Estimating and Costing If tensile stress of a steel rod of diameter ‘D’ is 1400 kg/cm² and bond stress is 6 kg/cm², the required bond length of the rod is 39 D 59 D 50 D 30 D 39 D 59 D 50 D 30 D ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The following item of earth work is not measured separately. Setting out of works Site clearance Steps in deep excavation All listed here Setting out of works Site clearance Steps in deep excavation All listed here ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The area is measured correct to the nearest 0.03 sqm 0.04 sqm 0.02 sqm 0.01 sqm 0.03 sqm 0.04 sqm 0.02 sqm 0.01 sqm ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Referring of given figure, pick up the correct statement from the following: Length of long wall out-to-out is 6.80 m Length of short walls in-to-in is 3.20 m The total length of centre line of four walls is 20 m All listed here Length of long wall out-to-out is 6.80 m Length of short walls in-to-in is 3.20 m The total length of centre line of four walls is 20 m All listed here ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The 'centre line method' is specially adopted for estimating Hexagonal buildings Octagonal buildings All of these Circular buildings Hexagonal buildings Octagonal buildings All of these Circular buildings ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn for earth work in excavation in ordinary soil per workman per day is 1.00 cum 2.00 cum 3.00 cum 4.00 cum 1.00 cum 2.00 cum 3.00 cum 4.00 cum ANSWER DOWNLOAD EXAMIANS APP