Estimating and Costing Anti-siphonage pipe is connected to Side of water closet Bottom of P trap W.C. Top of P trap W.C. Main soil pipe Side of water closet Bottom of P trap W.C. Top of P trap W.C. Main soil pipe ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Pick up the incorrect statement regarding a master trap from the following: It is provided a cleaning eye at the top of the trap The mica flap valve which opens inwards only, is fitted at the top of the inlet pipe The water seal is less than that of ordinary traps It is provided in between the lower end of the house drain and the street sewer It is provided a cleaning eye at the top of the trap The mica flap valve which opens inwards only, is fitted at the top of the inlet pipe The water seal is less than that of ordinary traps It is provided in between the lower end of the house drain and the street sewer ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of 2.5 cm cement concrete floor per mansion per day 2.5 sqm 7.5 sqm 5.0 sqm 10 sqm 2.5 sqm 7.5 sqm 5.0 sqm 10 sqm ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Pick up the excavation where measurements are made in square meters for payment. Both (B) and (C) Surface dressing up to 15 cm depths Surface excavation up to 30 cm depths Ordinary cuttings up to 1 m Both (B) and (C) Surface dressing up to 15 cm depths Surface excavation up to 30 cm depths Ordinary cuttings up to 1 m ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The damp proof course (D.P.C.) is measured in Sq. m None of these Meters Cub. m Sq. m None of these Meters Cub. m ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing In case of laying gullies, siphons, intercepting traps, the cost includes Setting and laying Connection to drains Bed concreting All of these Setting and laying Connection to drains Bed concreting All of these ANSWER DOWNLOAD EXAMIANS APP