Estimating and Costing For 100 sq. m cement concrete (1 : 2: 4) 4 cm thick floor, the quantity of cement required, is 0.98 m³ 0.90 m³ 1.00 m³ 0.94 m³ 0.98 m³ 0.90 m³ 1.00 m³ 0.94 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing If the formation level of a highway has a uniform gradient for a particular length, and the ground is also having a longitudinal slope, the earthwork may be calculated by Prismoidal formula Trapezoidal formula All of these Mid-section formula Prismoidal formula Trapezoidal formula All of these Mid-section formula ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of cement concrete 1 : 2 : 4 per mason per day is 1.5 m³ 5.0 m³ 2.5 m³ 3.5 m³ 1.5 m³ 5.0 m³ 2.5 m³ 3.5 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing In long and short wall method of estimation, the length of long wall is the centre to centre distance between the walls and Half breadth of wall on each side Breadth of the wall One fourth breadth of wall on each side None of these Half breadth of wall on each side Breadth of the wall One fourth breadth of wall on each side None of these ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The reduced levels of points, 30 metres apart along the longitudinal section of a road portion between chainages 5 and 9 are shown in the given figure. If there is a uniform up-gradient of the road 120 in 1, the chainage of the point with no filling or cutting is None of these (6 + 15) chains (6 + 12) chains (6 + 18) chains None of these (6 + 15) chains (6 + 12) chains (6 + 18) chains ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The weight of an item is measured correct to nearest 0.25 kg 1.00 kg 0.50 kg 0.75 kg 0.25 kg 1.00 kg 0.50 kg 0.75 kg ANSWER DOWNLOAD EXAMIANS APP