 cm
70 cm
75 cm to 80 cm

ANSWER DOWNLOAD EXAMIANS APP

Estimating and Costing
Cost of fittings and their fixing is specified for the following sanitary fittings

Water closets
Flushing pipes
Lavatory basins
All listed here

ANSWER DOWNLOAD EXAMIANS APP

Estimating and Costing
The 'centre line method' is specially adopted for estimating

Hexagonal buildings
Octagonal buildings
All of these
Circular buildings

ANSWER DOWNLOAD EXAMIANS APP

Estimating and Costing
The measurement is made in square metre in case of

None of these
Cement concrete in foundation
R.C.C. structure
Hollow concrete block wall

ANSWER DOWNLOAD EXAMIANS APP
MORE MCQ ON Estimating and Costing

DOWNLOAD APP

  • APPLE
    from app store
  • ANDROID
    from play store

SEARCH

LOGIN HERE


  • GOOGLE

FIND US

  • 1.70K
    FOLLOW US
  • EXAMIANSSTUDY FOR YOUR DREAMS.
  • SUPPORT :SUPPORT EMAIL ACCOUNT : examians@yahoo.com

OTHER WEBSITES

  • GUJARATI MCQ
  • ACCOUNTIANS

QUICK LINKS

  • HOME
  • QUIZ
  • PRIVACY POLICY
  • DISCLAIMER
  • TERMS & CONDITIONS
  • CONTACT US
↑