Estimating and Costing If tensile stress of a steel rod of diameter ‘D’ is 1400 kg/cm² and bond stress is 6 kg/cm², the required bond length of the rod is 39 D 30 D 59 D 50 D 39 D 30 D 59 D 50 D ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Pick up the item of work not included in the plinth area estimate Room area Wall thickness W' Area Courtyard area Room area Wall thickness W' Area Courtyard area ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The height of the sink of wash basin above floor level is kept 70 cm 80 cm 60 cm 75 cm to 80 cm 70 cm 80 cm 60 cm 75 cm to 80 cm ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The item of the brick structure measured in sq.m, is Broken glass coping Reinforced brick work Brick work in arches Brick edging Broken glass coping Reinforced brick work Brick work in arches Brick edging ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The main factor to be considered while preparing a detailed estimate, is Quantity of the materials All of these Availability of materials Transportation of materials Quantity of the materials All of these Availability of materials Transportation of materials ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The measurement is not made in square meters in case of P.C. (Damp proof course) Form works Concrete Jeffries R.C. Chhajja P.C. (Damp proof course) Form works Concrete Jeffries R.C. Chhajja ANSWER DOWNLOAD EXAMIANS APP