Estimating and Costing While preparing a detailed estimate Dimension should be measured correct to 0.01 m Area should be measured correct to 0.01 sqm All of these Volume should be measured correct to 0.01 cum Dimension should be measured correct to 0.01 m Area should be measured correct to 0.01 sqm All of these Volume should be measured correct to 0.01 cum ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing For the construction of buildings, the subheads of the estimate are All of these Brickwork Flooring, Wood work, Steel work Brickwork, Stone work, Roofing Earthwork, Concrete work, Brick work All of these Brickwork Flooring, Wood work, Steel work Brickwork, Stone work, Roofing Earthwork, Concrete work, Brick work ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The excavation exceeding 1.5 m in width and 10 sq.m in plan area with a depth not exceeding 30 cm, is termed as Excavation Surface excavation Surface dressing Cutting Excavation Surface excavation Surface dressing Cutting ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of 2.5 cm cement concrete floor per mansion per day 10 sqm 5.0 sqm 7.5 sqm 2.5 sqm 10 sqm 5.0 sqm 7.5 sqm 2.5 sqm ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The cross-sections for a highway is taken at 30 meters apart Intermediate points having abrupt change in gradient All of these Right angle to the centre line 30 meters apart Intermediate points having abrupt change in gradient All of these Right angle to the centre line ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing For 100 sq. m cement concrete (1 : 2: 4) 4 cm thick floor, the quantity of cement required, is 1.00 m³ 0.94 m³ 0.98 m³ 0.90 m³ 1.00 m³ 0.94 m³ 0.98 m³ 0.90 m³ ANSWER DOWNLOAD EXAMIANS APP