Estimating and Costing While preparing a detailed estimate Volume should be measured correct to 0.01 cum All of these Dimension should be measured correct to 0.01 m Area should be measured correct to 0.01 sqm Volume should be measured correct to 0.01 cum All of these Dimension should be measured correct to 0.01 m Area should be measured correct to 0.01 sqm ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing While estimating the qualities for the construction of a building, the correct metric unit is Cubic metre for area Meter for length Square meters for volume Liter for capacity Cubic metre for area Meter for length Square meters for volume Liter for capacity ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The rate of an item of work depends on Specifications of materials Proportion of mortar Specifications of works All of these Specifications of materials Proportion of mortar Specifications of works All of these ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The plinth area of a building not includes Internal shaft for sanitary installations up to 2 sq m. in area Lift and wall including landing Area of the walls at the floor level Area of cantilevered porch Internal shaft for sanitary installations up to 2 sq m. in area Lift and wall including landing Area of the walls at the floor level Area of cantilevered porch ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Anti-siphonage pipe is connected to Side of water closet Main soil pipe Bottom of P trap W.C. Top of P trap W.C. Side of water closet Main soil pipe Bottom of P trap W.C. Top of P trap W.C. ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Berms are provided in canals if these are All of these Fully in embankment Partly in excavation and partly in embankment Fully in excavation All of these Fully in embankment Partly in excavation and partly in embankment Fully in excavation ANSWER DOWNLOAD EXAMIANS APP