Estimating and Costing Pick up the incorrect statement regarding a master trap from the following: The mica flap valve which opens inwards only, is fitted at the top of the inlet pipe The water seal is less than that of ordinary traps It is provided in between the lower end of the house drain and the street sewer It is provided a cleaning eye at the top of the trap The mica flap valve which opens inwards only, is fitted at the top of the inlet pipe The water seal is less than that of ordinary traps It is provided in between the lower end of the house drain and the street sewer It is provided a cleaning eye at the top of the trap ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The total length of a cranked bar through a distance (d) at 45° in case of a beam of effective length L, is L + 0.42 d L - (2 × 0.4 d) L - (0.42 d) L + (2 × 0.42 d) L + 0.42 d L - (2 × 0.4 d) L - (0.42 d) L + (2 × 0.42 d) ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Pick up the correct statement regarding the centre line method of estimating a building The centre line length is reduced by half the layer of main wall joining the partition wall The centre line is worked out separately for different sections of walls of a building All of these Product of the centre line of the walls and area of cross-section of any item, gives total quantity of the item The centre line length is reduced by half the layer of main wall joining the partition wall The centre line is worked out separately for different sections of walls of a building All of these Product of the centre line of the walls and area of cross-section of any item, gives total quantity of the item ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of half brick partition wall per mason per day is 5.0 m2 1.5 m2 4.0 m2 2.0 m2 5.0 m2 1.5 m2 4.0 m2 2.0 m2 ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The measurement is not made in square meters in case of R.C. Chhajja Form works P.C. (Damp proof course) Concrete Jeffries R.C. Chhajja Form works P.C. (Damp proof course) Concrete Jeffries ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Due to change in price level, a revised estimate is prepared if the sanctioned estimate exceeds 0.04 0.02 0.025 0.05 0.04 0.02 0.025 0.05 ANSWER DOWNLOAD EXAMIANS APP