Estimating and Costing If tensile stress of a steel rod of diameter ‘D’ is 1400 kg/cm² and bond stress is 6 kg/cm², the required bond length of the rod is 59 D 50 D 30 D 39 D 59 D 50 D 30 D 39 D ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of 12 mm plastering with cement mortar is 8.0 sq m 2.5 sq m 4.0 sq m 6.0 sq m 8.0 sq m 2.5 sq m 4.0 sq m 6.0 sq m ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The 'centre line method' is specially adopted for estimating Circular buildings All of these Octagonal buildings Hexagonal buildings Circular buildings All of these Octagonal buildings Hexagonal buildings ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The main factor to be considered while preparing a detailed estimate, is Quantity of the materials All of these Transportation of materials Availability of materials Quantity of the materials All of these Transportation of materials Availability of materials ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Anti-siphonage pipe is connected to Main soil pipe Side of water closet Top of P trap W.C. Bottom of P trap W.C. Main soil pipe Side of water closet Top of P trap W.C. Bottom of P trap W.C. ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing While preparing a detailed estimate Volume should be measured correct to 0.01 cum All of these Area should be measured correct to 0.01 sqm Dimension should be measured correct to 0.01 m Volume should be measured correct to 0.01 cum All of these Area should be measured correct to 0.01 sqm Dimension should be measured correct to 0.01 m ANSWER DOWNLOAD EXAMIANS APP